- RFP-SC-27-723
Hazardous gas storage cabinets at Ames Lab, Ames, IA
Ames National Laboratory wants a subcontractor to buy and install hazardous and flammable gas storage cabinets in three buildings in Ames, Iowa, priced as a fixed-price base bid with several alternates.
Official title: RFP SC-27-723 Hazardous & Flammable Gas Cabinets and Install
- Deadline
- Jan 8, 2027, 4:00 PM CT
- 43 days left
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- Ames, IA
- Buyer: Ames Laboratory - DOE Contractor
What they're buying
The contract length and estimated value are not stated.
Top catches
“There is a mandatory pre-proposal meeting and project site tour.” Notice text
You must attend the pre-proposal meeting and site tour. The provided text gives no date, time or place, so ask Andrew Saxton before you plan your bid. Missing it likely means you cannot bid.
“your firm MUST be registered in SAM” Appendix H - Reps and Certs Supplemental 12-8-2022.pdf, page 1
Any subcontract of $10,000 or more requires SAM registration and completed representations and certifications. Confirm your SAM record is active and current before you bid.
Read by AI (Claude Haiku) on Nov 20, 2026 from the notice and 10 of 14 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Buy and install hazardous and flammable gas storage cabinets in Metals Development, Harley Wilhelm Hall and Spedding Hall.
- Price a base bid and alternate bids, using Alternate No. 1 through Alternate No. 6 on the bid form.
- Plan utility shutdowns: fire suppression up to 8 hours continuous, and mechanical exhaust up to 4 hours continuous, during normal hours of 7:30 AM to 4:30 PM, Monday through Friday.
- Allow for penetration permits (10-15 days for approval) and a non-citizen worker review process (45 days for review and approval), per the Wilhelm Hall drawing notes.
- Submit an ES&H program plan within 10 calendar days after award, plus a job safety analysis and hazard management statements before each hazardous task.
- Provide a construction phasing plan and an itemized cost breakdown that shows margin and overhead.
Who did it before
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Mandatory pre-proposal meeting. You must attend the pre-proposal meeting and site tour. The provided text gives no date, time or place, so ask Andrew Saxton before you plan your bid. Missing it likely means you cannot bid.
- SAM registration and certifications. Any subcontract of $10,000 or more requires SAM registration and completed representations and certifications. Confirm your SAM record is active and current before you bid.
- Safety record data required. Ames Lab requires three years of EMR and OSHA 300 injury data, and the safety questionnaire can come back as not approved. Gather these figures before you submit your bid.“List your firm's interstate Experience Modification Rate (EMR) for the past three consecutive years.” Appendix C - Contractor Safety and Quality Assurance Information Questionnaire.pdf, page 1
- Bonds required over $150,000. Subcontracts over $150,000 require performance and payment bonds, and the terms require insurance certificates before work starts. Price bond and insurance cost into any bid above that amount.“Subcontracts exceeding $150,000 (Miller Act)” Appendix A - Terms and Conditions for FP Construction (Oct 2023).pdf, page 2
- Wage determination not reviewed. The Story County wage determination is listed but was not included in what we could read. Read it on SAM.gov and price labor at those rates before you bid.“Construction Wage Rate Requirements” Appendix I - SF1413-13d.pdf, page 1
- Acceptance period conflicts. The form gives the acceptance period as thirty and as 45 days in the same sentence. Ask which applies, because it sets how long your price must hold.“The proposal may be accepted for a period of thirty (45) calendar days after the opening date.” Appendix J - Proposal Form.pdf, page 1
Key terms
| Who can bid | Open to all firms, no set-aside. SAM registration is required for subcontracts of $10,000 or more.Registration and annual representations are required under the supplemental form.SAM.gov record |
|---|---|
| How to submit | Priced proposal delivery method: Not statedRepresentations and certifications go by email to Andrew Saxton at saxton@ameslab.gov.Appendix H - Reps and Certs Supplemental 12-8-2022.pdf, page 1 |
| Contract type | Fixed-price subcontract with a base bid and alternatesPriced as a firm fixed price on the bid form.Notice text |
| Site visit | Mandatory pre-proposal meeting and site tour. Date and time not stated.The provided text does not give the date, time or place of the meeting or tour.Notice text |
How to respond
- Confirm your SAM registration, then complete the Representations and Certifications Supplemental (Appendix H) and email it to saxton@ameslab.gov.
- Attend the mandatory pre-proposal meeting and site tour. Date, time and place: Not stated, so confirm with Andrew Saxton.
- Complete the Proposal Form (Appendix J) with the base bid, Alternates 1 to 6, key personnel, and an itemized cost breakdown showing margin and overhead. Where and how to deliver it: Not stated. Response deadline is Friday, January 8, 2027, 16:00 (-06:00).
- Complete the Contractor Safety and Quality Assurance Questionnaire (Appendix C) with EMR and OSHA 300 data for three years. Sign the Affirmation and Certification (Appendix G) only if you are the authorized signer, since it is certified under perjury of law.
Attached files
From SAM.gov. Download links open the original files.
- Appendix H - Reps and Certs Supplemental 12-8-2022.pdfRepresentations and certifications form. You must complete and sign it, and email it to Andrew Saxton. Read.
- Appendix E - Story County WD IA20260074 dated 05-18-2026.pdf Not read: over our length limit.
- SC-27-723 Gas Cabinet Installation - Metals Development DWGs.pdf Not read: over our length limit.
- SC-27-723 Gas Cabinet Installation - Wilhelm Hall DWGs.pdfPartial drawing set for Wilhelm Hall. We reviewed only the first page; you must read the full drawings yourself. Read in part.
- Appendix G - Affirmation and Certification of Subcontract Terms and Conditions.pdfSafety affirmation form. An authorized signer must complete and sign it, certifying it under perjury of law. Read.
- Appendix D - Construction requiring delivery of data 06-24-2021.pdfIntellectual property and data rights terms. You should read it, since the government gets broad rights to data first produced under the contract. Read.
- Appendix A1 - ESH Ts and Cs - Sept. 5, 2024.pdfEnvironment, safety and health terms for the subcontract. You must read it and follow it, but do not sign it. Read.
- Appendix A - Terms and Conditions for FP Construction (Oct 2023).pdfGeneral fixed-price construction terms covering payment, bonds, insurance and liability. You must read it and price to it. Read.
- Appendix F - Hazardous Gas Cabinet Project Safety Requirements and Deliverables.pdfProject safety requirements and hazard list. You must read it, since many items need approved plans before work starts. Read.
- SC-27-723 Gas Cabinet Installation - Project Manual (2).pdf Not read: over our length limit.
- SC-27-723 Gas Cabinet Installation - Spedding Hall DWGs.pdf Not read: over our length limit.
- Appendix C - Contractor Safety and Quality Assurance Information Questionnaire.pdfSafety and quality questionnaire. You must complete it and submit it for approval. Read.
- Appendix I - SF1413-13d.pdfSubcontract statement and acknowledgment form. If awarded, the subcontractor signs Part II acknowledging the labor clauses. Read.
- Appendix J - Proposal Form.pdfBid form for the base bid, alternates, key personnel and receipt of addenda. You must complete and sign it. Read.
Not stated in what we read
- Estimated contract value: Not stated.
- Contract period, start date and completion schedule: Not stated.
- Date, time and place of the mandatory pre-proposal meeting and site tour: Not stated.
- How and where to deliver the priced proposal, and the format required: Not stated.
- Award basis and evaluation criteria: Not stated. Also the questions deadline is not stated.
- The project manual, the Metals Development and Spedding Hall drawings, and the Story County wage determination were not included in what we could review. You must read them on SAM.gov.
Notice text
Ames Laboratory, under a prime contract with the U.S. Department of Energy (DOE), has a requirement for construction. With this Request for Proposal (RFP), you are invited to furnish a fixed-price proposal for this requirement. All work is to be performed in accordance with Appendix B: Project Manual and Drawings Dated 11/16/2026. This RFP is for the purchase and install of Hazardous and Flammable Gas Storage Cabinets. This RFP includes a request for a base bid and several alternate bids. There is a mandatory pre-proposal meeting and project site tour.
As published on SAM.gov.
Contacts
- Andrew Saxton, saxton@ameslab.gov, 5152944191
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 20, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Jan 8, 2027, 4:00 PM CT43 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 238290, other building equipment contractors, soonest deadline first.
- Department of Veterans AffairsRoll-up door replacement at McClellan VA, Little Rock, AR
- Federal Prison System / Bureau of PrisonsReplace elevators at federal detention center, Miami, FL
- Department of Veterans AffairsElevator interior upgrades at Jesse Brown VA, Chicago, IL
- Department of Veterans AffairsElevator maintenance and repairs at White City VA, OR
- Department of Veterans AffairsElevator inspections and load tests at Big Spring VA, TX
- Departmental OfficesElevator maintenance and repair, Boston, MA
- Department of Veterans AffairsSmall Business Event | 2026 National Veterans Small Business Engagement | Cleveland Ohio Dec 8-9 | Amendment 1
- Department of Veterans AffairsModernize nine elevators at Jesse Brown VA, Chicago, IL
Free · at most one email a morning
Get new notices from Department of Energy by email
Each morning we'll send the new solicitations and sources-sought notices from Department of Energy, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy