The Prompt Payment Act (31 U.S.C. 3901–3907) requires federal agencies to pay contractors on time and to pay interest, without being asked, when they don’t. For most invoices, payment is due 30 days after the designated billing office receives a proper invoice, or 30 days after the government accepts the supplies or services, whichever is later (FAR 32.904). Late payments earn interest at a rate the Treasury Department sets every six months: 4.75% a year for July 1 to December 31, 2026 (Bureau of the Fiscal Service).
When payment is due
| Payment | Due date |
|---|---|
| Invoice for supplies or services | The later of 30 days after the billing office receives a proper invoice and 30 days after the government accepts the work |
| Payment that needs no invoice, such as a lease payment | The date the contract sets |
| Construction progress payment | 14 days after the billing office receives a proper payment request, unless the contract allows longer for inspection |
| Construction retainage | The date the contract sets, or 30 days after the contracting officer approves its release |
| Final payment on construction | The later of 30 days after a proper invoice and 30 days after acceptance |
Source: FAR 32.904. Food and other perishables have shorter deadlines.
Two rules work in your favor:
- Acceptance can’t drag on forever. For computing interest, the government is deemed to accept supplies or services 7 days after you deliver or perform, unless there’s a disagreement over quantity, quality or compliance. A contract for other than commercial products or services can set a longer period for inspection and testing.
- A lost receipt date counts from your invoice. If the billing office doesn’t mark the date it received your invoice, the due date is the 30th day after the date on the invoice.
What makes an invoice proper
The clock starts only when the billing office has a proper invoice. Under the Prompt Payment clause, it must include (FAR 52.232-25):
- Your name and address.
- The invoice date and invoice number.
- The contract number, with the order and line item numbers.
- A description, quantity, unit of measure, unit price and extended price of what you delivered or performed.
- Shipping and payment terms, such as the shipment number and date and any prompt payment discount.
- The name and address of the official payment goes to, matching the contract or a proper notice of assignment.
- The name, title, phone number and mailing address of the person to contact if the invoice is defective.
- Your Taxpayer Identification Number, if the contract requires it on invoices.
- Electronic funds transfer banking information, if the contract requires it on invoices. If not, the banking information in your registration must be correct for the invoice to be proper (SAM.gov registration).
- Anything else the contract requires, such as proof of shipment.
If an invoice is defective, the billing office must return it within 7 days after receipt and say why. Fix it and send it again: the new 30 days count from the corrected invoice.
Interest on late payments
- It’s automatic. The payment office pays interest without a request when the billing office had a proper invoice, the government documented acceptance without a dispute, and payment came after the due date (FAR 32.907).
- The rate. The rate in effect on the day after the due date applies, and Treasury publishes a new rate every January and July. Interest runs through the payment date on a 360-day year. For up to one year, unpaid interest is added to the principal every 30 days; it stops after a year, or once you file a claim for it under the Contract Disputes Act. Interest under $1 isn’t paid (5 CFR 1315.10).
- An example. A $100,000 invoice paid 30 days late at 4.75% earns $100,000 × 4.75% × 30/360 = $395.83.
- Wrong bank details pause it. If your banking information is wrong, interest starts only 7 days after the agency receives the correct information.
- If the agency skips the interest. When you’re owed $1 or more in interest and the agency doesn’t pay it within 10 days after paying the invoice, you can demand an additional penalty. Send a written demand within 40 days after the payment: name the invoice, ask for the overdue interest and the additional penalty, attach a copy of the invoice, and state that you received the principal and when. The additional penalty equals the interest owed, at least $25 and at most $5,000 (5 CFR 1315.11).
- Discounts taken late. If the government takes a prompt payment discount after the discount period, it owes interest on the discount amount.
Faster payment for small businesses
When the contract doesn’t set a payment date, agencies aim to pay small business contractors within 15 days after receiving a proper invoice and all other required documents. The same goal applies to a prime contractor that agrees to pay its small business subcontractors within 15 days of receiving the accelerated payment. It’s a goal, not a right: it creates no new rights under the Prompt Payment Act, and interest still counts from the regular due date (FAR 32.009-1).
Subcontractors
- Construction: 7 days. On a federal construction contract, the prime must pay a subcontractor for satisfactory work within 7 days after the government pays the prime for it, and owes the subcontractor interest at the Prompt Payment rate if it’s late. Each subcontractor must pass the same terms down to its own subcontractors and suppliers (FAR 52.232-27).
- What the prime can still hold back. A subcontract can allow retainage. A prime can also withhold payment for deficient work without owing interest, if it gives the subcontractor written notice of the withholding and sends a copy to the contracting officer. Once the deficiency is corrected, the prime pays within 7 days, or owes interest.
- Other contracts: pass on accelerated payments. A prime that receives accelerated payments must pay its small business subcontractors within 15 days, to the maximum extent practicable and without fees (FAR 52.232-40).
If cash is tight while you wait for payment, see contract financing and factoring.
Next step
Read today’s morning edition of new federal notices and get it by email for your state and up to five NAICS codes. To check a prime contractor before you sign a subcontract, look the company up by name, CAGE code or UEI in contractors.
Frequently asked questions
What is the Prompt Payment Act?
A federal law, 31 U.S.C. 3901–3907, that requires agencies to pay contractors by a due date and to pay interest automatically when they're late. For most invoices, the due date is 30 days after the billing office receives a proper invoice or 30 days after the government accepts the work, whichever is later.
What is the Prompt Payment Act interest rate?
4.75% a year for July 1 to December 31, 2026. Treasury sets a new rate every January and July. Interest runs from the day after the due date until the payment date, on a 360-day year, and unpaid interest is added to the principal every 30 days for up to a year.
Do I have to ask for late payment interest?
No. The payment office pays it automatically if it had a proper invoice and there was no disagreement over the work. If the agency pays late without the interest and doesn't pay the interest within 10 days, you can demand an additional penalty in writing within 40 days after the payment.
What makes an invoice proper?
It has your name and address, the invoice date and number, the contract and line item numbers, a description with quantities and prices, shipping and payment terms, who gets the payment, a contact for problems, and anything else the contract requires. A billing office must return a defective invoice within 7 days and say what's wrong.
How fast must a prime contractor pay its subcontractors?
On federal construction contracts, within 7 days after the government pays the prime for the subcontractor's satisfactory work, or the prime owes the subcontractor interest. On other contracts, a prime that gets accelerated payments must pass them on to small business subcontractors, to the maximum extent practicable, within 15 days.
Do small businesses get paid faster?
Agencies aim to pay small business contractors within 15 days of a proper invoice when the contract doesn't set a payment date. It's a goal, not a right: interest still runs only from the regular due date.
Sources
- FAR 32.904 — Determining payment due dates
- FAR 32.907 — Interest penalties
- FAR 32.009-1 — Accelerated payments to small businesses
- FAR 52.232-25 — Prompt Payment
- FAR 52.232-27 — Prompt Payment for Construction Contracts
- FAR 52.232-40 — Providing Accelerated Payments to Small Business Subcontractors
- 5 CFR 1315.10 — Late payment interest penalties
- 5 CFR 1315.11 — Additional penalties
- Bureau of the Fiscal Service — Prompt Payment interest rates
FedLook is not affiliated with SAM.gov or any U.S. government agency. Rules change; check the official sources before you act.
Related guides
- Government contract financing: how to fund the work before the government pays
How federal contract financing works: progress payments, performance-based payments and advance payments under FAR Part 32, plus bank and SBA options.
- Factoring government contracts: how the Assignment of Claims Act works
How factoring federal invoices works and what the Assignment of Claims Act requires: who can take an assignment, the notices to file and setoff risks.
- SAM registration and renewal: how to register in SAM.gov
Register your business in SAM.gov for free: what you need, the steps, how long it takes, yearly renewal, and why you don't need a paid service.
Free · at most one email a morning
Get new federal contracts by email
Pick an industry or a set-aside. Each morning we'll send the new notices that match, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy