1,200 steel wire trash racks for wildfire crews
The government wants 1,200 custom steel wire trash racks (NFES 002332), starting with one first article for government testing.
Official title: (1200 EA) Garbage Racks - First Article
- Deadline
- Dec 4, 5:00 PM ET
- 8 days left
- Who can bid
- Not stated
- The notice names no set-aside
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- Not stated
- Buyer: US Wildland Fire Contracting Activity
What they're buying
The other 1,199 racks are due 30 days after first article acceptance, and the contract period is otherwise not stated.
Top catches
“Delivery: 12/31/2026” Sol_140DWF27QL015.pdf, page 3
The cover page sets first article delivery at 60 days from award, but page 3 also says Delivery: 12/31/2026. Offers close 12/04/2026, so 60 days from any award would run past 12/31/2026. Ask the contracting officer which date governs before you price the job. Likely, not stated outright.
“The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered.” Sol_140DWF27QL015.pdf, page 12
The notice says the award is lowest price technically acceptable, but the evaluation clause says the government weighs technical capability, price and past performance together. Ask which method applies, and assume price drives the award if your rack only meets the minimum spec.
Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 1 of 1 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Supply 1,200 each of NFES 002332 custom made garbage racks, 32 gallon, per item 00010.
- Deliver one first article rack within 60 days from award for government testing and approval.
- Deliver the remaining 1,199 racks 30 days after first article acceptance.
- Build a steel wire frame of at least 3/8 inch wire, solid hot rolled round steel, with silver powder coating, in at least two pieces that fold flat.
- Hit the size of about 17 1/2 by 15 by 31 inches, with an opening of about 17 1/2 by 15 inches, and hold at least 25 pounds.
- Use new steel hinges of 3/16 inch thickness welded to each side, with rust-resistant rivets of at least 3/8 inch (galvanized zinc-plated preferred).
Who supplied it lately
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Fixed date conflicts with award timing. The cover page sets first article delivery at 60 days from award, but page 3 also says Delivery: 12/31/2026. Offers close 12/04/2026, so 60 days from any award would run past 12/31/2026. Ask the contracting officer which date governs before you price the job.
- LPTA conflicts with trade-off wording. The notice says the award is lowest price technically acceptable, but the evaluation clause says the government weighs technical capability, price and past performance together. Ask which method applies, and assume price drives the award if your rack only meets the minimum spec.
- Descriptive literature required with offer. If you do not send descriptive literature on time, the government will reject your bid. Include drawings or photos plus material and rivet details that show your rack meets each spec.“If the bidder fails to submit descriptive literature on time, the Government will reject the bid” Sol_140DWF27QL015.pdf, page 18
- Retest costs fall on you. You pay for all first article tests, including retests after a disapproval, and you may need to fix the rack and retest at your cost. The text does not name the testing facility, so ask where the first article goes and price the risk of a failed test.“All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval.” Sol_140DWF27QL015.pdf, page 16
- Short window for the bulk order. After first article acceptance, you have 30 days to deliver 1,199 racks, and failed racks are returned for repair or replacement. Line up steel, hinges, and rivets before the first article is approved.“(1199 EA) 30 days after first article acceptance.” Sol_140DWF27QL015.pdf, page 3
- Size given two ways. Page 2 gives the rack size as about 17 inches long, while the later specification page gives 17 1/2 inches. Ask which size governs, since a wrong size can make the rack non-compliant.“It must have a size of approximately 17 ½” Long by 15” Wide by 31” High.” Sol_140DWF27QL015.pdf, page 5
Key terms
| How they choose | Lowest price technically acceptable (LPTA)The evaluation clause also lists technical capability, price and past performance.Sol_140DWF27QL015.pdf, page 3 |
|---|---|
| Contract type | Firm-fixed priceThe notice states the government contemplates a firm fixed price contract.Sol_140DWF27QL015.pdf, page 14 |
How to respond
- Offer due Friday, 12/04/2026, 1700 ES. The notice does not say how to send an offer, so call Casey Boyd at 2083875353 to confirm.
- Include descriptive literature (drawings, photos, material and rivet details) showing your rack meets each spec, or the bid is rejected.
- Price one first article rack plus possible retests, since you pay for all test costs.
- If you win, deliver the first article within 60 days from award and the other 1,199 racks 30 days after first article acceptance.
- Submit each payment request electronically through the Treasury's Internet Processing Platform (IPP), at ipp.gov.
Attached files
From SAM.gov. Download links open the original files.
- Sol_140DWF27QL015.pdfThe solicitation with specifications, delivery schedule and clauses. You must read it, and complete offer blocks 12, 17, 23, 24 and 30 as the cover page notes. Read.
Not stated in what we read
- Set-aside status, since the SAM.gov record says not stated and the cover page boxes are unclear.
- How to submit the offer, including email, portal or mail, and the address.
- Delivery address and place of performance for the racks.
- Contract period beyond the delivery dates, and whether any option years exist.
- Estimated value or total award amount.
- Questions deadline and the address of the first article testing facility.
Notice text
NFES 002332 GARBAGE RACK
As published on SAM.gov.
Contacts
- Boyd, Casey, casey_boyd@ios.doi.gov, 2083875353
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 26, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 4, 5:00 PM ET8 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 332313, plate work manufacturing, soonest deadline first.
Free · at most one email a morning
Get new notices from Departmental Offices by email
Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy