Miscellaneous paving work at Dugway Proving Ground, Utah
Official title: Dugway Proving Ground (DPG) Horizontal Facility Construction Road Maintenance
Open, 5 days left
- Deadline
- Nov 24, 1:00 PM MT
- Notice type
- SolicitationThe request for bids, proposals or quotes
- Set-aside
- 8(a) set-asideReserved for firms in the SBA 8(a) Business Development program (FAR 19.8).
- Industry
- Highway, Street, and Bridge ConstructionNAICS 237310, Construction
- Place of performance
- Dugway, UT
- Buying office
- W6QM MICC-Dugway Prov GrdOffice W911S6, Department of the Army
- Solicitation number
- W911S6-27-B-A001
- Product or service code
- Y1LBService code (PSC)
- Posted
- Nov 17, 2026
- Source
- SAM.govVersion 1, last change seen Nov 18, 2026, 4:30 AM UTC
Should you bid?
A free report for your company: whether you can bid at all (registration, set-aside, size), what to confirm in this notice before you start, and who may hold the work now. Made from public data in about 15 seconds.
One free report a month. We email you the link and nothing else.Find your UEI
What they're buying
Miscellaneous paving work at Dugway Proving Ground, Utah, under an indefinite-quantity contract limited to 8(a) firms. It has a 12-month base period with four 1-year options and is estimated at up to $5,000,000.00 a year.
- Miscellaneous paving construction ordered by task orders under the IDIQ contract.
- Airfield pavement work to TE-03, including rubber and paint removal with approved equipment; shotblasting is prohibited.
- Asphalt core sampling from existing pavement and patching of the sampled areas (TE-11).
- Fugitive dust control on each activity using DPG form BMPs, with logbooks when water or chemicals are used, and trackout cleanup.
- Work only during 7:00 AM to 5:30 PM MST, Monday through Thursday, excluding federal holidays, unless the KO approves a change.
- Contractor quality control plan due 15 days after award; QC test reports due within two working days.
Key terms
- Who can bid
- 8(a) firms authorized by the SBA Utah District OfficeA firm served by another SBA district may qualify if it has a bona fide place of business in Utah.Notice text
- Contract period
- 12-month base period plus four 1-year optionsWork is ordered by task orders. Minimums and maximums are set in Section B.Notice text
- How they choose
- Lowest total price for all CLINs, from a responsive and responsible 8(a) bidderThe low bidder must also be certified by SBA and registered in SAM before award.1442-Solicitation W911S627BA001 DPG Horizontal Construction 101426.pdf, page 107
- How to submit
- Email both contacts with the signed SF 1442 and the required subject lineEmail is the preferred method. Hand delivery needs access arranged at least 24 hours before closing.Notice text
- Questions due
- 4 November 2026, 1500 MDT (passed)Question deadline has passed. The site visit question deadline was 22 October 2026, 1500 MDT.Question and Answers IFB W911S6-27-B-A001-102226.pdf, page 2
- Estimated value
- Up to $5,000,000.00 a year (SOW figure)Amendment 0003 bondability letter uses $6,000,000.00 a year. Total ceiling is $30,000,000.00.Notice text
- Contract type
- Indefinite-delivery, indefinite-quantity, firm-fixed priceA guaranteed minimum of $50,000.00 applies per period. Bidders do not price those CLINs.Notice text
- Site visit
- Virtual only; review provided maps and pictures insteadAttachment 2, the virtual site visit deck, could not be read by the system. You must review it yourself.Solicitation Amendment W911S627BA0010003 SF 30.pdf, page 4
What to watch for
Bid Opening will be Wednesday 18 November 2026 promptly at 1300 MDT
Notice text
Bondability Letter: The offeror shall provide a letter from a qualifying surety
Solicitation Amendment W911S627BA0010003 SF 30.pdf, page 4
A firm serviced by another SBA District Office may still qualify to submit a bid if it maintains a bona fide place of business in Utah
Question and Answers IFB W911S6-27-B-A001-102226.pdf, page 1
Bidders shall not enter pricing for CLINs 0003, 1003, 2003, 3003, and 4003.
Solicitation Amendment W911S627BA0010003 SF 30.pdf, page 4
Note: Please include Bid Submission and solicitation number W911S6-26-B-A001 in the subject line of the email.
Solicitation Amendment W911S627BA0010003 SF 30.pdf, page 5
The amount of the bid guarantee shall be __20__ percent of the bid price or $_1,000,000.00
1442-Solicitation W911S627BA001 DPG Horizontal Construction 101426.pdf, page 105
How to respond
- Confirm you are an 8(a) firm authorized by SBA's Utah District Office, or that you have a bona fide place of business in Utah that SBA confirms. If another SBA district serves you, ask that office to request the Utah site visit.
- Complete and sign SF 1442: name and title in Block 20a, signature in Block 20b, date in Block 20c, and list Amendments 0001, 0002 and 0003 with their dates in Block 19.
- Price the base and option CLINs from Technical Exhibit 01, which was not reviewed, and carry the totals to Section B. Enter No Bid or leave guaranteed minimum CLINs 0003, 1003, 2003, 3003 and 4003 as formatted.
- Email the signed SF 1442, the bondability letter, any required bid guarantee and the pricing to Nicholas J. Rowton and Jim Keetch, with subject line Bid Submission W911S6-27-B-A001, so it arrives before 1:00 PM MST on Tuesday 24 November 2026.
- Hard copies go to Room 1409 at 5330 Valdez Circle, MS#1, but the notice wording on hard copies is unclear. Hand delivery or attending the bid opening needs access notice to Alfred.j.keetch.civ@army.mil at least 24 hours before closing.
Attached files
- TE-02 Standard Specification Book Rev 9 June 2025.pdfUDOT 2026 road and bridge standard specifications for roadway work. Read only; most pages were not provided. Read in part (pages 1–16 and 578–589 of 589).
- TE-04 Standard Drawings.pdf Could not be read.
- Question and Answers IFB W911S6-27-B-A001-102226.pdfQuestions and answers on the 8(a) Utah District limit and the bona fide place of business rule. Read only. Read.
- TE-09 Dust Control Forms 5 June 2025.pdfCover index for the 18 fugitive dust control forms. Read only. Read.
- TE-09o Fugitive Dust Control Form 15-Loading.pdfDust control form for truck loading. If you load trucks, select the controls, sign, and keep records. Read.
- Solicitation Amendment W911S627BA0010001 SF 30.pdfAmendment 0001, which added the first Q&A. You acknowledge it in Block 19 of SF 1442. Read.
- 1442-Solicitation W911S627BA001 DPG Horizontal Construction 101426.pdfSolicitation SF 1442 with Section B CLINs, bid guarantee clause and Section M rules. You must complete and sign SF 1442. Pages 10 to 103 were not provided. Read in part (pages 1–9 and 104–109 of 109).
- TE-01 Contract Line Items Proposal Template Base plus 4 Year-rv1.xlsx Not read: over our length limit.
- TE-09c Fugitive Dust Control Form 03-Stockpiles.pdf Not read: over our length limit.
- Solicitation Amendment W911S627BA0010002 SF 30.pdfConformed SF 1442 copy labeled Amendment 0002, which the notice says is to be replaced. You acknowledge amendment 0002 in Block 19. Read in part (pages 1–9 and 104–109 of 109).
- TE-09i Fugitive Dust Control Form 09-Site Grading.pdfDust control form for cut and fill work. If you do this work, select the controls, sign, and keep records. Read.
- DPG_Paved_Roads_2026.pdfMap of paved and unpaved roads, showing 545,524 feet paved and 7,491,370 feet unpaved. Read only. Read.
- TE-03 Paving IDIQ Airfield Specifications.pdfAirfield pavement specification for rubber and paint removal. Read only; most pages were not provided. Read in part (pages 1–8 and 218–222 of 222).
- TE-09k Fugitive Dust Control Form 11-Disturbed Soil.pdfDust control form for disturbed soil. If you do this work, select the controls, sign, and keep records. Read.
- TE-09a Fugitive Dust Control Form 01-Crushing.pdf Not read: over our length limit.
- Attachment 1 Scope of Work W911S6 Construction Horizontal FY27 - FY 31.pdfStatement of work covering work hours, holidays, quality control and dust rules. Read only; you sign nothing. Pages 4 to 21 were not provided. Read in part (pages 1–3 and 22–25 of 25).
- TE-09g Fugitive Dust Control Form 07-Site Preparation.pdfDust control form for clearing and site preparation. If you do this work, select the controls, sign, and keep records. Read.
- TE-09e Fugitive Dust Control Form 05-Staging Areas.pdfDust control form for staging areas. If you use staging, select the controls, sign, and keep records. Read.
- TE-09n Fugitive Dust Control Form 14-Trenching.pdfDust control form for trenching. If you trench, select the controls, sign, and keep records. Read.
- TE-11 Existing Asphalt Core Sampling FY27 -FY31 Paving 12 March 2026.pdfShort description of pulling asphalt core samples and patching afterward. Read only. Read.
- TE-09p Fugitive Dust Control Form 16-Paving.pdfDust control form for paving and subgrade preparation. If you pave, select the controls, sign, and keep logbooks. Read.
- TE-10 Asphalt Slurry Seal.pdf Not read: over our length limit.
- TE-09l Fugitive Dust Control Form 12-Disturbed Land.pdfDust control form for disturbed land. If you do this work, select the controls, sign, and keep records. Read.
- TE-06 Min Sampling an Testing.pdf Not read: over our length limit.
- TE-05 Materials Manual of Instruction.pdfMaterials acceptance manual excerpts on sampling and testing. Read only; most pages were not provided. Read in part (pages 1–6 and 205–224 of 224).
- TE-07 Quality Management Plans 5 June 2025.pdf Not read: over our length limit.
- TE-09q Fugitive Dust Control Form 17-Trackout.pdfDust control form for trackout and cleanup on paved roads. If you do this work, sign and keep records. Read.
- TE-08 Work Zones.pdfMap of work zones by distance from the Main Gate. Read it to see which zone your work falls in. Read.
- TE-09m Fugitive Dust Control Form 13-Sawing-Cutting.pdfDust control form for sawing and cutting. If you saw or cut, select the controls, sign, and keep records. Read.
- TE-09j Fugitive Dust Control Form 10-Demolition.pdfDust control form for mechanical demolition. If you do this work, select the controls, sign, and keep records. Read.
- TE-09f Fugitive Dust Control Form 06-Backfilling.pdf Not read: over our length limit.
- Solicitation Amendment W911S627BA0010003 SF 30.pdfAmendment 0003 with the new due date, bondability letter, guaranteed minimum rule and virtual site visit. You must acknowledge it in Block 19. Read.
- Attachment 2 Dugway Proving Ground Paving IDIQ Virtual Site Visit.pptx Could not be read.
- TE-09d Fugitive Dust Control Form 04-Hauling.pdfDust control form for hauling materials. If you haul, select the controls, sign, and keep an aggregate logbook. Read.
- TE-09b Fugitive Dust Control Form 02-Screening.pdf Not read: over our length limit.
- TE-09r Fugitive Dust Control Form 18-Traffic.pdfDust control form for traffic on unpaved roads and parking. If you do this work, select the controls, sign, and keep records. Read.
Not stated in what we read
- Which annual value is correct: $5,000,000.00 in the SOW and notice, or $6,000,000.00 in the Amendment 0003 bondability letter.
- Whether a bid guarantee is required. The SF 1442 check box is not readable in the copy reviewed.
- The wage determination the SOW cites for Utah holidays and pay is not among the files reviewed.
- Technical Exhibit 01 pricing spreadsheet and Standard Drawings (TE-04) could not be reviewed. You must read them yourself.
- Whether the 30-day start and 90-day completion periods are mandatory or negotiable. The SF 1442 check box is not readable.
- Content of Attachment 2, the virtual site visit deck, which could not be read. You must review it yourself.
Notice text
Amendment 0001 Q&A has been added Date: 22 October 2026 Amendment 0002 Final revised Q&A has been added Date: 05 November 2026 Amendment 0003 issued for the following reason: Correct formulas that has multiple QTY to add final totals accurately Update Section L Instructions, Conditions, & Notices to Offerors or Quoters Extend the IFB Solicitation date until Tuesday 24th November 2026 1:00 MST Bid opening will occur on Tuesday 24th November 2026 1:00 MST Replace current Amendment 0002 attachment in SAMs from Conformed Copy SF 1442 to Amendment SF30 f. PROJECT TITLE: MISCELLANEOUS PAVING REQUIREMENTS PROJECT LOCATION: U.S. ARMY DUGWAY PROVING GROUND, UTAH DESCRIPTION: THIS IS AN INDEFINITE-DELIVERY, INDEFINITE-QUANTITY (IDIQ), FIRM-FIXED PRICE REQUIREMENT FOR MISCELLANEOUS PAVING CONSTRUCTION SERVICES. ANY WORK REQUIRED BY THE GOVERNMENT SHALL BE ACCOMPLISHED BY THE ISSUANCE OF TASK ORDERS BY THE CONTRACTING OFFICER AGAINST THE PROPOSED CONTRACT. THE PERIOD OF PERFORMANCE (POP) FOR THIS REQUIREMENT IS A TWELVE (12) MONTH BASE PERIOD AND FOUR (4) ONE (1) YEAR OPTION PERIODS OF ONE YEAR EACH. THE ESTIMATED MAGNITUDE IS UP TO $5,000,000.00 ANNUALLY. THE NAICS FOR THIS ACQUISITION IS 237310, HIGHWAY, STREET, AND BRIDGE CONSTRUCTION (SMALL BUSINESS SIZE STANDARD $45 MILLION). PER FEDERAL ACQUISITION REGULATION (FAR) 19.108, THIS REQUIREMENT IS RESTRICTED TO 8(A) FIRMS AUTHORIZED BY THE SMALL BUSINESS ADMINISTRATION'S UTAH DISTRICT OFFICE TO PERFORM WITHIN THE DISTRICT'S GEOGRAPHICAL REGION. Offers shall be received prior to the closing date and time identified on SF 1442 (18 November 2026 by 1300 MDT) to the following address: Contract Specialist: Nicholas J. Rowton; Email Address: nicholas.j.rowton.civ@army.mil Contracting Officer: Jim Keetch; Email Address: Alfred.j.keetch.civ@army.mil Note: Please include Bid Submission and solicitation number W911S6-27-B-A001 in the subject line of the email. Example Subject Reference: Bid Submission W911S6-27-B-A001 DPG Horizontal Construction Paving Bid Opening will be Wednesday 18 November 2026 promptly at 1300 MDT at Dugway Proving Ground Building 5330 Valdez Circle conference room 1201, no bids will be accepted or considered after that time. Site Visit: The Government will hold a virtual site visit only. Bidders are required to submit a completed SF 1442, including the acknowledgement of all amendments in Block 19. SF 1442 cannot be accepted without being signed. The SF 1442 must be completed in full by the bidder, to include the Name and Title of the Person Authorized to sign in Block 20a, an original signature in Block 20b, and the Bid Date in Block 20c. Bids cannot be accepted and will be declared non-responsive without a valid signature in Block 20b. The final total bid price(s) from Technical Exhibit 01 must be annotated on the appropriate CLINs of Section B of the solicitation. Refer to Section L for additional details
As published on SAM.gov. Attachments are listed there; FedLook does not read them yet.
Contacts
- Nicholas J. Rowton, nicholas.j.rowton.civ@army.mil, 4358312620
- Alfred J. Keetch, alfred.j.keetch.civ@army.mil, 4358312362
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at Department of the Army for the same kind of work (NAICS 237310, service code Y1LB) in Utah that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
| Contract | Obligated | Ends | State |
|---|---|---|---|
| Dpg Maintenance and Repair Paving Idiq ContractMl-Tkl Construction II Jv · W911S625FA022 | $410,965 | Oct 30, 2026ended | UT |
| Dpg Maintenance and Repair Paving Idiq ContractMl-Tkl Construction II Jv · W911S626FA010 | $1,903,626 | Apr 21, 2027in 5 months | UT |
| Dpg Maintenance and Repair Paving Idiq ContractMl-Tkl Construction II Jv · W911S625FA020 | $424,542 | May 28, 2026ended | UT |
| Dpg Maintenance and Repair Paving Idiq ContractMl-Tkl Construction II Jv · W911S625FA019 | $577,583 | Apr 30, 2026ended | UT |
| Dpg Maintenance and Repair Paving Idiq ContractMl-Tkl Construction II Jv · W911S625FA011 | $119,723 | Nov 21, 2025ended | UT |
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 18, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Other open notices in highway, street, and bridge construction
| Notice | Set-aside | Place | Due |
|---|---|---|---|
| Paving Acquisition Vehicle - Rockies (PAV-R) IDIQ Sources SoughtDepartment of the Air Force, sources sought | Small business | Colorado Springs, CO | Nov 20Due tomorrow |
| Bridge foundation repair at Mammoth Cave, KYDepartmental Offices, sources sought | Not stated | Mammoth Cave, KY | Nov 234 days left |
| W9127827SC002 FY28 Horizontal Launch Infrastructure, SPOTFi (OTA) Progressive-Design-Build OTDepartment of the Army, special notice | Not stated | Not stated | Nov 245 days left |
| NAS Whiting Field Airfield Pavement RepairsDepartment of the Navy, special notice | Not stated | Milton, FL | Nov 245 days left |
| Al-Wheeler Nwr-Waterman GateDepartmental Offices | Not stated | Not stated | Nov 278 days left |
| Humbolt Pacific Crest Trail Bridge ReplacementForest Service | Not stated | Bridgeport, CA | Nov 289 days left |
| W912EK27BA003 - Detroit Project Office Detroit, MI Wayne County Roads, Parking, and Grounds RenovationDepartment of the Army, presolicitation | 8(a) | Not stated | Nov 3011 days left |
| Z NPS Repair or Alteration of Highways, Roads, Streets, Trails and Bridges MultipDepartmental Offices, sources sought | Not stated | Not stated | Nov 3011 days left |
Get new notices from Department of the Army by email
Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.
Free. We use your email only for these alerts and never share it. Privacy