1. Opportunities
  2. Department of the Interior
  3. Departmental Offices
  4. 140FF027Q0027

Deck handrail and stair replacement, Fergus Falls, MN

Replace about 130 feet of deck handrail and a 23 by 4 foot stairway at the Prairie Wetlands Learning Center in Fergus Falls, MN, with new aluminum rail and a prefabricated steel stair.

Official title: Y--MN FERGUS FALLS WMD HANDRAIL STAIRS

Deadline
Nov 23, 12:00 PM ET
3 days left
Who can bid
Small businesses
Size standard for NAICS 236220: $45 million in average annual receipts · Who qualifies
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: Fws Contracting Activity

What they're buying

Work is allowed only from June 5 to August 31, 2027, and the stair and rail materials must reach the site before June 5, 2027.

Top catches

Two different submission emails
“christa_garrigas@yahoo.com” Sol_140FF027Q0027.pdf, page 1

Section L.1.2 says to email christa_garrigas@ios.doi.gov, but SF 1442 block 8 shows a yahoo address. Confirm the correct address with the contracting officer before you send, because a quote sent to the wrong address may not count.

Old due date still on the form
“11/13/2026” Sol_140FF027Q0027.pdf, page 1

SF 1442 block 13 still shows 11/13/2026, which has passed. Amendments 0002 and 0003 set Monday, 23 November at 12:00pm EST, so plan to that date and time.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 19, 2026 from the notice and 15 of 17 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Remove about 130 feet of existing deck handrail and the existing 23'x 4' wide stairway.
  • Install a new aluminum two-line guardrail, 43 inches high, with fascia-mounted brackets and AAMA 2604 powder coat.
  • Furnish and install a prefabricated steel stair system on concrete pad foundations, hot-dip galvanized and powder coated.
  • Replace about 130 linear feet of 2x14 cedar fascia. The Q&A allows a two-piece assembly.
  • Provide barricades, signs, utility locating, asphalt cutting and removal, and site restoration, with the deck closed off completely.
  • Fabricate and deliver all stair and handrail materials to the site before June 5, 2027.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Two different submission emails. Section L.1.2 says to email christa_garrigas@ios.doi.gov, but SF 1442 block 8 shows a yahoo address. Confirm the correct address with the contracting officer before you send, because a quote sent to the wrong address may not count.
  • Old due date still on the form. SF 1442 block 13 still shows 11/13/2026, which has passed. Amendments 0002 and 0003 set Monday, 23 November at 12:00pm EST, so plan to that date and time.
  • Schedule conflicts with work window. SF 1442 item 11 says 60 calendar days after award, but work is allowed only from June 5 to August 31, 2027, and materials must arrive before June 5. Build fabrication lead time into your schedule and ask the contracting officer which schedule governs.“It is imperative that all stair and handrail materials be fabricated and delivered to the site prior to the June 5th, 2027 construction start date.” A05_Statement_of_work.docx
  • Payment protection due in 10 days. You must post a payment bond or irrevocable letter of credit for 100 percent of the contract price within 10 days of award, covering the work period plus one year. Price that cost into your quote and line up the surety or bank before you bid.“The submission of the payment protection is required within 10 days of contract award.” Sol_140FF027Q0027.pdf, page 17
  • Minnesota-registered engineer required. The aluminum rail design and the steel stair drawings must be sealed by an engineer registered in Minnesota. Price that engineering into your quote, or decide not to bid if you cannot find one.“Yes, they have to be registered to work in the state the work is being performed.” Responses_to_Bidder_s_Questions_0003.docx
  • Site conditions not verified. The Q&A adds a requirement to visit the site before bidding, and the site visit date has passed. No structural drawings or stair footing details were provided, so contact the District Manager at (218) 736-0627 to inspect and price for hidden conditions.“The Contractor shall visit the site to determine actual site conditions prior to submitting bids.” Responses_to_Bidder_s_Questions_0003.docx

Key terms

Who can bidSmall businesses only (total small business set-aside)NAICS 236220. The size standard is not stated in the notice.SAM.gov record
Contract periodWork allowed June 5 to August 31, 2027SF 1442 item 11 says 60 calendar days after award. See catches.A05_Statement_of_work.docx
How they chooseLowest evaluated price that is fair and reasonable; price onlyAward is made without discussions. There are no other evaluation factors.Sol_140FF027Q0027.pdf, page 38
How to submitBy email, as stated in Section L.1.2Section L gives christa_garrigas@ios.doi.gov. SF 1442 block 8 gives a different address. See catches.Sol_140FF027Q0027.pdf, page 35
Questions due11/10/2026 at 12:00 pm EST (passed)This date has passed. Use the Q&A attachment for answers already given.Sol_140FF027Q0027.pdf, page 35
Contract typeFirm fixed price, lump sum constructionThe base bid is paid as one lump sum for the whole job.Sol_140FF027Q0027.pdf, page 38
Site visit11/9/26 at 12:30pm local time (passed)Questions were not taken at the visit. The SOW also lets you inspect by contacting the District Manager.Sol_140FF027Q0027.pdf, page 3

How to respond

  1. Confirm the email address with the contracting officer, Christa Garrigas, first. Section L.1.2 says christa_garrigas@ios.doi.gov, and SF 1442 block 8 shows christa_garrigas@yahoo.com.
  2. Fill in SF 1442 blocks 14 through 20C, list amendments 0001, 0002 and 0003 with their dates, and sign the offer. Section L also requires your representations and certifications, which can be confirmed as already in SAM.gov.
  3. Complete the Section B quote schedule for item 0001, Replace handrail and stairs, as one lump sum. The price must include labor, materials, equipment, overhead and profit.
  4. Email the complete package to the confirmed address before Monday, 23 November 2026 at 12:00pm EST. If you cannot use the Invoice Processing Platform (IPP) for invoices, include your written waiver request with the quote.

Attached files

  • Sol_140FF027Q0027_Amd_0001.pdfAmendment 0001 adds the aluminum handrail installation attachment. You must read it and acknowledge it in your offer. Read.
  • Responses_to_Bidder_s_Questions_0003.docxThese are the government answers to bidder questions, and they change parts of the specifications. You must read them before pricing. Read.
  • A06_Prefabricated_Steel_Stair_System.docxThis is the specification for the prefabricated steel stair, including foundations, engineer stamps and finish. You must read it. Read.
  • A06_Aluminum_Handrails_Install_0001.docxThis is the installation specification for the new aluminum guardrail, including engineering and finish rules. You must read it because these rules affect price. Read.
  • Sol_140FF027Q0027.pdfThis is the SF 1442 offer form and Sections B through M. You must complete the offer blocks, sign, and fill in the Section B price schedule. Read.
  • Sol_140FF027Q0027_Amd_0003.pdfAmendment 0003 adds the bidder Q&A and a site access pathway map and sets the 12:00pm EST time. You must read it and acknowledge it in your offer. Read.
  • A06_Submittal_Register.docxThis is the list of required shop drawings and submittals. You must prepare these items after award. Read.
  • A05_Statement_of_work.docxThis is the statement of work with the work list, access limits, safety rules and site contact. You must read it; no form is filled in. Read.
  • Sol_140FF027Q0027_Amd_0002.pdfAmendment 0002 moves the due date to Monday, 23 November and restates item 00010. You must read it and acknowledge it in your offer. Read.
  • A06_Project_Coordination.docxThis covers superintendence, change orders, the preconstruction conference and progress meetings. You must read it. Read.
  • A06_Aluminum_Handrails.docxThis is the demolition specification for removing the existing handrail and steel stair. You must read it and document the removal. Read.
  • A06_Drawings.pdf Scanned image, not read.
  • A06_Site_Map_Access_Pathways_0003.pdf Scanned image, not read.
  • A06_Definitions_and_Standards.docxThis covers codes, means and methods, and permits. You must read it and obtain any permits you need at your own cost. Read.
  • B03_Wage_Determination.pdfThese are the Minnesota Davis-Bacon wage rates for Otter Tail County. You must pay these rates and submit certified payrolls. Read.
  • A06_Submittals.docxThese are the submittal rules, including submittals due within 21 days of award and delivery tickets. You must read it. Read.
  • A06_Closeout.docxThis covers final inspection, record drawings and a one-year warranty. You must read it and plan for these closeout tasks. Read.

Not stated in what we read

  • I could not review A06_Drawings.pdf or A06_Site_Map_Access_Pathways_0003.pdf because they are scanned images. You must read both before you price the work.
  • The size standard for NAICS 236220 is not stated in the notice. Check that your company qualifies before you bid.
  • SF 1442 item 12a shows YES and NO, and the text does not show which box is marked. Ask whether bonds are required.
  • The actual contract value is not stated. The notice gives only a magnitude range of $100,000 to $250,000.
  • The materials staging area is not set. The Q&A says it will be discussed at the Preconstruction Conference, and the date and place of that conference are not stated.

Notice text

MN FERGUS FALLS WMD HANDRAIL STAIRS

As published on SAM.gov. Attachments are listed there; FedLook does not read them yet.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 19, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Departmental Offices by email

Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy