Airlock wall and overhead door, Rock Island Arsenal, IL

The Army is buying one airlock wall inside Building 299 at Rock Island Arsenal, Illinois, with one large high-speed overhead door and one standard man-door, under a firm fixed price contract for one lot.

Official title: Airlock Doors - Rock Island Arsenal

Deadline
Dec 17, 9:00 AM CT
21 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Rock Island, IL
Buyer: W6QK ACC-RI

What they're buying

Offers are due Thursday, 17 December 2026 at 09:00 AM local time, and the notice lists work from 21 Dec 2026 to 01 Mar 2027.

Top catches

Bonds at 100 percent in 5 days
“The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.” W519TC27RA013.pdf, page 56

If you win, you must provide performance and payment bonds, each for 100 percent of the contract price, within 5 calendar days after award. Get a surety quote before you bid, because the bond cost must be in your price.

Bid guarantee may be 20 percent
“The amount of the bid guarantee shall be 20 percent of the bid price” W519TC27RA013.pdf, page 77

The bid guarantee clause sets the guarantee at 20 percent of your bid price. Item 13b does not show whether a guarantee is required. Ask the contracting officer before you bid and plan for a bid bond if it applies. Likely, not stated outright.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 25, 2026 from the notice and 2 of 3 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Build one airlock wall about 60 ft wide by 38 ft high inside Building 299, at the top of an existing ramp about 82 ft in from the west exterior.
  • Supply and install one large high-speed overhead door, 24 ft wide by 21 ft high, that stops automatically at 15 ft and has a full-height override.
  • Supply one standard non-locking man-door with a viewing window. The door leaf must be at least 3 ft by 7 ft.
  • Connect the overhead door to the building fire suppression control panel, with the reset reachable from floor level. Use flame-resistant fabric and Class A rigid panels.
  • Do site preparation, a flat landing at least 12 inches beyond the door swing, and all utility connections beyond the first connection point. Also shorten and terminate the bridge crane power strip.
  • Deliver all equipment on one day between 6:00 am and 12:00 pm, Monday to Thursday, marked ATTN: Mr. Drew Canada TARA-LGC. Provide training and complete documentation packages.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Bonds at 100 percent in 5 days. If you win, you must provide performance and payment bonds, each for 100 percent of the contract price, within 5 calendar days after award. Get a surety quote before you bid, because the bond cost must be in your price.
  • Bid guarantee may be 20 percent. The bid guarantee clause sets the guarantee at 20 percent of your bid price. Item 13b does not show whether a guarantee is required. Ask the contracting officer before you bid and plan for a bid bond if it applies.
  • Performance dates conflict. The notice gives two schedules: 60 calendar days after notice to proceed, and fixed dates of 21 Dec 2026 to 01 Mar 2027. The fixed start is 4 days after bids close. Ask which schedule governs before you plan crews and materials.“21 Dec 2026” W519TC27RA013.pdf, page 8
  • Site preparation is your job. You are solely responsible for site preparation, including excavation, foundation work and surface preparation. You also pay for all utility connections beyond the first connection point. Visit the site and price these items before you bid.“The contractor will be solely responsible for site preparation except as specifically excluded in this document.” RIPD E4000-25-4-05 Airlock Wall B299 (R1) (10-Nov-26).docx
  • Site visit needs a reservation. You need a reservation for the site visit at least two business days before, even if you have badge access. Without one you cannot attend. Ask the contact how to reserve, and bring steel-toed shoes and safety glasses.“You will not be allowed to attend without a reservation regardless of installation access.” Notice text
  • Davis-Bacon wages apply. Labor on this job must be paid at Davis-Bacon rates from wage determination IL20260012, Modification 3. That determination is not in the attachment list, so get it yourself and price labor from it.“Davis-Bacon Act WD # IL20260012 Modification 3 applies to this action” W519TC27RA013.pdf, page 5

Key terms

Contract period21 Dec 2026 to 01 Mar 2027Item 11 also says 5 days to start and 60 days after notice to proceed. These conflict.W519TC27RA013.pdf, page 8
How they chooseLowest price from a responsive, responsible bidderOne firm fixed price contract is awarded for the total evaluated price.W519TC27RA013.pdf, page 5
How to submitSealed bid delivered to ACC-RI, Building 60, 3055 Rodman Ave, Rock Island, IL 61299-0000Mark the envelope with your name and address, the solicitation number, and the due date and time. Delivery method (mail, hand delivery, email) is not stated.W519TC27RA013.pdf, page 1
Questions dueBefore bid closing, 17 Dec 2026No separate question date is given. Submit questions in writing to the contracting officer.RIPD E4000-25-4-05 Airlock Wall B299 (R1) (10-Nov-26).docx
Contract typeFirm fixed price, one lotConstruction work with Davis-Bacon wage rates. You must price the full lot.W519TC27RA013.pdf, page 4
Site visitThursday, 3 December 2026, 1000 Central TimeReservation required. Meet at the northeast corner of Building 299.Notice text

How to respond

  1. Reserve a spot for the 3 December 2026 site visit at least two business days before, through the contact John Jacobsen at john.e.jacobsen16.civ@army.mil or 520-693-1190. The reservation method is not stated.
  2. Send any questions in writing to the contracting officer before bid closing on 17 December 2026.
  3. Complete the offer section on page 2 of the solicitation form, sign it, and include your bid price and amendment acknowledgments. The number of copies is not stated beyond the original.
  4. Deliver the sealed bid to ACC-RI, Building 60, 3055 Rodman Ave, Rock Island, IL 61299-0000, by 09:00 AM local time on Thursday, 17 December 2026. Submission by email or portal is not stated.
  5. Mark the envelope with your name and address, the solicitation number W519TC27RA013, and the due date and time.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • 25-4-05+Quality+Assurance+Surveillance+Plan.xls: we could not read this spreadsheet, so we did not review it. You must read it on SAM.gov before you bid.
  • Estimated value of the contract is not stated.
  • Set-aside status and size standard are not stated.
  • How to reserve the site visit is not stated, beyond the contact name and email.
  • Whether a bid guarantee is required is not clear, because Item 13b does not show a selected option.
  • How to submit the bid (mail, hand delivery, email) and how many copies are required beyond the original are not stated.

Notice text

A pre-construction site visit is scheduled for 1000 Central Time on 03 December 2026, at Rock Island Arsenal -Joint Manufacturing and Technology Center (RIA-JMTC) with meeting Government representatives at the Northeast corner of Building 299, Rock Island Arsenal. All attendees will be required to wear steel toed safety shoes, safety glasses. Reservations for this site visit are mandatory for all attendees at least two business days prior to the site visit. If you currently have badge access you still must make a reservation for the site visit in order for the government to control the number of attendees at any given time. You will not be allowed to attend without a reservation regardless of installation access.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 25, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy