Parking garage repair and redesign in Reno, Nevada

Design-build repair of the two-story VA parking garage in Reno, Nevada: investigate, then repair corroded steel, spalled concrete, stairs, expansion joints and the second-floor traffic coating, and restripe the deck.

Official title: Z2DA--654-24-004 | Remediate Old Parking Garage

Deadline
Tomorrow, 3:00 PM PT
Wednesday, Nov 25
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: 261-Network Contract Office 21 (36C261)

What they're buying

It is a firm-fixed-price contract of 210 calendar days, open only to verified service-disabled veteran-owned small businesses (SDVOSB).

Top catches

Phase 1 deadline moved to Nov 25
“Due Date has changed to November 25, 2026 at 15:00 PT for Phase I.” 36C26126Q1297 0004.docx

Earlier dates of November 16 and November 20 were replaced. Your Phase 1 quote is due Wednesday, November 25 at 15:00 PT, the day before Thanksgiving, so send early and keep proof of the send time.

SDVOSB status must be verified
“A quote will be rejected and will not be considered for an award if offeror’s SDVOSB/VOSB status cannot be verified at the time of submission of quote and prior to award.” 36C26126Q1297_1.docx

The SAM record says set-aside is Not stated, but the solicitation is limited to verified SDVOSB firms. If your status is not verified in the SBA search at submission and before award, your quote is rejected, so check your listing now.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 19, 2026 from the notice and 9 of 10 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Investigate and report on the condition of concrete, reinforcing and structural steel, metal deck and stairs before any repair, then design the repairs.
  • Remove unsound concrete, clean and coat reinforcing steel, and rebuild slab edges with structural repair mortar.
  • Remove severely corroded metal deck, clean corroded structural steel, and apply zinc-rich primer and a finish coat.
  • Remove the failed traffic coating over the whole second-floor parking area, install new vehicular coating, then paint and restripe.
  • Repair steel stair assemblies, replace second-floor expansion joint seals, and repair the ramp transition with waterproofing sealant.
  • Submit a PE-stamped design package within 30 days of notice to proceed, a schedule in MS Project, a traffic control plan, and as-built drawings at close-out.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Phase 1 deadline moved to Nov 25. Earlier dates of November 16 and November 20 were replaced. Your Phase 1 quote is due Wednesday, November 25 at 15:00 PT, the day before Thanksgiving, so send early and keep proof of the send time.
  • SDVOSB status must be verified. The SAM record says set-aside is Not stated, but the solicitation is limited to verified SDVOSB firms. If your status is not verified in the SBA search at submission and before award, your quote is rejected, so check your listing now.
  • Asbestos exclusion can disqualify insurance. Your general liability policy must have no asbestos exclusion that would void coverage, and you must show proof to the Contracting Officer before award. The minimum general liability is $500,000 per occurrence, and VA said it will not waive this, so check your policy with your broker now.“The successful bidder must present to the Contracting Officer, prior to award, evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage.” 36C26126Q1297_1.docx
  • Surety letter needed for Phase 1. Phase 1 needs only a surety letter, and bid bonds are due in Phase 2 by email. Payment bond and insurance certificate are due within 10 calendar days of award, and only emailed bonds are accepted, so line up a surety early.“A letter from surety will suffice for phase I.” 36C26126Q1297 RFI Question and Responses.docx
  • No repair quantities provided. The Government will not release condition surveys, prior reports or quantities, so you must set your own repair quantities for the Phase 2 price. The December 2 site visit is the only chance to see the garage, so plan to attend if you advance.“The Government will not release underlying condition surveys, any prior assessment reports, or estimated quantities” 36C26126Q1297 RFI Question and Responses.docx
  • Key staff need 5 years and 3 projects. Each of the five key people needs 5 years of experience and 3 similar projects, or the factor is rated unacceptable. One licensed engineer may fill two roles, but the Architect must hold a current license in any U.S. state.“To be considered acceptable or higher on this this factor, the offeror must provide project personnel who meet the minimum of 5 years’ experience and 3 projects of similar size and scope.” 36C26126Q1297_1.docx

Key terms

Who can bidSDVOSB concerns only (100% set-aside)Verify SDVOSB status in the SBA search at quote submission and before award. The SAM record shows set-aside as Not stated.36C26126Q1297_1.docx
Contract period210 calendar days from Notice to ProceedDesign phase is 30 days, then 180 days of construction. Notice to Proceed comes after award and approved bonds.36C26126Q1297_1.docx
How they chooseBest-value tradeoff, one firm-fixed-price contractSection 2.1 says selection will be based on price only, which conflicts with the tradeoff answer.36C26126Q1297 RFI Question and Responses.docx
How to submitEmail only, to christopher.aguon@va.gov with a copy to charee.harris@va.govFaxed or mailed quotes are not accepted.36C26126Q1297_1.docx
Questions dueOctober 28, 2026, 12:00 PM Pacific Time (closed)RFI submission will not be extended. A second RFI window is to be set in Phase 2.36C26126Q1297_1.docx
Estimated value$1,300,000.00 estimated construction priceProject magnitude is between $1,000,000 and $5,000,000. NAICS 236220.36C26126Q1297_1.docx
Contract typeFirm-fixed-price design-build contractThe design and the construction are both bid under one contract.36C26126Q1297_1.docx
Site visitDecember 2, 2026, 10:00 AM PTOnly for offerors selected for Phase 2. Not needed for Phase 1.36C26126Q1297_1.docx

How to respond

  1. Confirm that your SDVOSB status is verified in the SBA Small Business Search and that your UEI and SAM registration are current before you send anything.
  2. Email your Phase 1 quote by Wednesday, November 25, 2026 at 15:00 PT to christopher.aguon@va.gov, with a copy to charee.harris@va.gov. Phase 1 covers technical approach, key personnel, specialized experience and past performance.
  3. Use the subject line RFQ: 36C26126Q1297, Remediate Old Parking Garage. Keep each file under 7MB; multiple emails are acceptable, and one file with all factors labeled by factor is acceptable.
  4. Include a surety letter, a Key Personnel Evaluation form for each of the five roles, and three past-performance projects with CPARS or PPQs from VA or another U.S. federal agency. The same projects must appear under specialized experience.

Attached files

From SAM.gov. Download links open the original files.

  • 36C26126Q1297 0002.docxAmendment 0002 dated 10-27-2026, now superseded in part, that you read for the site visit timing and earlier dates; nothing to fill in. Read.
  • Supplemental Price Breakdown by Division Sheet.docxDivision-by-division price sheet with bonds, overhead and profit lines that you must complete and sign only if you advance to Phase 2. Read.
  • 36C26126Q1297_1.docxMain solicitation with the SF 1442 offer page, statement of work, instructions, evaluation and clauses C.1 to C.10, which you must read and sign on the offer page; only part was provided to us. Read in part.
  • 36C26126Q1297 0003.docxAmendment 0003 dated 11-12-2026 that posts RFI responses and says Phase I is due November 20, a date later changed; nothing to fill in. Read.
  • 36C26126Q1297 0001.docxAmendment 0001 dated 10-21-2026 that moved the due date to November 20 and corrected a contracting officer email; superseded, nothing to fill in. Read.
  • Attachment - REQUEST FOR INFORMATION RFI FORM.docxBlank RFI form; the October 28 deadline has passed, so you would use it only if a second RFI window opens in Phase 2. Read.
  • Attachment Drawings Remediate Old Parking Garag.pdf Not read: over our length limit.
  • 36C26126Q1297 0004.docxThe final amendment dated 11-18-2026 that sets the Phase 1 due date at November 25 and posts more RFI answers; read it and acknowledge amendments in your offer. Read.
  • 36C26126Q1297 RFI Question and Responses.docxGovernment answers to RFI questions that change or clarify requirements, including key personnel, licensing, insurance and bonds; read it, nothing to sign. Read.
  • Key Personnel Evaluation.docxForm for resumes of the Project Manager, Superintendent, Safety Officer, Architect and Civil Engineer, which you must complete for each role. Read.

Not stated in what we read

  • The drawings file Attachment+Drawings+Remediate+Old+Parking+Garag.pdf was left out for length, so you must read it yourself for repair locations and layout.
  • The rest of the main solicitation after clause C.10 (clauses C.11 onward, design-build special provisions SP-1 to SP-33, and Sections D and E) was not provided to us, so you must read it.
  • Required bid guarantee amount or percentage: Not stated; the RFI answer says the Contracting Officer will respond.
  • Whether the signed SF 1442 offer page, representations and certifications, and all solicitation pages are due with Phase 1 or only in Phase 2: Not stated.
  • Estimated repair quantities or allowances for concealed deterioration: Not stated; the Government said it will not release them.
  • Date and terms of the second RFI window in Phase 2: Not stated.

Notice text

36C26126Q1297 Page 1 of Page 95 of 95 Page 1 of See RFQ 36C26127Q1297 on www.SAM.gov for more information.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 19, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of Veterans Affairs by email

Each morning we'll send the new solicitations and sources-sought notices from Department of Veterans Affairs, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy