1. Opportunities
  2. Department of Defense
  3. Department of the Air Force
  4. HARBSS-2027-01

Fitness building supplies, Homestead Air Reserve Base, FL

Buy and deliver materials and a pre-engineered building package, rent construction equipment, and install a steel picket fence for an outdoor fitness facility at Building B-389, Homestead Air Reserve Base, Florida.

Official title: Outdoor Fitness Facility, Building 389— Supply, Delivery, and Limited Installation Support

Deadline
Nov 27, 12:00 PM ET
2 days left
Who can respond
Any business
Market research, not a bid
Last time
$521K
Likely Ske Support Services GMBH
Place
Homestead, FL
Buyer: FA6648 482 LSS LGC

What they're buying

The Air Force RED HORSE team does most construction, and this sources sought is for market research only, so the contract length is not stated.

Top catches

Two different deadlines listed
“Response Due Date/Time: November 26, 2026, 5:00 PM EST” Notice text

The notice body says November 26 at 5:00 PM EST. Amendment 4 says Friday, November 27 at 12:00 pm EST, and amendments override. Send before 5:00 PM EST on November 26 so either version is met.

BOM rows have no item names
“64 | 1 | 60 DAY RENTAL | 0” Attachment 2 Outdoor Fitness Facility BOM Template.xlsx

Several BOM rows show only a number, a quantity and a rental term, with no item name. All cost cells are blank. Ask the contact named in the notice what these rows are before you price the list.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 25, 2026 from the notice and 4 of 4 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Procure and deliver all materials on the Government bill of materials, with each submittal approved in writing before you order.
  • Furnish a pre-engineered building package with signed and sealed shop drawings, a 20-year material warranty and a Miami-Dade Notice of Acceptance.
  • Furnish rental construction equipment on site, fueled and ready to run, for the BOM rental periods, including a telehandler, skid loaders, scissor lifts, a roller and a mini excavator.
  • Install a steel picket fence at least five feet from the roof overhang, with two single doors, one double equipment door and lockable hardware.
  • Restore disturbed areas with St. Augustine sod.
  • If the building has no built-in lightning protection, furnish and install a copper system with third-party certification.

Who supplied it lately

$521K

on a recent contract for the same kind of product: Ske Support Services GMBH. It ends Dec 6, 2026.

Matched in USAspending.gov by agency, NAICS and product code; notices rarely name the supplier.

What to watch for

  • Two different deadlines listed. The notice body says November 26 at 5:00 PM EST. Amendment 4 says Friday, November 27 at 12:00 pm EST, and amendments override. Send before 5:00 PM EST on November 26 so either version is met.
  • BOM rows have no item names. Several BOM rows show only a number, a quantity and a rental term, with no item name. All cost cells are blank. Ask the contact named in the notice what these rows are before you price the list.
  • Miami-Dade approval needed for building. The building and insulation need a current Miami-Dade Notice of Acceptance and a 20-year material warranty. Confirm that your building source can meet both before you respond.“The SOW requires a minimum 20-year material warranty, a current Miami-Dade Notice of Acceptance for the PEB and insulation” Notice text
  • Base access needs personal data. Workers need base passes, and the access request asks for REAL ID numbers, dates of birth and Social Security numbers. Background checks can take up to 72 hours, so plan staffing with that delay.“This installation has up to 72 hours to complete the background request process.” Attachment 1 KYJM19-9003 Outdoor Fitness SOW Red Horse Project 12 Nov 2026.pdf, page 6
  • Drawings are dated 2020 and mislabeled. Drawing sheets are marked as 65% or 100% design from 2020, and some sheets say gazebo. Ask which drawing set governs the building and fence layout before you price.“GAZEBO FLOOR PLAN - LOW VOLTAGE LIGHTING” Attachment 4 Outdoor Fitness Building B-389 Set of Drawings.pdf, page 19
  • Excavation permits need three weeks. Any excavation needs a base civil engineering permit requested at least three weeks ahead. Build this lead time into your schedule and fence price.“Permit shall be requested at least three weeks before the start of excavation.” Attachment 1 KYJM19-9003 Outdoor Fitness SOW Red Horse Project 12 Nov 2026.pdf, page 4

Key terms

Who can bidCapable commercial sources, including all small-business categoriesNo set-aside is stated on the SAM.gov record.Notice text
How to submitEmail to nika.salemi.2@us.af.milUse the required subject line and number each email.Notice text

How to respond

  1. Plan to send before 5:00 PM EST on November 26, 2026, the earlier date in the notice body. Amendment 4 sets the final close at Friday, November 27, 2026 at 12:00 pm EST.
  2. Email nika.salemi.2@us.af.mil. Use the subject line: Sources Sought Response - Outdoor Fitness Facility B-389 - [Company Name]. Number each email as Email X of X.
  3. Keep the capability statement to 10 pages or fewer, excluding product literature and certifications. Include your UEI, CAGE code if assigned, SAM status and expiration, and business size under NAICS 236220.
  4. Add up to three recent projects from the past five years, a rough-order-of-magnitude estimate split by category, lead times and any proprietary parts clearly marked. Do not send classified information.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated value of the work. You are asked for a planning estimate, but no budget is given.
  • Contract type, set-aside decision and acquisition approach.
  • Period of performance and how long the construction and equipment rentals will run.
  • Whether the BOM lists every item; several rows have no name and costs are blank.
  • Which drawing set governs; the drawings appear to be 2020 design work.
  • Whether and when a solicitation will follow this notice.

Notice text

AMENDMENT 4 The purpose of this amendment is to correct the Response Date Year error on Amendment 3 from November 27, 2027 to November 27, 2026, 12:00 pm EST. This Sources Sought for Market Research Purposes Only will Close Friday, November 27, 2026 at 12:00 pm EST. ---------------------------------------------------------------------------------------------------------- AMENDMENT 3 The purpose of this amendment is to extend the Response Date from November 26 to November 27, 2027, 12:00 pm EST. ---------------------------------------------------------------------------------------------------------- AMENDMENT 2 The purpose of this amendment is to add Attachment 4 Outdoor Fitness Building B-389 Set of Drawings ---------------------------------------------------------------------------------------------------------- AMENDMENT 1 The purpose of this amendment is to add Attachment 3 Spec 26 41 01.0010 Lightning Protection System ----------------------------------------------------------------------------------------------------------- Outdoor Fitness Facility, Building 389— Supply, Delivery, and Limited Installation Support Notice Type: Sources Sought / Market Research Notice Number: HARBSS-2027-01 Contracting Office: 482d CONF/PK Location of Performance: Homestead Air Reserve Base, Florida Response Due Date/Time: November 26, 2026, 5:00 PM EST Response Submission: Nika Salemi, nika.salemi.2@us.af.mil Proposed NAICS Code: 236220, Commercial and Institutional Building Construction Proposed Product Service Code (PSC): 5670 Building Components, Prefabricated 1.

Notice Purpose THIS IS A SOURCES SOUGHT NOTICE ISSUED FOR MARKET-RESEARCH AND PLANNING PURPOSES ONLY. THIS NOTICE IS NOT A SOLICITATION, REQUEST FOR PROPOSAL, REQUEST FOR QUOTATION, INVITATION FOR BID, OR COMMITMENT BY THE GOVERNMENT TO AWARD A CONTRACT. The 482d Contracting Flight, Homestead Air Reserve Base (HARB), FL, seeks information from capable commercial sources, including all small-business socioeconomic categories, to determine the availability and capability of firms that can perform the requirement described in Attachment 1 KYJM19-9003 Outdoor Fitness SOW, Red Horse Project, 12 Nov 2026.

Responses will be used to support acquisition planning, including consideration of the appropriate contract type, acquisition approach, and potential small-business set-aside strategy. The Government will not reimburse respondents for any costs associated with preparation or submission of information in response to this notice. A response to this notice is not required to respond to a future solicitation, if issued. Any future solicitation will be announced separately.

2. Requirement Overview The 482d Contracting Flight, Homestead Air Reserve Base (HARB), FL is conducting market research for the Outdoor Fitness Facility, Building 389 project at Homestead Air Reserve Base (HARB), Florida. The anticipated requirement is primarily for the procurement, delivery, and associated submittals for construction materials and equipment required to support construction of an outdoor fitness facility. Air Force RED HORSE personnel will perform the majority of construction and installation activities.

Contractor installation responsibilities are limited principally to the steel picket fence and, if applicable, a separate lightning-protection system. The contractor would be expected to: Procure and deliver all materials identified in the Government-furnished bill of materials (BOM), Attachment 2 Outdoor Fitness Facility, BOM Template. Furnish the Pre-Engineered Building (PEB) package, including engineered shop drawings and all associated structure materials.

Coordinate concrete-truck deliveries to support Government construction execution. Furnish the specified construction equipment for the required durations, fueled and ready for operation at the work site. Install a new steel picket fence, including site restoration for areas disturbed by fence installation. Install a lightning-protection system if the proposed PEB cannot include a compliant built-in lightning-protection system. The provided BOM identifies, among other materials and equipment, rubber fitness flooring, concrete masonry materials, electrical distribution materials, outdoor fans, motion-activated lighting, concrete, base course, PEB-related items, and construction-equipment rentals.

3. Anticipated Scope 3.1 Material Procurement and Delivery The contractor shall be capable of procuring, delivering, and warranting the materials and equipment identified in the Government-furnished BOM. The contractor shall provide required material and equipment submittals before ordering materials, and the Government will approve final submittals in writing before purchase. Anticipated submittals include: Steel picket fence; PEB signed and sealed shop drawings; Outdoor ceiling fans; Lighting; Smart meter; Electrical panel; Fitness flooring; Bird netting; Material warranty plan, including roof, flooring, and other applicable equipment warranties; and Fence material and labor warranty.

3.2 Pre-Engineered Building Package The contractor shall be capable of providing a complete PEB material package based on Government design drawings, including digitally signed and sealed shop drawings prepared by a Professional Engineer. The PEB package is expected to include, at a minimum: Lifting-rack/support beams; A fixed steel beam with predrilled holes for 25-foot ropes; Toe-hold bars located three inches above the finished floor; Factory coating and painting, with Government-selected colors; Medium-bronze exterior roof panels and manufacturer-standard light interior roof panels; Standing seam metal roofing; Gutters and downspouts; Built-in copper lightning protection, where available; and Black, heavy-duty polyethylene bird netting with ¾-inch mesh meeting or exceeding the specified mesh-quality and break-strength requirements.

The PEB shall be designed in accordance with the SOW’s specified structural and high-velocity-wind requirements. The SOW requires a minimum 20-year material warranty, a current Miami-Dade Notice of Acceptance for the PEB and insulation, and a roof assembly capable of the stated uplift and wind criteria. Zinc-plated metal is prohibited. 3.3 Lightning Protection System — Conditional Installation If a compliant PEB with built-in lightning protection is unavailable, the contractor shall be capable of furnishing and installing a conventional lightning-protection and grounding system following completion of RED HORSE construction activities.

The contractor’s capability should include: Copper lightning-protection materials; Installation shop drawings; UL-listed and labeled components; Fence-bonding connections; Grounding-system testing and test-point documentation; Third-party inspection and written certification by an entity independent of the system designer and installer; and Compliance with the project’s cited lightning-protection requirements. 3.4 Steel Picket Fence Installation and Site Restoration The contractor shall be capable of furnishing and installing a steel picket fence around the outdoor-fitness-facility overhang structure.

The fence must be located at least five feet from the roof overhang and include an accessible, lockable gate/door. The fence-related scope includes required access and equipment doors, hardware, and restoration of disturbed areas using St. Augustine sod. 3.5 Construction Equipment The contractor shall be capable of furnishing the construction equipment identified in the BOM for the stated rental periods or project duration. Anticipated equipment includes a 12,000-pound telehandler forklift, skid loaders with buckets and forks, a water truck, scissor lifts, straight-track manlifts, a double-drum roller, a mini excavator with hammer, a dump truck, and concrete forms with pins.

Equipment shall be delivered to the project site, fueled, and ready for operation. The contractor will not be responsible for subsequent refueling unless otherwise established in a future solicitation. 3.6 Installation Access and On-Site Requirements Potential sources should be capable of working on an active military installation and complying with applicable installation access, identification, safety, security, and operations-security requirements.

For contractor-performed installation work, the contractor must be capable of providing an English-fluent site superintendent who remains on site during contract performance. Excavation, if required, will require coordination and permits before work begins; the SOW specifies that permit requests must be submitted at least three weeks before excavation. Normal anticipated work hours for fence installation are 0730–1630, Monday through Friday, excluding Federal holidays, unless alternate hours are approved in writing.

4. Requested Capability Statement Information Interested firms should submit a capability statement of no more than 10 pages, excluding product literature and certifications. Responses should address the following: Company Information Legal business name; Unique Entity Identifier (UEI); CAGE code, if assigned; SAM registration status and expiration date Physical address; Point of contact, telephone number, and email address; and Identification of any General Services Administration schedule, multiple-award contract, or other contract vehicle the Government could consider, if applicable.

Business size and Socioeconomic Status under the proposed NAICS code(s) Business Size Under Proposed NAICS Code 236220 Small Business Status Small Disadvantaged Business Status 8(A) Business Development Program Status HUBZone Small Business Status Service-Disabled Veteran-Owned Small Business Status Veteran-Owned Small Business Status Women-Owned Small Business Status Economically Disadvantaged Women-Owned Small Business Status Technical Capability Demonstrated capability to procure, deliver, and manage the full BOM; Demonstrated capability to furnish a PEB meeting the project’s engineering, wind-resistance, warranty, and Miami-Dade Notice of Acceptance requirements; Ability to provide shop drawings signed and sealed by a qualified Professional Engineer; Capability to provide construction equipment in the quantities and durations described in the BOM; Capability to install steel picket fencing and restore disturbed site areas; and If applicable, capability to install, test, and obtain independent third-party certification of a lightning-protection system.

Relevant Experience Provide up to three recent projects of similar size, complexity, and technical characteristics completed within the past five years. For each project, identify the customer, location, period of performance, brief scope, total contract value, and a customer point of contact if release is authorized. Schedule and Supply-Chain Information Estimated lead time for PEB engineering, fabrication, and delivery; Estimated lead time for major material categories and equipment rentals; Known supply-chain risks or long-lead items; Ability to coordinate concrete deliveries; and Recommended phasing approach to support RED HORSE construction.

Commerciality and Alternatives Identify whether the proposed supplies are commercial products; Identify any commercially available alternatives that meet or exceed the salient project requirements; Identify material substitutions or specification clarifications that may improve availability, schedule, resiliency, or lifecycle cost; and Clearly identify any requirement that the respondent believes limits competition, along with a technically acceptable alternative.

Rough-Order-of-Magnitude Information Provide a nonbinding rough-order-of-magnitude estimate, broken out by: PEB package; Materials procurement and delivery; Construction equipment; Fence installation and site restoration; Conditional lightning-protection installation; and Any other significant cost driver. This information is requested for planning only and will not be treated as an offer or proposal. 5. Response Instructions Submit responses via email to nika.salemi.2@us.af.mil no later than 5:00 PM EST on November 26, 2026.

Use the following subject line: Sources Sought Response – Outdoor Fitness Facility B-389 – [Company Name] Email X of X (insert number of the email and total number of emails) Do not submit classified information. If a respondent believes its submission contains proprietary information, the respondent shall clearly identify the specific proprietary portions of its submission. 6. Government Reservation of Rights This Sources Sought notice is issued solely for planning and market-research purposes.

The Government may use information received in response to this notice to refine the requirement, determine the appropriate acquisition strategy, assess the availability of capable small-business concerns, and determine whether to issue a future solicitation. The Government is not obligated to issue a solicitation or award a contract as a result of this notice. The Government may revise, cancel, or take no further action regarding this requirement.

7. System for Award Management Firms are encouraged to provide their SAM registration status and expiration date with their response. While SAM registration is not required to submit a response to this Sources Sought notice, any firm submitting an offer or quotation under a future solicitation must be registered in the System for Award Management at the time required by the applicable solicitation and Revolutionary FAR Overhaul requirements.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

Who has supplied this lately

Contracts at Department of the Air Force for the same kind of product (NAICS 236220, product code 5670) that end within a year either way of today. Notices rarely name the current supplier: these are likely candidates, not a fact.

ContractObligatedEndsState
TWCF Tyfr 25-0035 Mr Repair Pump Station B3330 the Contractor Shall Perform All Labor, Materials, Tools and Expertise Necessary to Complete the Required in Accordance With the Proposal Dated…Ske Support Services GMBH · FA561325F0312$521,417Dec 6, 2026within a monthNot stated
Tyfr 22-1122 Replace Lennox Chiller Pax Terminal B3333: the Contractor Shall Perform All Labor, Materials, Tools and Expertise Necessary to Complete the Requirement in Accordance With the Proposal…F. K. Horn GMBH & Co. KG-Bauunternehmung · FA561325F0307$3,295,389Dec 10, 2026within a monthNot stated
Tyfr 21-1180 Sus/Rep Replace Fire Alarm B2403 the Contractor Shall Perform All Labor, Materials, Tools and Expertise Necessary to Complete the Requirement in Accordance With the Proposal Dated…Mickan Generalbaugesellschaft Amberg MBH & Co. KG · FA561325F0413$634,130Oct 29, 2026endedNot stated
Tyfr 18-1130 Sus/Repair Sub Station, BLDG. 2189 F-Ramp the Contractor Shall Perform All Labor, Materials, Tools and Expertise Necessary to Complete the Requirement in Accordance With the Proposal…Mickan Generalbaugesellschaft Amberg MBH & Co. KG · FA561325F0438$1,054,542Dec 28, 2026in 1 monthNot stated
Tyfr 22-1125 Resiliency Rep Air Outdated/Defective HVAC Components Munitions Shipment Center. the KTR Shall Perform All Labor, Material, Tools and Expertise Necessary to Complete the Requirement in…Mickan Generalbaugesellschaft Amberg MBH & Co. KG · FA561325F0394$990,608Oct 19, 2026endedNot stated

Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.

History

  • Nov 25, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Air Force by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Air Force, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy