1. Opportunities
  2. Department of Transportation
  3. Federal Aviation Administration
  4. 6973GH-26-R-00082

HQ building electrical and HVAC upgrades, Oklahoma City, OK

The FAA is buying mechanical and electrical upgrades in the Headquarters Building at the Mike Monroney Aeronautical Center in Oklahoma City, OK, with six optional add-on items for ductwork, lighting controls, raceways, carpet and paint, fire alarm, and emergency radio coverage.

Official title: Headquarters Building (HQB) Mechanical and Electrical Upgrades at the Mike Monroney Aeronautical Center (MMAC), Oklahoma City, OK.

Deadline
Dec 4, 4:00 PM CT
8 days left
Who can bid
Any business
Registered in SAM.gov · How to register
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Oklahoma City, OK
Buyer: 6973GH Franchise Acquisition Svcs

What they're buying

The base contract runs 887 calendar days after notice to proceed.

Top catches

Two different due times
“5:00 pm, Central Time on Friday, December 4,” Amendment 0008.pdf, page 3

SAM.gov shows 4:00 PM on December 4, but Amendment 0008 says 5:00 PM Central. Plan to submit by 4:00 PM Central and ask the contracting officer in writing which time applies.

Past performance can disqualify you
“will eliminate the offeror from consideration for contract award” Amendment 0002.pdf, page 6

To be eligible, you and both proposed subcontractors need High, Moderate, or Satisfactory past performance confidence. Little or No Confidence removes you from award, so check your references and subcontractor records before you commit.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 21 of 40 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Base bid: mechanical and electrical upgrades in the HQ building, including new electrical rooms, an emergency generator with gas service, and VAV box and AHU-1 valve work.
  • Six additive bid options: HVAC ductwork, lighting controls, in-slab raceway conductors, carpet and wall base with paint, fire alarm upgrade, and new ERRCS emergency radio coverage.
  • Hydronic system drain, flush, strainer cleaning and refill, plus hydrostatic testing at 1.5 times design pressure, minimum 100 psi, held 15 minutes.
  • Waste plan within 15 days after notice to proceed, and diversion of at least 55 percent of non-hazardous waste by weight.
  • Pre-work and post-work test and balance for the air handling units.
  • Surplus soil sampling and testing, with approval before any soil leaves the site; unsuitable soil goes to a special-waste landfill.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Two different due times. SAM.gov shows 4:00 PM on December 4, but Amendment 0008 says 5:00 PM Central. Plan to submit by 4:00 PM Central and ask the contracting officer in writing which time applies.
  • Past performance can disqualify you. To be eligible, you and both proposed subcontractors need High, Moderate, or Satisfactory past performance confidence. Little or No Confidence removes you from award, so check your references and subcontractor records before you commit.
  • Key personnel must be your staff. Your construction project manager and superintendent each need seven years in that role and two completed multi-discipline projects in the past seven years, and both must be employed by you. If they do not meet this, your technical volume is rated unacceptable, so confirm each person's record before you submit.“Must be employed by the offeror” L.12 TECHNICAL ACCEPTABLE - UNACCEPTABLE EVALUATION OF KEY PERSONNEL.pdf, page 1
  • Performance period conflicts. Addendum 01 sets 887 calendar days after notice to proceed, but a Q&A question cites a 365-day limit. The Q&A answer points back to Addendum 01, so price 887 days unless the contracting officer confirms otherwise in writing.“complete the entire Work ready for occupancy and use not later than 887 days after issuance of Notice to Proceed.” Addendum 01 Full Document.pdf, page 2
  • After-hours work and outage notice. Demolition is limited to 6 PM to 6 AM on weekdays, and other work outside 6 AM to 6 PM needs advance approval. Outages need seven working days notice, so price the after-hours and weekend labor.“Prior to any outage or shutdown, seven (7) working days notification must be made” Addendum 01 Full Document.pdf, page 4
  • Bonds due soon after award. The form says performance and payment bonds are required, with 7 calendar days after award to furnish them. Ask your surety now whether it can issue both bonds on that timeline.“The offeror agrees to furnish any required performance and payment bonds.” Solicitation Offeror and Award Construction.pdf, page 2

Key terms

Who can bidOpen to all businesses; no set-asideThe NAICS 236220 size standard is based on dollars, per Q&A 90.SAM.gov record
Contract period887 calendar days after notice to proceedYou must begin within 10 calendar days of the award notice. A Q&A question cites a 365-day limit.Addendum 01 Full Document.pdf, page 2
How to submitElectronically, Volume II technical and Volume IV cost and priceThe email address or portal is not stated in the text provided.Questions Answer Log 6-2-26.pdf, page 8
Questions dueClosed: 5:00 p.m. CT, June 3, 2026Amendment 0004 set a firm cut-off. No further questions are considered after that time.Amendment 0004.pdf, page 2
Contract typeConstruction; lump-sum base bid plus six optional itemsBid options are additive and may be awarded in any order, per Q&A 25.Questions Answer Log 6-2-26.pdf, page 12
Site visitHeld April 23, 2026; no new visit statedQ&A 91 asks whether subcontractors had to attend the mandatory site visit, and the answer is not clear.HQ BUILDING MECHANICAL AND ELECTRICAL UPGRADES SITE VISIT SIGN IN.pdf, page 1

How to respond

  1. Where to send: Not stated in the text provided. Confirm the submission address or portal with the contracting officer, Cynthia Cooper, at 405-954-2601 before the deadline.
  2. Volume II technical proposal: submit electronically, with key personnel resumes on SIR Attachment 17 (up to 25 pages, optional). It is due Friday, December 4, 2026, and the earlier time of 4:00 PM Central is the safer target.
  3. Volume I: complete and notarize Attachments 15 and 16 and include them with your proposal, per Q&A 135.
  4. Volume IV cost and price: complete Attachment 1, Section B and Attachment 14 even if your price did not change. Due Friday, December 18, 2026, 5:00 PM Central.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • How proposals are judged and whether price is weighed, scored, or used as a pass-fail test.
  • The estimated contract value; the total in Attachment 1 has no amount.
  • Whether a bid bond (offer guarantee) is required; item 13B is unclear and Q&A 92 mentions a bid bond.
  • The address or portal where proposals must be sent.
  • Amendment 0001 text, including the minimum offer acceptance period, is not in the text provided.
  • Attachment 2 (design analysis) could not be read and Attachment 9 is scanned, so you must review them on SAM.gov.

Notice text

SIR 6973GH-26-R-00082 and Attachments 1 through 16 are provided for potential offerors Amendment 0001 is hereby issued to to provide the Site Visit Attendees, provide Addendum 01 to the Specifications and Drawings included with this SIR, incorporate new AMS Clause 3.6.2-50, Implementation of E.O. 14398(INTERIM April 2026) and incorporate revised AMS Clauses 3.6.1-4 Small Business Subcontracting Plans (INTERIM April 2026) and 3.10.1-15, Changes-Construction, Dismantling, Demolition, or Removal of Improvements (INTERIM April 2026), revise the Minimum Offer Acceptance Period on Page 1, Block 11 of the SIR and AMS Clause 3.2.2.3-2, Minimum Offer Acceptance Period, revise the date for submission of Questions and extend the closing date of the SIR. Amendment 0002 is hereby issued to revise Provision M.3 RELEVANT EXPERIENCE AND PAST PERFORMANCE EVALUATION (REVISED MAY 15, 2026).

Amendment 0003 is hereby issued to incorporate Amendment 0003, Attachment 1 - Questions and Answers, Attachment 2 - Addendum 02, Attachment 3 - Asbestos Abatement Information, Attachment 4 - HQB Furniture Information, and Attachment 5 - HQB Requested Photos. Amendment 0004 is hereby issued to remove Pages 1 and 2 of the Original SIR, Solicitation, Offer and Award, and incorporate New Pages 1 and 2, Solicitation, Offer and Award (Construction, Alteration, or Repair) attached.

In addition, Amendment 0004 provides New Questions and Answers 160 through 165 (attached), establishes a firm cut-off date for submission of questions and extends the proposal due date to June 5, 2026. NOTE: OFFERORS ARE TO SUBMIT NEWLY INCORPORATED PAGES 1 AND 2, SOLICITATION, OFFER AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR) WITH THEIR PROPOSAL. Amendment 0005 is hereby issued to extend the proposal due date to June 10, 2026. Amendment 0006 is hereby issued to provide Questions and Answers 1 through 192, including new Questions and Answers 166 through 192.

The proposal due date remains June 10, 2026. Amendment 0007 is hereby issued to incorporate Addendum 03, HQB Mechanical and Electrical Upgrades – SIR - 6973GH-26-R-00082, dated June 5, 2026. Amendment 0008 is hereby issued to revise Provision L.3 INSTRUCTIONS FOR PREPARATION AND SUBMISSION OF PROPOSALS, add new Provision L.12 TECHNICAL ACCEPTABLE/UNACCEPTABLE EVALUATION OF KEY PERSONNEL and request revised Cost Price Proposals. NOTE: New Volume II Technical Proposals are due on December 4, 2026 and Revise Cost/Price Proposals are due on December 18, 2026.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 26, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Federal Aviation Administration by email

Each morning we'll send the new solicitations and sources-sought notices from Federal Aviation Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy