Replace 150 kVA backup generator at Camp Zama, Japan
Replace the 150 kVA emergency diesel generator that backs up Building 121 at Camp Zama, Japan, including removal and disposal of the old unit, installation, testing and a warranty.
Official title: Replace DSN-HDD Generator for 78th Signal Battalion, Camp Zama, Japan.
- Deadline
- Dec 2, 11:00 AM UTC+09:00
- 5 days left
- Last time
- $205K
- Likely Cummins Inc.
- Place
- Zama, JPN
- Buyer: FA5209 374 Cons PK
What they're buying
The work must be done in Japan over about 602 calendar days from award, and asbestos removal in one room is also required under Amendment 0003.
Top catches
“For pricing and schedule purposes, offerors shall assume that removal of known ACM in Building 121, Room 112, will be performed under full negative-pressure containment.” SOW Amend 0003.pdf, page 3
The newest SOW tells you to price full negative-pressure containment for Room 112 asbestos, but the Q and A says to leave abatement out of the base quote. Get the contracting officer to confirm before you price.
“A minimum 2-year warranty is required for the new generator system.” Notice text
The notice still says 2-year warranty, but the Amendment 0003 SOW and the Q and A say 1 year for parts and labor. Get written confirmation of the term before you price the warranty.
Read by AI (Claude Haiku) on Nov 21, 2026 from the notice and 10 of 10 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Decommission, drain, remove and dispose of the existing Toyo Denki TYND-215 generator at licensed off-base facilities in Japan, with receipts or manifests.
- Supply, deliver and anchor a new 150 kVA / 120 kW diesel generator, 208/120 VAC, 50 Hz, with an EPA Tier 3 or Tier 4 engine, 1,000 to 1,500 W heater, radiator fan guard and local output breaker.
- Connect the new unit to the existing or new ATS in Building 121. Retain and certify the 2008 diesel tank, fuel piping and wiring only if they are serviceable.
- Provide a temporary backup generator that stays running for Building 121 during construction.
- Remove known asbestos-containing material in Building 121, Room 112, under an accepted ACM abatement work plan, priced for full negative-pressure containment.
- Run an 8-hour load test on site load of about 30 to 40 kVA, deliver the test plan and reports in English and Japanese, train staff, and provide a 1-year warranty with on-site service in Japan.
Who supplied it lately
$205K
on a recent contract for the same kind of product: Cummins Inc.. It ended Sep 29, 2026.
Matched in USAspending.gov by agency, NAICS and product code; notices rarely name the supplier.
What to watch for
- Asbestos pricing rules conflict. The newest SOW tells you to price full negative-pressure containment for Room 112 asbestos, but the Q and A says to leave abatement out of the base quote. Get the contracting officer to confirm before you price.
- Warranty term conflicts. The notice still says 2-year warranty, but the Amendment 0003 SOW and the Q and A say 1 year for parts and labor. Get written confirmation of the term before you price the warranty.
- Survey required, no site visit. You must confirm the new generator fits the existing ATS before you quote. The government will not arrange another survey, so request the ATS drawings from the COR or GR now.“no further site surveys will be arranged for prospective offerors.” SOW Amend 0003.pdf, page 6
- Japanese licenses needed with quote. Three Japanese electrical licenses must be held by your staff. The SOW says copies are needed before award, but this notice says at quote time, so send them with your quote.“Failure to submit verifiable evidence of these qualifications and certifications at the time of quote submission may result in the offer being evaluated as technically unacceptable.” Notice text
- Local partner proof if not in Japan. If your firm is not physically in Japan, you must name a local partner able to give on-site service. Without that proof your quote is unacceptable and will not be considered for award.“Failure to submit verifiable evidence of local warranty service capability at the time of quote submission will result in the offer being evaluated as technically unacceptable and not considered for award.” Notice text
Key terms
| Who can bid | Open to all firms; no set-asideNAICS 335312. Trade Agreements Act applies. Staff need Japanese electrical licenses.SAM.gov record |
|---|---|
| Contract period | 602 calendar days from awardAward expected around 23 Dec 2026, subject to change. Earlier amendments said 560 days.Solicitation Amendment FA520926Q00770003 SF 30.pdf, page 3 |
| How they choose | Lowest total evaluated price among quotes that pass technical reviewThe new generator is judged pass or fail. The government may run a price realism check.Solicitation - FA520926Q0077.pdf, page 25 |
| How to submit | Email quote to two Air Force contactsWord, Excel or PDF files only. No zip files. Send to hiroko.takahashi.jp@us.af.mil and kaori.kanematsu.jp@us.af.mil.Solicitation - FA520926Q0077.pdf, page 24 |
| Contract type | Firm fixed price, one lotOne line item (CLIN 0001) covering removal, disposal and installation. Commercial products format under FAR Part 12.Solicitation - FA520926Q0077.pdf, page 3 |
| Site visit | No further site visitThe 7 Oct 2026 visit has passed. Pre-quote checks of ATS compatibility are still required.Notice text |
How to respond
- Email your quote to hiroko.takahashi.jp@us.af.mil and kaori.kanematsu.jp@us.af.mil by 11:00 AM, Wednesday, 2 Dec 2026, +09:00. Send early, because you carry the risk of blocked email.
- Send files as Word, Excel or PDF only. Do not send zip files. Include the make, model, specifications and catalog cut of the new generator.
- Attach copies of the three Japanese electrical licenses. If you are not in Japan, also give the local partner's name, address, responsible person, email and phone number.
- Complete SF 1449 blocks 12, 17a, 30a, 30b and 30c, the price schedule for CLIN 0001, and an acknowledgment of all four amendments. Keep prices firm for 60 calendar days.
- Questions deadline: Not stated. Ask the contracting officer about the asbestos pricing rule and the warranty term before you submit, because the notice text conflicts with the amendments.
Attached files
From SAM.gov. Download links open the original files.
- Ans to KTR Questions.docxGovernment answers to contractor questions that change the SOW, so read them. You do not sign anything. Read.
- SOW Amend 0003.pdfLatest statement of work, updated 10 Nov 2026, with asbestos work added. Read it; pages 9 to 15 were not provided, so you must read them on SAM.gov. Read in part (pages 1–8 and 16–40 of 40).
- Solicitation Amendment FA520926Q00770002 SF 30.pdfAmendment 0002 that changed the due time, the SOW version and the delivery period. Read it and acknowledge it with your quote. Read.
- SOW 24 Aug Clear Copy.pdfFirst statement of work dated 24 Aug 2026, since replaced. Read for background only. Read.
- Solicitation - FA520926Q0077.pdfOriginal solicitation with quote instructions and evaluation terms. Pages 13 to 20 were not provided, so you must read them on SAM.gov. You fill in SF 1449 blocks and the price schedule. Read in part (pages 1–12 and 21–26 of 26).
- SOW Amdnment 02.docxUpdated statement of work dated 26 Oct 2026 with Q and A answers built in, since replaced by the Amendment 0003 SOW. Read for background only. Read.
- Solicitation Amendment FA520926Q00770003 SF 30.pdfAmendment 0003 that adds asbestos work and extends delivery to 602 days. Read it and acknowledge it with your quote. Read.
- Solicitation Amendment FA520926Q00770004 SF 30.pdfAmendment 0004 that moves the response due date to 2 Dec 2026. Read it and acknowledge it with your quote. Read.
- Solicitation Amendment - FA520926Q00770001.pdfPartial copy of the solicitation under number FA520926Q00770001 with the same terms. Pages 13 to 20 were not provided, so you must read them on SAM.gov. Read in part (pages 1–12 and 21–26 of 26).
- Solicitation Amendment FA520926Q00770001 SF 30.pdfAmendment 0001 that moved the closing date to 10 Nov 2026. Read it and acknowledge it with your quote. Read.
Not stated in what we read
- Estimated value of the contract: Not stated.
- Price basis for asbestos removal, and whether the government will add a separate CLIN by amendment: Not stated beyond Amendment 0003 and the Q and A.
- ATS specifications, as-built electrical drawings and tank drawings: not in the text provided; the notice says they are available from the COR or GR.
- Questions deadline: Not stated.
- Pages 9 to 15 of SOW Amendment 0003 and pages 13 to 20 of the solicitation were not provided, so we could not review them. You must read them on SAM.gov.
- Current condition of the 2008 diesel tank, fuel piping and wiring: stated only as serviceable. You must inspect and certify them.
Notice text
This Statement of Work (SOW) defines the requirements, scope, responsibilities, and deliverables for the replacement and disposal of the 150kVA emergency power diesel generator located on Camp Zama Japan Building 121. This is a solicitation for commercial products or commercial services prepared in accordance with the format in FAR 12 as supplemented with additional information included in this notice. The written solicitation, issued as SF1449 (Form), is attached to this notice and constitutes the official solicitation.
Quotes are being requested in accordance with the instructions herein and within the attached SF1449. The statements required by FAR 12.202(b)(1) are included in the uploaded documents. Expecting award date is around 23 Dec 2026 (subject to change). Description of Services: The contractor shall provide all necessary labor, management, tools, equipment, transportation, and materials to perform the decommissioning, removal, disposal, and replacement of the existing 150kVA emergency power diesel generator at Building 121, Camp Zama, Japan.
The primary objective is to safely disconnect and dispose of the existing unserviceable generator (Toyo Denki Seizo / TYND-215) and install a brand new 150 kVA / 120 kW diesel generator (208/120 VAC, 50 Hz). The new system must be fully integrated and compatible with the existing Automatic Transfer Switch (ATS) in Panel P-M/L-M. The project includes full testing, an 8-hour load test, commissioning, and training. All disposal of the old generator and hazardous materials must comply with Japanese environmental regulations utilizing off-base facilities.
A minimum 2-year warranty is required for the new generator system. The contractor is required to provide employees who have demonstrated experience in work like this requirement. The contractor or their sub-contractors shall ensure their employees have the flicenses as required at paragraph 10.4. of the SOW. Failure to submit verifiable evidence of these qualifications and certifications at the time of quote submission may result in the offer being evaluated as technically unacceptable.
Note 1: All work for this project shall be performed exclusively in Japan. The contract price shall be inclusive of all travel and lodging expenses required for project execution. Note 2: Mandatory On-Site Warranty & Local Service Capability The project and product utilization will occur entirely within the country of Japan. During the Warranty Period, the selected contractor must provide on-site repair, troubleshooting, or replacement services at the Off-Post locations in Japan.
Note 3: If the offeror is not physically located in Japan, the offeror MUST submit documentation demonstrating an established partnership with a local authorized service provider in Japan capable of meeting all on-site requirements. Please provide the partner company’s Name, Address, Point of Contact, Email, and Phone Number with your quote. Failure to submit verifiable evidence of local warranty service capability at the time of quote submission will result in the offer being evaluated as technically unacceptable and not considered for award.
Note 4: If successful offeror is a U.S. vendor, resulting contract will include DFARS clause 252.225-7976, Contractor Personnel Performing in Japan (Deviation 2018-O0019). The clause requires DoD contractors to account for contractor personnel and dependents in the Synchronized Predeployment and Operational Tracker (SPOT), in order for the contractor personnel and dependents to be eligible for coverage under the Status of Forces Agreement. Note 5: Trade Agreements Act (TAA) Compliance & Prohibited Sources This procurement is subject to the Trade Agreements Act (TAA).
Quotes will be evaluated IAW DFARS 252.225-7020, FAR 52.212-1 and 52.212-2. Note 6: Site Visit. A pre-solicitation site visit is scheduled to be conducted on 7 October 2026, at 10:00 AM (JST) at Camp Zama, Japan. All prospective quoters are strongly encouraged to attend. To participate, submit a list of all attendees (including full name, residential address, nationality, pass port number or driver’s license number) via email to hiroko.takahashi.jp@us.af.mil and kaori.kanematsu.jp@us.af.mil no later than 7 calendar days prior to the scheduled visit.
Note 7: No additional site visit is scheduled.?
As published on SAM.gov.
Contacts
- Akane Jukurogi, akane.jukurogi.jp@us.af.mil, 81425516120
- Kaori Kanematsu, kaori.kanematsu.jp@us.af.mil, 3152252634
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who has supplied this lately
Contracts at Department of the Air Force for the same kind of product (NAICS 335312, product code 6115) that end within a year either way of today. Notices rarely name the current supplier: these are likely candidates, not a fact.
| Contract | Obligated | Ends | State |
|---|---|---|---|
| Cummins Rugged Mobile Power 1070 60KW GeneratorsCummins Inc. · FA500025P0089 | $205,131 | Sep 29, 2026ended | AK |
| This Is a Brand-Name Requirement for a Caterpillar Brand Standby Generator and Ats Installation of One New Commercial Powered Diesel Engine 500 KW, 120/208 Volt, 60 HZ, 2000-Amp, Genset Generator…Imperial Electrical Contracting, LLC · FA303025C0012 | $489,403 | Sep 1, 2026ended | TX |
| Erhs Back 40 GeneratorTribus Energies LLC · FA502526CB008 | $419,800 | Aug 11, 2026ended | GU |
| Upgrade B2 Digital Master Control & Control System on Peterson SFB.Yukon Fire Protection Services, Inc. · FA251723P0053 | $589,050 | Jul 31, 2026ended | CO |
| 72KW Gpu, 144KW Gpu, 144KW UlbAviation Ground Equipment Corp · FA853224F0001 | $27,418,720 | Jul 25, 2026ended | NY |
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 19, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 2, 11:00 AM UTC+09:005 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 335312, motor and generator manufacturing, soonest deadline first.
- Department of the ArmyMotor control units for PATRIOT launcher, Fort Bliss, TX
- Department of the NavyRepair of alternating motors for the Navy
- Defense Logistics AgencyPower conditioner units for military supply
- Defense Logistics AgencyController units to a Navy design, for DLA Mechanicsburg
- Defense Logistics AgencyPower supplies for DLA depots, CONUS and OCONUS
- Defense Logistics Agency13 power supplies for DLA depots, U.S. and overseas
- Defense Logistics Agency14 generator rotors for DLA, San Diego
- Defense Logistics AgencyTwo distribution boxes for DLA Aviation
Free · at most one email a morning
Get new notices from Department of the Air Force by email
Each morning we'll send the new solicitations and sources-sought notices from Department of the Air Force, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy