Fire alarm upgrade at Montrose VA Medical Center

Replace fire alarm systems in 28 existing buildings and add new systems in two new buildings, CLC and 7B, on the VA Montrose Medical Center campus.

Official title: Y1DA--Project620-22-110 Replace and Upgrade Fire alarm System at Montrose VAMC

Deadline
Dec 16, 10:00 AM ET
20 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: 242-Network Contract Office 02 (36C242)

What they're buying

The work is phased over about 76 work weeks (532 calendar days) while the campus stays in operation.

Top catches

Scope sits in pages not provided
“Refer to specification 28 31 00, section 1.2 for the scope of work.” Specifications-Final.pdf, page 23

The scope points to section 1.2 of specification 28 31 00, and that section is in pages not provided to you. Read that section before you price the bid.

Wage determination not reviewed
“1.53 MINIMUM HOURLY RATE OF WAGES” Specifications-Final.pdf, page 16

A Westchester County wage determination is attached but was not included here. Get it from SAM.gov and price labor to its rates before you bid.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 18, 2026 from the notice and 5 of 7 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Replace the fire alarm system in 28 existing buildings and install new systems in new CLC and 7B buildings, each with its own control panel.
  • Build a networked, addressable, non-proprietary system on the campus fiber loop, including a fiber link from the new CLC building to Building 6.
  • Set up a primary master station in the Fire Department (Building 19) and a secondary master station at the Boiler Plant (Building 20).
  • Provide two full days of factory-trained on-site training for up to ten Fire Department and electrical staff.
  • Provide a 5-year maintenance and service agreement covering parts and labor, plus spare parts.
  • Phase the cutovers with a fire watch and at least 72 hours written notice before each old panel is removed.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Scope sits in pages not provided. The scope points to section 1.2 of specification 28 31 00, and that section is in pages not provided to you. Read that section before you price the bid.
  • Wage determination not reviewed. A Westchester County wage determination is attached but was not included here. Get it from SAM.gov and price labor to its rates before you bid.
  • Warranty term conflicts. Section 01 00 00 mentions a one-year construction warranty, while section 28 31 00 says two years. Ask the contracting officer which applies, and price the longer term until you get an answer.“two years from the date of acceptance of the entire installation by the” Specifications-Final.pdf, page 361
  • Discrepancies must be priced high. If drawings and specifications disagree, the base bid must include the most stringent and most expensive option. Price any conflict at the costlier option, or your base bid may come in low.“the most expensive option shall be included in the base bid.” Specifications-Final.pdf, page 23
  • Superintendent cannot do hands-on work. The superintendent must be dedicated to this project and cannot do hands-on work. This person must also sign in and out at the COR's office each day, so price this as a full-time cost.“The superintendent must also have no hands-on construction interaction.” Specifications-Final.pdf, page 19
  • Badges and screening before work. Every worker, including subcontractors, needs fingerprinting and a favorable screening before starting. Names are due within ten days of notice to proceed, so start the paperwork early.“complete the following within five (5) business days of receiving these instructions.” Fire Alarm Replacement Attachment A - Identification Card Process.doc

Key terms

Who can bidLicensed, factory-authorized fire alarm firms onlySet-aside is not stated on the SAM.gov record. The size standard is not in the text reviewed.Specifications-Final.pdf, page 18
Contract period76 work weeks (532 calendar days)From the phasing plan. The bid form line for number of completion days is blank.Specifications-Final.pdf, page 43
Contract typeConstruction with a base bid and three alternatesPricing type, such as fixed price, is not stated in the text reviewed.Specifications-Final.pdf, page 22
Site visitBy appointment only, through the Medical Center Engineering OfficerWhether a site visit is mandatory is not stated.Specifications-Final.pdf, page 17

How to respond

  1. Read the full specification pages 61 to 353 and the drawings on SAM.gov before pricing, since they were not reviewed here.
  2. Price the base bid and Alternates 1, 2 and 3 on the bid form in section 01 00 00 1.4, itemized by building, and state the number of completion days.
  3. Complete the Buy American Certificate, listing any foreign end products by line item and country of origin.
  4. Submission method, address and format: Not stated. Send the signed bid so it arrives by Wednesday, December 16, 2026, 10:00 AM (offset -05:00).

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated value: not stated, and the base bid amounts are blank.
  • Set-aside and size standard: not stated. The limitations on subcontracting certificate was not included, so you must read it.
  • Wage rates: the Westchester County wage determination was not included, so you must read it before pricing labor.
  • Submission method, address and questions deadline: not stated.
  • Drawings: the drawings file text did not come through, so the drawings could not be reviewed. You must read them.
  • Award basis: whether bids are compared on price alone or on other factors is not stated.

Notice text

See attached

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 18, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of Veterans Affairs by email

Each morning we'll send the new solicitations and sources-sought notices from Department of Veterans Affairs, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy