1. Opportunities
  2. Department of Energy
  3. RFP510922

Integrated Mazak FUSE machining system, Knoxville, TN

ORNL's Defense Manufacturing Program Office wants a firm fixed price, fully integrated Mazak FUSE manufacturing system: one subtractive machining station, one WAAM station, two blank machine stations, five pallet changer modules and a two-level PALLETECH system with 32 pallets.

Official title: X209 Mazak FUSE System FY27

Deadline
Tomorrow, 3:00 PM ET
Friday, Nov 27
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Oak Ridge, TN
Buyer: Ornl UT-Battelle LLC-DOE Contractor

What they're buying

Equipment must be delivered and installed at ORNL's Knoxville, Tennessee facility within 13 to 14 months after order.

Top catches

Deadline moved to December 7
“Extend the response date through 7 December 2026, 4:00 PM EST.” Amendment 1.pdf, page 1

Amendment 1 moved the due date. The SAM.gov record and RFP still show November 27, so use the amended date and time. The amendment must be acknowledged in your final proposal or the offer may be rejected.

Mazak only, or a domestic equivalent?
“Mazak FUSE System or domestic equivalent” Notice text

The notice allows a domestic equivalent, but the SOW names Mazak models and the RFP says offers must meet the SOW with no exceptions. Ask the Procurement Officer in writing before you price a non-Mazak machine.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 24, 2026 from the notice and 11 of 11 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • One Mazak VC-EZ20X subtractive machining station with option package and pallet changer specification
  • One WAAM (wire arc additive manufacturing) station with base machine, option package, pallet changer specification and WAAM configuration package
  • Two blank machine stations, each with option package and pallet changer specification
  • Five pallet changer modules and five connection modules linking machines to the pallet management controller (PMC)
  • One two-level PALLETECH system with 32 pallets, PMC-to-machine connection package, customized layout and heat treatment module interface (the heat treatment module itself is excluded)
  • Engineering, design review, runoff testing, delivery, installation and final acceptance at ORNL Manufacturing Demonstration Facility, Knoxville, TN, within 13 to 14 months after order

Who supplied it lately

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Deadline moved to December 7. Amendment 1 moved the due date. The SAM.gov record and RFP still show November 27, so use the amended date and time. The amendment must be acknowledged in your final proposal or the offer may be rejected.
  • Mazak only, or a domestic equivalent? The notice allows a domestic equivalent, but the SOW names Mazak models and the RFP says offers must meet the SOW with no exceptions. Ask the Procurement Officer in writing before you price a non-Mazak machine.
  • U.S. persons only for this work. Project work is limited to U.S. persons, and deliveries to ORNL must be made by a U.S. citizen. Confirm that your crew, installers and drivers qualify before you bid.“Please note that project work associated with this procurement is limited to U.S. persons only.” Attachment E - Fixed Price Subcontract - Draft.pdf, page 9
  • 13 to 14 month delivery must be confirmed. You must confirm delivery within 13 to 14 months after order in your technical proposal. Runoff is due at 12 months, so check your build and test time before you commit.“the schedule requirement of delivery within 13 to 14 months after receipt of order shall be confirmed within the technical proposal.” RFP510922.pdf, page 5
  • Factory test data needed with equipment. Electrical items that are not NRTL listed or field evaluated must come with schematics, wiring diagrams, detailed factory test results and operating instructions. ORNL may reject equipment without them, so price this paperwork now.“Detailed results of factory tests. Certificates of compliance or conformity alone are not acceptable.” Attachment E - Fixed Price Subcontract - Draft.pdf, page 7
  • Payment only after final acceptance. Payment is due after final acceptance, which follows installation. The RFP says Net 30 or Net 15 depending on size, while the draft subcontract says Net 15, so ask which applies and whether milestone billing is allowed.“Payment terms are Net 30 (Large Business) or Net 15 (Small Business) days upon final acceptance of the product/service.” RFP510922.pdf, page 8

Key terms

Who can bidOpen to all offerors; no set-asideThe SAM.gov record shows set-aside as Not stated. NAICS 333517 size standard is 500 employees.RFP510922.pdf, page 1
Contract periodNot stated; delivery within 13 to 14 months after orderThe RFP lists the subcontract period of performance as TBD.RFP510922.pdf, page 5
How they chooseLowest price technically acceptable (LPTA)The RFP also says your affordability response is part of the evaluation.RFP510922.pdf, page 7
How to submitEmail to Procurement Officer Rian Lewis at lewisgr@ornl.govThe notice does not give a full submission method. The RFP asks for proposals in MS Excel, MS Word or PDF.Amendment 1.pdf, page 1
Questions dueFriday, November 20, 2026, 3:00 PM EST (passed)Questions must now go to the Procurement Officer in writing.RFP510922.pdf, page 1
Contract typeFirm fixed price subcontractPrices must be in U.S. dollars on a firm fixed price basis.RFP510922.pdf, page 6

How to respond

  1. Use the amended deadline of Monday, December 7, 2026, 4:00 PM EST, not the November 27 date on the SAM.gov record.
  2. Email your offer to Procurement Officer Rian Lewis at lewisgr@ornl.gov. The notice does not state a file size limit. The RFP asks for MS Excel, MS Word or PDF format.
  3. Include the signed acknowledgment of Amendment 1 in your final proposal, or the offer may be rejected.
  4. Include a technical proposal that confirms delivery in 13 to 14 months, a firm fixed price U.S. dollar price proposal, and a separate Exceptions/Non-Compliance section.
  5. Include the representations required by the RFP (Attachment D if your proposal is over $15,000) and a quality manual showing an adequate quality control program. Page limit: Not stated.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Total value or budget for the subcontract, shown only as $TBD.
  • Start and end dates of performance, shown as TBD, and the exact delivery date.
  • Whether a site visit or pre-bid meeting is required.
  • Whether a non-Mazak domestic equivalent is acceptable, and what proof ORNL would need.
  • Warranty and service support terms for the system, which the SOW does not state.
  • Whether the SAM.gov record will be updated to the December 7 due date.

Notice text

UT-Battelle LLC's Defense Manufacturing Program Office (DMPO) requires an integrated manufacturing system consisting of subtractive machining, wire arc additive manufacturing (WAAM), blank machine stations, pallet changer modules, and a two-level PALLETECH system with associated engineering and interfaces per Attachment A - Statement of Work - Mazak FUSE System or domestic equivalent.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 24, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of Energy by email

Each morning we'll send the new solicitations and sources-sought notices from Department of Energy, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy