Transformer fluid testing at Glen Canyon Power Plant, AZ

You would test oil samples from about 28 transformers at the Glen Canyon Power Plant in Page, Arizona, and report results for each sample.

Official title: H--GC TRANSFORMER FLUID TESTING

Deadline
Nov 30, 10:00 AM ET
5 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: Reclamation Contracting Activity

What they're buying

The contract is a 12-month base year plus four 12-month options, running 2027 to 2031. The transformer counts in the documents do not agree, so the price basis is unclear.

Top catches

Transformer counts conflict
“Natural ester fluid: annual testing required for 11 transformers” Sol_140RR027Q0037.pdf, page 29

The revised PWS lists 20 ester and 14 silicone transformers. The older PWS in the main file lists 11 and 11. Schedule B prices 20, 14 and 15 units. Ask the contracting officer which count to price before you submit.

Extra mineral oil testing unpriced
“we have allowed an extra cushion for extra testing if” A02_PWS_REVISED_2026_11_20_0001.pdf, page 1

The PWS has a stray note that extra testing may be needed, but Schedule B has no price line for it. Ask how extra tests will be paid, or price a per-test rate in your quote.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 21, 2026 from the notice and 4 of 4 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Deliver sampling test kits within five business days of a government request, each with serialized bottles and syringes, forms, and return packaging.
  • Run lab tests on every sample under the ASTM methods in PWS section 5, for natural ester, silicone and mineral oil fluids.
  • Test 20 natural ester and 14 silicone transformers each year, plus one mineral oil sample each month, per the revised PWS. Other documents give different counts.
  • Send one electronic report per sample with graphical and tabular results, historical trend data, and collection and analysis dates.
  • Keep ISO/IEC 17025:2017 accreditation for the whole performance period and redo any test that needs retesting at no cost to the government.
  • Price the base year and all four option years on the Schedule B table, with a grand total.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Transformer counts conflict. The revised PWS lists 20 ester and 14 silicone transformers. The older PWS in the main file lists 11 and 11. Schedule B prices 20, 14 and 15 units. Ask the contracting officer which count to price before you submit.
  • Extra mineral oil testing unpriced. The PWS has a stray note that extra testing may be needed, but Schedule B has no price line for it. Ask how extra tests will be paid, or price a per-test rate in your quote.
  • ISO 17025 accreditation required. You must hold current ISO/IEC 17025:2017 lab accreditation for the whole contract and show proof when asked. If you do not hold it, do not bid, or ask the contracting officer whether another lab can be used.“The Contractor shall maintain a current ISO/IEC 17025:2017 laboratory accreditation throughout the period of performance” Sol_140RR027Q0037.pdf, page 31
  • Email only, active SAM needed. Send the quote only by email to Kelly Cook, using the exact subject line. Your SAM registration must be active when you submit, or the quote is not considered. A quote missing the price table may be rejected.“Quotes submitted by entities without an active SAM registration will not be considered.” Sol_140RR027Q0037.pdf, page 28
  • Signed paper invoice needed. Each invoice needs a paper copy on your letterhead with the COR's original signature, sent with the IPP upload. The COR is named only at award, so plan how you will get that signature in time.“Failure to attach the signed invoice will result in significant delay or rejection of the payment request.” Sol_140RR027Q0037.pdf, page 8
  • Payment waits on verified results. Payment waits until all testing is done, all reports are received and the government verifies every result. Retesting after a problem is at your cost. Plan cash flow for that delay.“The Government will not authorize payment until all required testing has been completed, all test reports have been received, and all results have been verified by the Government.” Sol_140RR027Q0037.pdf, page 32

Key terms

Who can bidAny business (full and open); no set-aside statedNotice says unrestricted. SAM record lists set-aside as Not stated. You must have an active SAM registration to submit.Sol_140RR027Q0037.pdf, page 1
Contract periodBase year 2027, plus four 1-year options to 12/31/2031Dates begin at award and may be adjusted in the awarded contract.Sol_140RR027Q0037_Amd_0001.pdf, page 2
How they chooseBest value by comparative evaluation, with price and other stated factorsOption prices are added to the base price for evaluation. The text we reviewed lists no non-price factors.Sol_140RR027Q0037.pdf, page 3
How to submitEmail only to kelly_cook@ios.doi.govUse the subject line Transformer Fluid Testing Quote.Sol_140RR027Q0037.pdf, page 28
Contract typeFirm-fixed-priceThe government plans to award a firm fixed price contract.Sol_140RR027Q0037.pdf, page 1

How to respond

  1. Confirm your SAM registration is active now, because it must be active when you submit.
  2. Fill in the Schedule B table with a unit price and total for the base year and each option year, plus a grand total. The notice says an incomplete quote may be unacceptable.
  3. Add sample reports (at least one showing all tests for ester, silicone and mineral fluids), relevant certifications, and the number of years you have tested transformer fluids.
  4. Email everything to kelly_cook@ios.doi.gov with the subject line Transformer Fluid Testing Quote before 10:00 am Eastern on Monday, November 30, 2026. Acknowledge amendment 0001 in your quote.
  5. Before the deadline, ask the contracting officer about the transformer counts and how extra mineral oil testing is priced, since the answers change your price.

Attached files

From SAM.gov. Download links open the original files.

  • Sol_140RR027Q0037.pdfThe main combined solicitation with terms, clauses, submission rules and the PWS. You must read it and send the price table and certifications it asks for. We could review only part of this file, so read the rest. Read in part.
  • C02_CS_TRANSFORMER_FLUID_TESTING_2026_11_12.pdfA partial copy of the same solicitation, dated 11/12 in its file name. It does not say whether it is the current version, so use it only as a cross-check against the main file and the amendment. Read in part.
  • Sol_140RR027Q0037_Amd_0001.pdfAmendment 0001 dated 11/12/2026 that changes the PWS and states the period of performance. You must acknowledge receipt of it in your quote. Read in part.
  • A02_PWS_REVISED_2026_11_20_0001.pdfThe revised PWS dated 11/20/2026, with the latest transformer counts and test rules. You must price from it. We could review only part of it, up to section 8, so read the rest. Read in part.

Not stated in what we read

  • Which transformer counts govern pricing, since the documents conflict.
  • Estimated value or budget for the contract.
  • Whether extra mineral oil testing is included in the price, and how it is paid.
  • Size standard for NAICS 541380 and whether any set-aside applies. The SAM record says Not stated.
  • Deadline for questions to the contracting officer.
  • Any non-price evaluation factors, and whether sample reports are required or only requested.

Notice text

TRANSFORMER FLUID TESTING

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 21, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Departmental Offices by email

Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy