  2. Types of government contracts (FAR Part 16)

Types of government contracts (FAR Part 16)

Updated

Every government contract has a contract type: the rule for how the price is set and who carries the risk if costs run higher than expected. Part 16 of the Federal Acquisition Regulation (FAR) describes the different contract types agencies may use, and a type the FAR doesn’t describe can’t be used without a deviation (FAR 16.102). The FAR groups them into two broad categories, fixed-price and cost-reimbursement (FAR 16.101), and adds time-and-materials contracts and a few special instruments. Choosing the appropriate contract type is part of every procurement and generally a matter for negotiation; the goal is reasonable contractor risk and the greatest incentive for efficient and economical performance (FAR 16.103).

Check the type of contract before you price: every notice on FedLook links to the official solicitation on SAM.gov, which usually states the contract type. Browse open notices.

Contract types at a glance

Each type of government contract splits the cost risk differently:

Type How the price works Who carries cost risk FAR
Firm-fixed-price (FFP) One price, not adjusted for actual costs The contractor 16.202
Fixed-price with economic price adjustment (FP-EPA) Fixed, but revised up or down on stated triggers Mostly the contractor 16.203
Fixed-price incentive (FPI) Profit adjusted by a formula, under a price ceiling Shared 16.403
Cost-plus-fixed-fee (CPFF) Allowable costs plus a fee fixed at award The government 16.306
Cost-plus-incentive-fee (CPIF) Allowable costs plus a fee adjusted by a formula Shared 16.304
Cost-plus-award-fee (CPAF) Allowable costs, a base fee and an award fee The government 16.305
Time-and-materials (T&M) Fixed hourly rates plus materials, up to a ceiling Mostly the government 16.601
Labor-hour Like T&M, without materials Mostly the government 16.602

Fixed-price contracts

Fixed-price contracts fix the price, or the formula for adjusting it, at contract award.

A firm-fixed-price contract provides for a price that isn’t adjusted for the contractor’s cost experience in performing the contract. This fixed-price contract type puts the maximum risk on the contractor, who keeps the savings when costs come in low and absorbs the loss when they don’t (FAR 16.202-1). It fits commercial products and services and other purchases with reasonably definite specifications when a fair price can be set, for example through adequate price competition (FAR 16.202-2).

A fixed-price contract with economic price adjustment lets the price move up or down on contingencies stated in the contract: changes in published prices, in the actual cost of labor or material, or in a named cost index (FAR 16.203-1).

A fixed-price incentive contract adjusts profit and sets the final contract price by a formula based on final negotiated cost against a target cost, and the final price can’t go above a ceiling negotiated at the start (FAR 16.403).

Two rules decide where the government uses fixed-price contracts:

  • Contracts from sealed bidding must be firm-fixed-price or fixed-price with economic price adjustment (FAR 16.102).
  • So must contracts for commercial products and commercial services, with a narrow exception for time-and-materials and labor-hour work on commercial services (FAR 12.207).

Cost-reimbursement contracts

A cost-reimbursement contract provides for payment of the contractor’s allowable costs, up to a ceiling set in the contract, and in most forms a fee on top (FAR 16.301-1). It shifts most of the cost risk to the government, so government agencies may use one only when the requirement can’t be defined well enough for a fixed price, or when costs can’t be estimated accurately enough (FAR 16.301-2). Before award, the agency needs a written acquisition plan approved above the contracting officer, government resources to manage the contract, and a contractor whose accounting system is adequate for tracking contract costs. Cost-reimbursement contracts can’t be used for commercial products or services (FAR 16.301-3).

Form Fee
Cost No fee; may suit research with nonprofit institutions (FAR 16.302)
Cost-sharing No fee, and only an agreed share of costs is reimbursed (FAR 16.303)
Cost-plus-fixed-fee The parties fix the fee at award; it doesn’t change with actual cost (FAR 16.306)
Cost-plus-incentive-fee A target fee adjusted by a formula comparing allowable costs to target costs (FAR 16.304)
Cost-plus-award-fee A base fee, which can be zero, plus an award fee based on the government’s evaluation of contract performance (FAR 16.305)

On cost-plus-fixed-fee contracts the fee is capped: 15% of estimated cost for experimental, developmental or research work, 6% of the estimated construction cost for architect-engineer design work, and 10% for everything else (FAR 15.404-4). One form is banned outright: the cost-plus-a-percentage-of-cost system, where the fee grows with spending (FAR 16.102).

Time-and-materials and labor-hour contracts

A time-and-materials (T&M) contract provides for buying supplies or services on the basis of direct labor hours at fixed hourly rates, which include wages, overhead, general and administrative expenses and profit, and materials at cost. A labor-hour contract is the same without materials (FAR 16.602). Because the contractor has no built-in reason to control hours, the rules are tight (FAR 16.601):

  • a T&M contract may be used only when the extent or duration of the work, or its costs, can’t be estimated with reasonable confidence;
  • the contracting officer must sign a determination that no other type is suitable;
  • the contract includes a ceiling price, and the contractor goes over it at its own risk;
  • the government must watch performance closely.

Indefinite-delivery contracts and other instruments

Indefinite-delivery contracts allow the government to order supplies or services when the exact timing or quantities aren’t known in advance. The FAR has three types (FAR 16.501-2):

  • A definite-quantity contract covers a set quantity over a fixed contract period, with deliveries scheduled as orders come in.
  • A requirements contract fills all of an agency’s actual needs for specific supplies or services during the contract period from one contractor, and the government places orders as needs arise.
  • An indefinite-quantity contract, the IDIQ contract, sets a minimum and a maximum. It must require the government to order at least the minimum, and agencies must, to the maximum extent practicable, prefer multiple-award contracts (FAR 16.504). See IDIQ contracts.

Three more instruments come up often:

  • With a letter contract, the government may let a contractor start work immediately, before the full contract is settled (FAR 16.603-1). A letter contract has to be turned into a final, definitive contract, normally within 180 days or before 40 percent of the work is done, whichever comes first (FAR 16.603-2).
  • Basic ordering agreements hold contract terms, a description of the supplies or services and pricing methods for future contracts (orders), but they aren’t contracts and don’t promise any orders (FAR 16.703).
  • Blanket purchase agreements set up charge accounts with suppliers for repeat purchases. See blanket purchase agreements.

What the contract type means for your bid

The contract type places cost risk between the government and contractor, so for government contractors the type of contract shapes how you price:

  • Fixed-price: your price is your promise. Build in the risks you can see; the government won’t cover overruns.
  • Cost-reimbursement: on a cost-type contract you need an accounting system that can separate allowable contract costs, and a CPFF fee is capped.
  • Time-and-materials: you’re paid by the hour up to the ceiling. Hours over the ceiling are on you unless the ceiling is raised.

The FAR overhaul

The FAR is being rewritten under the Revolutionary FAR Overhaul, and agencies have issued deviations to apply overhauled parts. Section numbers in a solicitation may therefore differ from the ones above, which follow the FAR as published on acquisition.gov (FAC 2026-01).

Next step

FedLook lists open federal opportunities by agency, state and industry, adds plain-English summaries to more notices every day, and sends free alerts when something new matches your field.

Frequently asked questions

What are the four types of government contracts?

FAR Part 16 groups contract types into two broad categories: fixed-price and cost-reimbursement. Lists of four usually add time-and-materials (with labor-hour) and indefinite-delivery contracts such as IDIQs. Part 16 also covers incentive contracts, letter contracts and agreements such as basic ordering agreements.

What is a firm-fixed-price contract?

A contract whose price is not adjusted for the contractor's actual costs. The contractor carries the maximum risk and keeps any savings (FAR 16.202-1).

What is a cost-plus-fixed-fee contract?

A cost-reimbursement contract that pays the contractor's allowable costs plus a fee fixed when the contract is awarded. The fee generally can't exceed 10% of estimated cost, or 15% for research and development work (FAR 16.306, 15.404-4).

Is a cost-plus-percentage-of-cost contract allowed?

No. Federal law prohibits the cost-plus-a-percentage-of-cost system, and prime contracts other than firm-fixed-price must prohibit such subcontracts too (FAR 16.102(c)).

Can agencies buy commercial products on a cost-reimbursement contract?

No. Commercial products and services are bought on firm-fixed-price or fixed-price with economic price adjustment contracts. Time-and-materials and labor-hour contracts are allowed for commercial services only under extra conditions (FAR 12.207, 16.301-3).

When is a time-and-materials contract used?

Only when the extent or duration of the work, or its costs, can't be estimated with reasonable confidence. The contracting officer must document that no other contract type is suitable and include a ceiling price the contractor exceeds at its own risk (FAR 16.601).