Three bridges and road rebuild in Arches National Park, UT

The government wants a contractor to build three 100-foot-span concrete bridges over washes on Delicate Arch Road, plus road raising, realignment, paving and guardrail work, in Arches National Park near Moab, Utah.

Official title: UT NP ARCH 100(2) Bridges on Delicate Arch Road

Deadline
Dec 1, 2:00 PM MT
6 days left
Who can bid
Any business
Registered in SAM.gov · How to register
Last time
$23.9M
Likely S & L Landscaping & Excavation Inc
Place
Moab, UT
Buyer: 6982AF Central Federal Lands Divisi

What they're buying

The work is anticipated to run from a December 2026 notice to proceed to December 2028 completion.

Top catches

Due date conflicts across documents
“Response deadline: 2026-12-01T14:00:00-07:00” SAM.gov record

SAM.gov shows 2:00 p.m. on December 1, 2026 with a -07:00 offset. The bid form page A-1 shows 11/10/26 at 2:00 p.m. local time, and the amendments show a garbled date, so the newer date is likely but not confirmed. Ask the contracting officer which date governs before you plan.

Quantities differ from bid schedule
“20420-0000 Embankment Construction: 10,000 CUYD” Notice text

The notice text lists 10,000 cubic yards of embankment and 5,140 tons of roadway aggregate. The Schedule A bid lines show 5,600 cubic yards and 2,700 tons, so ask which quantities govern before you price.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 18, 2026 from the notice and 36 of 124 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Design and build three 100-foot-span concrete bridges at Salt Valley Wash, Salt Wash and Winter Camp Wash.
  • Raise the road profile at each wash for a 10-year design flood, and realign the road north of the existing crossing at Salt Valley Wash.
  • Place 10,000 cubic yards of embankment, 1,725 cubic yards of Class 3 riprap and 5,140 tons of roadway aggregate, per the notice text.
  • Full depth reclamation or pavement removal on the 3R sections, including parking areas, then a 4-inch asphalt overlay totaling 8,300 tons.
  • Structural concrete (752 cubic yards), epoxy-coated rebar (138,000 pounds), steel bridge railing (642 linear feet), and 24-inch and 30-inch drilled shafts (750 and 890 linear feet).
  • Concrete curb (3,921 linear feet), guardrail (1,290 linear feet) and 5,800 hours of flagger traffic control.

Who did it before

$23.9M

on the contract that likely holds this work now: S & L Landscaping & Excavation Inc. It ends Dec 31, 2026.

Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.

What to watch for

  • Due date conflicts across documents. SAM.gov shows 2:00 p.m. on December 1, 2026 with a -07:00 offset. The bid form page A-1 shows 11/10/26 at 2:00 p.m. local time, and the amendments show a garbled date, so the newer date is likely but not confirmed. Ask the contracting officer which date governs before you plan.
  • Quantities differ from bid schedule. The notice text lists 10,000 cubic yards of embankment and 5,140 tons of roadway aggregate. The Schedule A bid lines show 5,600 cubic yards and 2,700 tons, so ask which quantities govern before you price.
  • Plan set could not be read. The main plan file could not be read, and many survey, staking and surface files were left out or could not be read. The bid form makes you responsible for checking the plans, so review them on SAM.gov before you price.“It is the responsibility of the bidder to verify that this solicitation document, including the plans, are complete as listed in the table of contents and the index to sheets.” 6982AF27B000005.pdf, page 5
  • Price all three schedules. Your bid must price Schedule A, Option X and Option Y. The government may fund only part of this, and it can exercise options up to 120 days after award, so price every line.“the offeror shall submit prices for each item necessary to complete all contract work in Schedule A, Option X and Option Y.” 6982AF27B000005.pdf, page 13
  • Original bid bond required. The bid guarantee is 20% of the bid price or $3,000,000, whichever is less. The bond must be an original with original signatures and corporate seals, or your bid is non-responsive.“Photocopied and faxed copies of bonds will be rejected and cause your bid to be non-responsive.” 6982AF27B000005.pdf, page 6
  • $8,700 per day for delay. If the work runs past the contract time, the government can charge $8,700 for each calendar day of delay. The completion time is in special requirements not included here, so confirm it before you set your schedule and price.“shall pay liquidated damages to the Government in the amount of $ 8,700.00 for each calendar day of delay until the work is completed or accepted.” 6982AF27B000005.pdf, page 50

Key terms

Who can bidOpen to all bidders; no set-asideLarge business offers get a 10% factor added to their price for evaluation. The size standard is $45 million in average annual gross receipts.SAM.gov record
Contract periodStart December 2026 (anticipated); completion December 2028 (anticipated)The exact completion time in days is not in the pages provided.Notice text
How they chooseLowest responsive, responsible bidder, if funds are availableSchedule A plus any options funded at award are evaluated together first.6982AF27B000005.pdf, page 14
How to submitSealed printed bid to the Lakewood, Colorado office; electronic bids not acceptedBid modifications may be emailed to cflcontracts@dot.gov before the deadline.6982AF27B000005.pdf, page 4
Questions dueClosed at 4 p.m. on November 2, 2026This date has passed. Answers are to be posted on sam.gov.6982AF27B000005.pdf, page 7
Estimated value$10,000,000 to $20,000,000This is a range only. The bid schedule total is blank in the text provided.Notice text
Contract typeFirm fixed price with economic price adjustmentSealed bid. The economic price adjustment terms are not in the pages provided.6982AF27B000005.pdf, page 44
Site visitNot mandatory; held October 8, 2026 (passed)The site visit was on Thursday, October 8, 2026. Its agenda and sign-in sheet were to be posted on sam.gov.6982AF27B000005.pdf, page 9

How to respond

  1. Confirm the due date first with the contracting officer, Laura Slauter, at CFLContracts@dot.gov, because SAM.gov and the bid form disagree.
  2. Fill in and sign SF-1442 pages A-1 and A-2, including Item 19 for amendments A001 and A002, the bid schedule pages A-7 to A-17 for Schedule A, Option X and Option Y, the bid bond on pages B-1 to B-4 with original signatures, and the bidder information on pages B-5 to B-8.
  3. Put the printed bid in a sealed envelope marked with your name and address, solicitation number 6982AF27B000005, project name UT NP ARCH 100(2), and the due date and time. Address it to Federal Highway Administration, Central Federal Lands Division Office, 12300 W. Dakota Avenue, Suite 167, Lakewood, CO 80228.
  4. Keep your SAM.gov registration active with NAICS 237310 in your profile, both at bid submission and at award. Email any bid modifications to cflcontracts@dot.gov before the deadline.
  5. If you win, furnish performance and payment bonds within 10 calendar days after award, as stated on SF-1442 item 12B.

Attached files

From SAM.gov. Download links open the original files.

109 more files from a ZIP archive, 32 read
  • Alignment Reports/ARCH 100(2) DAR Horizontal Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) DAR Vertical Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) SVB Horizontal Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) SVB Vertical Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) SVWB Horizontal Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) SVWB Vertical Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WCB Horizontal Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WCB Vertical Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WOLFE Horizontal Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WOLFE Vertical Alignment.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WRAP Horizontal Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/ARCH 100(2) WRAP Vertical Alignment Report.pdf Scanned image, not read.
  • Alignment Reports/UT ARCH 100(2) DAR Horizontal Alignment Report.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) DAR Vertical Alignment Report.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) SVB Horizontal Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WCB Horizontal Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WCB Vertical Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WOLFE Horizontal Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WOLFE Vertical Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WRAP Horizontal Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2) WRAP Vertical Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2)-SVB Vertical Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2)-SVWB Horizontal Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2)-SVWB Vertical Alignment.xlsx Read.
  • Alignment Reports/UT ARCH 100(2)-SVWB.xml Could not be read.
  • Alignment Reports/UT ARCH 100(2)-WCB.xml Could not be read.
  • Alignment Reports/UT NP ARCH 100(2) SWB.xml Could not be read.
  • Alignment Reports/UT NP ARCH 100(2)-BL (WOLFE).xml Could not be read.
  • Alignment Reports/UT NP ARCH 100(2)-BL3 (DAR).xml Could not be read.
  • Alignment Reports/UT NP ARCH 100(2)-WRAPL.xml Could not be read.
  • StakingReports/Channel Grading/UT ARCH 100(2) SVB Staking Notes.pdf Scanned image, not read.
  • StakingReports/Channel Grading/UT ARCH 100(2) SVB Staking Notes.xlsx Read.
  • StakingReports/Channel Grading/UT ARCH 100(2) SVWB Staking Notes.pdf Scanned image, not read.
  • StakingReports/Channel Grading/UT ARCH 100(2) SVWB Staking Notes.xlsx Read.
  • StakingReports/Channel Grading/UT ARCH 100(2) WCB Staking Notes.pdf Scanned image, not read.
  • StakingReports/Channel Grading/UT ARCH 100(2) WCB Staking Notes.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Blue Tops Cross Section.pdf Scanned image, not read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Blue Tops Cross Section.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Finished Surface.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Finshed Surface.pdf Scanned image, not read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Subgrade Cross Section.pdf Scanned image, not read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 11 00 - 16 40 Subgrade Cross Section.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Blue Tops Cross Section.pdf Scanned image, not read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Blue Tops Cross Section.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Finished Surface Cross Section.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Finished Surface.xlsx Read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Subgrade Cross Section.pdf Scanned image, not read.
  • StakingReports/DAR/DAR Option X/ARCH 100(2) DAR 17 40 - 29 36 Subgrade Cross Section.xlsx Read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Blue Tops.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Blue Tops.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Finished Surface Cross Section.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Finished Surface.xlsx Read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Subgrade Surface Cross Section.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 29 36 - 31 18 Subgrade Surface.xlsx Read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Blue Tops.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Blue Tops.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Finished Surface Cross Section.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Finished Surface.xlsx Read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Subgrade Surface.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 32 18 - 37 50 Subgrade Surface.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Blue Tops.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Blue Tops.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Finished Surface.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Finished Surface.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Subgrade Surface.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 38 50 - 47 00 Subgrade Surface.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 47 00 - 81 50 Blue Tops.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 47 00 - 81 50 Blue Tops.xlsx Older version, not read.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 47 00 - 81 50 Finished Surface.pdf Not read: over our length limit.
  • StakingReports/DAR/DAR Schedule A/ARCH 100(2) DAR 47 00 - 81 50 Finished Surface.xlsx Older version, not read.
  • StakingReports/Wolfe/UT ARCH 100(2) WOLFE Blue Tops Staking Notes.pdf Not read: over our length limit.
  • StakingReports/Wolfe/UT ARCH 100(2) WOLFE Blue Tops Staking Notes.xlsx Older version, not read.
  • StakingReports/Wolfe/UT ARCH 100(2) WOLFE Finished Grade Staking Notes.pdf Not read: over our length limit.
  • StakingReports/Wolfe/UT ARCH 100(2) WOLFE Finshed Grade Staking Notes.xlsx Read.
  • StakingReports/WRAP/ARCH 100(2) WRAP Blue Tops.pdf Not read: over our length limit.
  • StakingReports/WRAP/ARCH 100(2) WRAP Blue Tops.xlsx Older version, not read.
  • StakingReports/WRAP/ARCH 100(2) WRAP Finished Surface.pdf Not read: over our length limit.
  • StakingReports/WRAP/ARCH 100(2) WRAP Finished Surface.xlsx Older version, not read.
  • StakingReports/WRAP/ARCH 100(2) WRAP Subgrade Surface.pdf Not read: over our length limit.
  • StakingReports/WRAP/ARCH 100(2) WRAP Subgrade Surface.xlsx Older version, not read.
  • StakingReports/Template Point ID sheet 1.pdfSurvey template point diagrams for road cross sections; read for reference only, no form to fill in. Read.
  • StakingReports/Template Point ID sheet 2.pdfSurvey template point diagrams for road cross sections; read for reference only, no form to fill in. Read.
  • StakingReports/Template_Point_Identification FLH Web.pdf Not read: over our length limit.
  • Superelevation/ARCH 100(2) DAR Superelevation data.pdf Scanned image, not read.
  • Superelevation/ARCH 100(2) DAR Superelevation data.xlsx Read.
  • Superelevation/ARCH 100(2) WOLFE Superelevation data.pdf Scanned image, not read.
  • Superelevation/ARCH 100(2) WOLFE Superelevation data.xlsx Read.
  • Surfaces/DXF/Channel Grading DXF.bak Could not be read.
  • Surfaces/DXF/Channel Grading DXF.dxf Could not be read.
  • Surfaces/DXF/DAR DXF.bak Could not be read.
  • Surfaces/DXF/DAR DXF.dxf Could not be read.
  • Surfaces/DXF/WOLFE DXF.bak Could not be read.
  • Surfaces/DXF/WOLFE DXF.dxf Could not be read.
  • Surfaces/DXF/WRAP DXF.bak Could not be read.
  • Surfaces/DXF/WRAP DXF.dxf Could not be read.
  • Surfaces/3R Section.UT NP ARCH 100(2) Blue Tops.xml Could not be read.
  • Surfaces/DAR Blue Tops 4R.xml Could not be read.
  • Surfaces/DAR Finished Surface 4R.xml Could not be read.
  • Surfaces/DAR Subgrade 4R.xml Could not be read.
  • Surfaces/SVB Surface.xml Could not be read.
  • Surfaces/SVW-Surface.xml Could not be read.
  • Surfaces/UT_ARCH_100(2)_Delicate_Arch_Existing_Ground.xml Could not be read.
  • Surfaces/Winter Camp Wash.xml Could not be read.
  • Surfaces/WOLFE - Blue.xml Could not be read.
  • Surfaces/WOLFE Finished Surface.xml Could not be read.
  • Surfaces/WRAP Finished Surface.xml Could not be read.
  • ARCH 100(2) DAR Earthwork Summary Option X.pdfA quantity summary for Option X showing 5,117 cubic yards of embankment and borrow needs; read it for pricing context only. Read.
  • ARCH 100(2) DAR Earthwork Summary Schedule A.pdfA quantity summary for Schedule A showing 5,195 cubic yards of embankment and borrow needs; read it for pricing context only. Read.
  • electronic-file-disclaimer.docA federal disclaimer that electronic working files may differ from the contract plans and are not part of the contract; read it, nothing to fill in. Read.

Download the archive from SAM.gov.

Not stated in what we read

  • The correct bid due date and time, since SAM.gov and the bid form disagree and the amendments show a garbled date.
  • Contract completion time in calendar days; the special contract requirements (SCR 108.01) were not provided.
  • Federal wage rates for the work; the construction wage rate section was not provided.
  • Insurance minimums; the referenced FP-14 Subsection 107.05 was not provided.
  • Whether Options X and Y will be funded or exercised, and which schedule will be awarded.
  • Answers to the bidder questions (QnA dated 10.15.26) and the pre-bid slides, which were left out of the provided files.

Notice text

PROJECT NUMBER: UT NP ARCH 100(2) PROJECT NAME: Bridges on Delicate Arch Road PROJECT DESCRIPTION: Delicate Arch Road (DAR) is within Arches National Park (Park) and provides access to Delicate Arch. DAR is a functional class 1 roadway (Principal Park Road) and is heavily traveled by visitors and often congested during periods with moderate-to-high levels of visitation. DAR crosses three low-gradient ephemeral washes (Salt Valley Wash, Salt Wash, and Winter Camp Wash) near their confluence in the Salt Wash Basin downstream of Wolfe Ranch.

Culverts installed during original road construction in the mid-1990s and during subsequent upgrades are inadequate to allow unobstructed stream flow and sediment transport downstream. This existing condition produces flooding and sediment deposition, which creates unsafe conditions for visitors, triggers road closures, potentially strands Park visitors, diminishes visitor experience of the Park, and generates high operational costs associated with traffic management, visitor safety, and cleanup operations.

SCOPE OF THE WORK: This project will be designated as Reconstruction (4R) with one segment of restoration (3R), and will design and construct 100’ span concrete bridges at the Salt Valley Wash, Salt Wash, and Winter Camp Wash. The DA roadway profile at each Wash will be raised to accommodate a 10-year design frequency and allow a medium-sized excavator to access each wash. The DA will be realigned at the Salt Valley wash, moving the roadway and new bridge location to the north of the existing roadway and drainage crossing.

The remaining 3R sections of the roadway will receive full depth reclamation (FDR) or removal of pavement, including all parking areas, followed by a 4-inch pavement overlay. PRINCIPAL WORK ITEMS: 20420-0000 Embankment Construction: 10,000 CUYD 25101-0300 Placed Riprap, Class 3: 1,725 CUYD 30202-2000 Roadway Aggregate, Method 2: 5,140 TON 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch or 3/4-Inch Nominal Maximum Size Aggregate, 0.3 To <3 Million ESAL: 8,300 TON 55201-0200 Structural Concrete, Class A (AE): 752 CUYD 55401-2000 Reinforcing Steel, Epoxy Coated: 138,000 LB 55601-1100 Bridge Railing, Steel, Two Rail: 642 LNFT 56501-0200 Drilled Shaft, 24-Inch Diameter: 750 LNFT 56501-0300 Drilled Shaft, 30-Inch Diameter: 890 LNFT 60901-1300 Curb, Concrete, 15-Inch Depth (Reinforced, Colored): 3,921 LNFT 61701-4500 Guardrail System Mgs, Type 2, Class A Steel Posts: 1,290 LNFT 63506-0500 Temporary Traffic Control, Flagger: 5,800 HOUR ANTICIPATED SCHEDULE: Advertisement – September 2026 Award – November 2026 NTP – December 2026 Contract Completion – December 2028 ESTIMATED COST RANGE: Total estimated cost between $10,000,000 and $20,000,000 This will be solicited as a full and open competition.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

Who may hold this work now

Contracts at Federal Highway Administration for the same kind of work (NAICS 237310, service code Y1LB) in Utah that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.

Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.

History

  • Nov 18, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Federal Highway Administration by email

Each morning we'll send the new solicitations and sources-sought notices from Federal Highway Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy