Road paving and repairs on Dent Bridge Road, Orofino, ID
Road work on Dent Bridge Road, 4.69 miles near Orofino, Idaho, including full-depth reclamation, asphalt paving, shoulder work, guardrail and striping, to be finished by 09/20/2027.
Official title: ID FLAP CLEAR 4783(1), Dent Bridge Road Improvements
- Deadline
- Dec 8, 2:00 PM PT
- 13 days left
- Who can bid
- Not stated
- The notice names no set-aside
- Last time
- $5.27M
- Likely M.J. Hughes Construction, Inc.
- Place
- Orofino, ID
- Buyer: 690567 Western Federal Lands Div
What they're buying
Only six named MATOC prime contractors may submit a proposal, and the notice says it is posted to help potential subcontractors.
Top catches
“A PROPOSAL WILL ONLY BE ACCEPTED FROM THE ABOVE PRIME CONTRACTORS.” Notice text
Only the six contractors named in the notice may submit a proposal. If you are not one of them, the notice says this posting is meant to help potential subcontractors find work.
“Electronic proposals will not be accepted.” RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 1
Electronic and email offers are not accepted. Print your proposal and deliver it to the Vancouver, WA office by 2:00 PM on Tuesday, December 8, 2026, and plan to deliver early, since a late offer will not be considered under the standard clause.
Read by AI (Claude Haiku) on Nov 20, 2026 from the notice and 2 of 7 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Full-depth reclamation with cement over 72,600 square yards at 8-inch depth, with 1,040 tons of cementitious material
- Asphalt concrete pavement, 14,950 tons of 1/2-inch gyratory mix with PG 58-34 binder, plus 72 tons of prime coat and 30 tons of tack coat
- Milling 4-inch depth over 69,300 square yards, hauled to the Clearwater County Maintenance Yard in Orofino
- Subexcavation of 1,440 cubic yards, select borrow of 1,120 cubic yards, 2,660 square yards of stabilization geogrid and 836 square yards of geotextile
- Shoulder reconditioning over 9.85 miles, 315 linear feet of guardrail with 7 terminal systems, and 200 linear feet of underdrain
- Pavement markings of 103,000 linear feet of 4-inch white and 104,000 linear feet of 4-inch yellow, plus traffic control with 500 flagger hours and a 60-day pilot car
Who did it before
$5.27M
on the contract that likely holds this work now: M.J. Hughes Construction, Inc.. It ended Nov 13, 2026.
Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.
What to watch for
- Only six named primes may bid. Only the six contractors named in the notice may submit a proposal. If you are not one of them, the notice says this posting is meant to help potential subcontractors find work.
- Printed proposal only, no email. Electronic and email offers are not accepted. Print your proposal and deliver it to the Vancouver, WA office by 2:00 PM on Tuesday, December 8, 2026, and plan to deliver early, since a late offer will not be considered under the standard clause.
- Bid bond or the bid is rejected. A valid Standard Form 24 bid bond must come with your bid, or the bid is rejected. Performance and payment bonds are also due within 10 calendar days after award. The bid bond amount is not stated in the pages we could review, so ask your surety now.“Bids received without a valid bid bond will be rejected.” RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 4
- Award basis: price or best value? The Notice to Offerors says the award is based on price, but a contract clause says the Government awards to the best value after evaluation under the RFP's factors. The evaluation factors are not in the pages we could review, so read that section and ask the contracting office which rule applies before you price.“Selection of the successful offer is based on price.” RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 14
- TERO fees not in bid schedule. Some work is inside the Nez Perce Reservation, and the bid schedule has no line for Tribal fees. Get the TERO fee rules from the Nez Perce Tribe and build the cost into your unit prices, since the Government is not a party to that agreement.“take into consideration any TERO fees that may be assessed by the Nez Perce Tribe when preparing their offer.” RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 15
- Weekend and holiday traffic blackout. Work that delays public traffic is barred from 6:00 p.m. Friday to 6:00 a.m. Monday unless the CO approves, and during set holiday windows such as Memorial Day and Independence Day. Build these blackout windows into your schedule and your crew costs.“From 6:00 p.m. Friday through 6:00 a.m. Monday, unless approved by the CO.” RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 233
Key terms
| Who can bid | Only six named MATOC prime contractorsOther firms would likely work as subcontractors to these primes.Notice text |
|---|---|
| Contract period | Complete by 09/20/2027Start within 10 calendar days after notice to proceed. The date moves later if notice to proceed is late; 01/27/2027 is assumed.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 20 |
| How they choose | Price, per the Notice to OfferorsA contract award clause says best value instead. See the catches.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 14 |
| How to submit | Printed copy, delivered to Vancouver, WA officeAddress: FHWA Western Federal Lands Division, 610 E Fifth Street, Vancouver, WA 98661.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 1 |
| Questions due | Close of business five days before the due dateFive days before December 8, 2026 is December 3, 2026. The notice does not give a time.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 14 |
| Estimated value | $5,000,000 to $10,000,000 (price range)Stated as the estimated price range of the project work.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 21 |
| Contract type | Firm fixed-price task orderTask order under the Idaho, Montana and Surrounding Areas MATOC.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 48 |
| Site visit | Encouraged, not stated as mandatoryThe notice says no government staff will give show-me tours. Viewing is best in fall.RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdf, page 15 |
How to respond
- Confirm that your firm is one of the six named prime contractors. If it is not, you can only take part by offering your price to one of them as a subcontractor.
- Print the SF 1442 offer, bid schedule, Authority to Sign form, completed B-pages and an original bid bond with its power of attorney. Sign block 20B and list any amendments in block 19.
- Mark the lower left corner of the envelope with 'Proposal Enclosed', solicitation number 69056726R000009, and the project name and number.
- Deliver the sealed printed proposal to FHWA Western Federal Lands Division, 610 E Fifth Street, Vancouver, WA 98661, by 2:00 PM on Tuesday, December 8, 2026. Email offers are not accepted.
- Send written technical questions to wfl.plans-spec@dot.gov and general questions to wfl.contracts@dot.gov before close of business five days before the due date.
Attached files
From SAM.gov. Download links open the original files.
- RFP_69056726R000009_ID FLAP CLEAR 4783(1).pdfThe solicitation package with the offer form, bid schedule, bid bond, certifications and special requirements, which you must fill in, sign and return; pages 55 to 221 were not included, so you must read them yourself. Read in part (pages 1–54 and 222–271 of 271).
- Lab Trailer Blank Check In Form.docx Not read: over our length limit.
- ida-clear4783-1_plans.pdf Not read: over our length limit.
- ida-clear4783-1_Control-Points.xlsx Not read: over our length limit.
- QA_11.19.26.pdfFive written questions and answers dated 9/14/26 and 11/19/26; nothing to sign, but the answer to Question 4 repeats the question and does not say whether the geogrid is acceptable. Read.
- ida-clear4783-1_GR 0226 Dent Bridge Road Final Geotechnical Report.pdf Not read: over our length limit.
- ida-clear4783-1_PM 03-26 Dent Bridge Road Final Pavement Memo.pdf Not read: over our length limit.
Not stated in what we read
- Bid bond amount: the form points to FAR 52.228-1, which was not in the pages we could review.
- Insurance minimums and liquidated damages: not stated in the pages we could review.
- Evaluation factors and how price and any other factors are weighed.
- Number of calendar days to finish after notice to proceed: Block 11 leaves this blank and gives only the 09/20/2027 date.
- Whether a coated, knitted polyester geogrid is acceptable: the 11/19/26 answer does not say.
- Set-aside status: the SAM.gov record says Not stated.
Notice text
Update 11/19/2026: QA_11.19.26.pdf posted to Attachments. Project No. ID FLAP CLEAR 4783(1), Dent Bridge Road Improvements See attachments for Request for Proposal (RFP), plans, and phyiscal data files. THIS “TASK ORDER REQUEST FOR PROPOSAL” IS SOLELY FOR THE FOLLOWING CONTRACTS AND CONTRACTORS: *Contract No. 69056725D000002 Contractor: ASCORP INC, DBA DEBCO CONSTRUCTION Address: 217 College Ave. STE 5, Orofino, ID 83544 Phone: 208-476-3617 *Contract No. 69056725D000003 Contractor: GRANITE CONSTRUCTION Address: 585 W Beach St., Watsonville, CA 95076 Phone: 360-606-1335 *Contract No. 69056725D000004 Contractor: HAMILTON CONSTRUCTION Address: 2213 South F Street, Springfield, OR 97477 Phone: 541-746-2426 *Contract No. 69056725D000005 Contractor: M.A. DEATLEY CONSTRUCTION, INC. Address: 829 Evans Road, Clarkston, WA 99403 Phone: 509-751-1580 *Contract No. 69056725D000006 Contractor: MJ HUGHES CONSTRUCTION, INC. Address: 11510 NE 87TH AVE, Vancouver, WA 98662 Phone: 360-314-2024 *Contract No. 69056725D000007 Contractor: THOMPSON CONTRACTING, INC Address: 502 Gruber Rd., Libby, MT 59923 Phone: 406-293-5392 THIS PROJECT IS BEING ADVERTISED ON SAM.GOV TO ANNOUNCE THE UPCOMING PROJECT AND ASSIST POTENTIAL SUBCONTRACTORS BY PUBLICIZING OPPORTUNITIES.
A PROPOSAL WILL ONLY BE ACCEPTED FROM THE ABOVE PRIME CONTRACTORS. This information is also available on our website: Idaho, Montana and Surrounding Areas MATOC:https://highways.dot.gov/federal-lands/business/construction-contracting/idaho-montana-andsurrounding-areas-idiq-matoc Interested Vendor List The Interested Vendor List on SAM.gov is viewable only by users who are linked to an entity with an active Unique Entity Identifier (UEI) and hold an assigned role (such as Contract Opportunities Administrator, Data Viewer, or Data Entry).
The Federal Government does not maintain or provide a separate plan holders list. If you need assistance, go to https://www.fsd.gov/gsafsd_sp.
As published on SAM.gov.
Contacts
- Contracts G. Office, wfl.contracts@dot.gov, 3606197520
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at Federal Highway Administration for the same kind of work (NAICS 237310, service code Y1LB) in Idaho that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 20, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 8, 2:00 PM PT13 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 237310, highway, street, and bridge construction, soonest deadline first.
- Departmental OfficesWaterman canal gate for Wheeler refuge, Decatur, AL
- Department of the ArmyRoads, parking and grounds renovation, Detroit, MI
- Departmental OfficesRoad and bridge repair at national parks nationwide
- Department of the NavyService road realignment and roundabout, Camp Lejeune, NC
- Federal Highway AdministrationThree bridges and a culvert on SR 35, Mimbres, NM
- Federal Highway AdministrationThree bridges and road rebuild in Arches National Park, UT
- Forest ServiceRoad and trailhead upkeep, Little Missouri Grassland, ND
- Department of the Air ForceAirfield rubber removal and striping, Dover AFB, DE
Free · at most one email a morning
Get new notices from Federal Highway Administration by email
Each morning we'll send the new solicitations and sources-sought notices from Federal Highway Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy