Building 1 structural assessment and shoring, Milford, CT

NOAA's Northeast Fisheries Science Center is market testing for a contractor to assess structural distress in Building 1 at its Milford, Connecticut lab, design and install temporary shoring using government-furnished post shores, and monitor the structure.

Official title: NEFSC - Milford Lab Main Building Structural Assessment and Temporary Shoring

Deadline
Nov 30, 3:00 PM ET
5 days left
Who can respond
Any business
Market research, not a bid
Last time
None found
No contract like it at this agency in USAspending.gov
Place
CT
Buyer: Dept of Commerce NOAA

What they're buying

This is a sources sought notice, not a solicitation, so no bid is open yet.

Top catches

Not a solicitation, no bid yet
“THIS IS NOT A SOLICITATION, REQUEST FOR QUOTE (RFQ),” REQUIREMENTS-27-0637 SSN.pdf, page 1

This notice is market research only. NOAA does not guarantee a solicitation will follow, and any bid sent now will not be accepted. Reply only if you want to be considered, and do not plan a bid yet.

You supply almost everything
“All equipment, equipment rentals, material, manpower, permits, testing, and fees shall be the responsibility of the contractor.” REQUIREMENTS-27-0637 SSN.pdf, page 1

Only the 14 post shores come from NOAA. You must price all equipment, rentals, materials, labor, permits, testing, and fees, including the lumber and fasteners the shoring needs.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 19, 2026 from the notice and 2 of 2 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Visual and physical investigation of all floors and areas of Building 1, with focus on Room 16 and Room 24.
  • Chain drag sounding of suspected slab delamination per ASTM D 4580 Procedure B.
  • Inspection report with photos, crack mapping, root-cause analysis, repair recommendations, and cost estimates.
  • Temporary shoring design using 14 government-furnished SureBuilt SBPS350 post shores, with calculations and Connecticut PE-stamped drawings.
  • Installation of shoring with all lumber, fasteners, bracing, labor, and OSHA compliance.
  • Monitoring plan, bi-monthly inspections, shoring adjustments, and data reports for 12 months.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Not a solicitation, no bid yet. This notice is market research only. NOAA does not guarantee a solicitation will follow, and any bid sent now will not be accepted. Reply only if you want to be considered, and do not plan a bid yet.
  • You supply almost everything. Only the 14 post shores come from NOAA. You must price all equipment, rentals, materials, labor, permits, testing, and fees, including the lumber and fasteners the shoring needs.
  • Monitoring length and option years conflict. The draft SOW says monitoring runs 12 months, but the period of performance runs four years with Task 4 in every option year. Two option years are also both labeled Option Year 2. Ask NOAA which period to price.“for a 12-month period.” REQUIREMENTS-27-0637 Draft SOW.pdf, page 3
  • Connecticut-licensed engineer must stamp. Drawings and calculations must be stamped by a professional engineer licensed in Connecticut. Confirm you or a partner can supply that stamp before you respond.“Drawings and calculations to be stamped by a professional engineer licensed in the state of Connecticut.” REQUIREMENTS-27-0637 Draft SOW.pdf, page 2
  • Shoring may stay up about two years. The shoring must stay in place for about 24 months while funding for a future repair arrives. Price for that long hold, the bi-monthly visits, and possible delays.“approximately 24 months to allow for funding to arrive for a future structural repair project.” REQUIREMENTS-27-0637 Draft SOW.pdf, page 2
  • One-day email alert after inspection. Within one day after the inspection, you must email NOAA about any major deficiency that needs immediate action. Plan staff time for this before the draft report is due.“Within one day of the completion of the inspection, the Contractor shall provide an email informing the Government of any major deficiencies that require immediate action.” REQUIREMENTS-27-0637 Draft SOW.pdf, page 2

Key terms

Who can bidSet-aside not statedNOAA asks for your size and any SBA certifications. Stamped drawings need a Connecticut-licensed professional engineer.SAM.gov record
Contract periodOne base year plus three option years, shown as 2/6/2027 to 2/5/2031Only Task 4 (monitoring) is in the option years. The base year starts at Notice to Proceed.REQUIREMENTS-27-0637 Draft SOW.pdf, page 3
How to submitEmail to Kelsey Hendrix and Rachel StoneTelephone responses are not accepted. Limit is eight PDF pages, excluding the cover page.REQUIREMENTS-27-0637 SSN.pdf, page 2

How to respond

  1. Prepare a response of no more than eight PDF pages, not counting the cover page. Include firm name and address, a point of contact with phone, business size and SBA certifications, relevant experience, whether you are likely to quote, and what information you need to quote.
  2. Email the PDF to Kelsey Hendrix at kelsey.hendrix@noaa.gov and to Contracting Officer Rachel Stone at rachel.stone@noaa.gov.
  3. Send it by 12:00 p.m. Pacific Time on Monday, November 30, 2026. SAM.gov lists this as 3:00 PM at UTC-05:00.
  4. Do not respond by telephone. The notice says telephone responses are not accepted.

Attached files

From SAM.gov. Download links open the original files.

  • REQUIREMENTS-27-0637 Draft SOW.pdfThe draft statement of work listing tasks, shoring equipment, schedule, and standards. Read it to plan your price. You do not sign it. Read.
  • REQUIREMENTS-27-0637 SSN.pdfThe sources sought notice with the response instructions. You must read it, and you must write and email a reply if you want to be considered. No form is required. Read.

Not stated in what we read

  • Estimated value of the work: Not stated.
  • Whether a solicitation will follow and when: Not stated. NOAA does not guarantee one.
  • Set-aside and size standard for any future solicitation: Not stated.
  • Contract type and payment terms: Not stated.
  • Whether NOAA will provide the existing drawings the SOW says the contractor will review: Not stated.
  • Which period is correct for monitoring and option years: Not stated. The draft SOW conflicts with itself.

Notice text

The NEFSC is seeking a contractor to provide structural engineering services to evaluate multiple instances of observed structural distress within Building # 1 at the National Marine Fisheries Service (NMFS) Northeast Fisheries Science Center (NEFSC) Milford Lab in Milford, Connecticut. The Contractor will perform a comprehensive structural assessment, provide an inspection report, deliver a temporary shoring design using Government Furnished post shores, and implement a monitoring program.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 19, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from National Oceanic and Atmospheric Administration by email

Each morning we'll send the new solicitations and sources-sought notices from National Oceanic and Atmospheric Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy