Maintenance dredging of Jacksonville Harbor, FL

The Army Corps of Engineers wants a firm fixed price contract to maintain the federal channel in Jacksonville Harbor, Florida, about 20 miles long, with dredged sediment placed at Bartram Island or an ocean disposal site.

Official title: Jacksonville Harbor Maintenance Dredging

Deadline
Dec 11, 1:00 PM ET
16 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: W074 Endist Wilmington

What they're buying

The base work runs 120 calendar days, with five options (A to E) adding up to 100 days.

Top catches

Solicitation not yet available
“This solicitation will be issued in electronic format only and will be available on or about 02 November 2026.” Notice text

The notice says the solicitation would be available on or about 02 November 2026, a date that has already passed. No solicitation files are attached here, so check SAM.gov for the issued package and bid opening date before you price the work.

Fixed date for channel cuts
“Complete all work within Cut-17 Sta. 0+00 through Cut-41 Sta. 20+00 (BASE work), which are located within an Outstanding Florida Waters (OFW), no later than May 20, 2027.” Notice text

Base work in Cut-17 through Cut-41 must finish by May 20, 2027. That date may fall earlier than the 220-day limit, depending on when you get notice to proceed, so check it against your schedule.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 25, 2026 from the notice. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Maintenance dredging of the federal channel, about 20 miles long, to -47 ft MLLW plus advanced maintenance areas and allowable overdepth
  • Dredge with hopper and/or pipeline or mechanical dredges, depending on work location
  • Haul dredged sediment to Bartram Island Cell F (upland) or Jacksonville ODMDS Release Zone C1, about 6 nautical miles offshore, depending on reach
  • Complete Cut-17 Sta. 0+00 through Cut-41 Sta. 20+00 (base work) in Outstanding Florida Waters by May 20, 2027
  • Start within 10 calendar days of notice to proceed and finish all work, including final cleanup, within 220 days
  • Base work of 120 calendar days, plus options A (15), B (20), C (30), D (25) and E (10) calendar days

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Solicitation not yet available. The notice says the solicitation would be available on or about 02 November 2026, a date that has already passed. No solicitation files are attached here, so check SAM.gov for the issued package and bid opening date before you price the work.
  • Fixed date for channel cuts. Base work in Cut-17 through Cut-41 must finish by May 20, 2027. That date may fall earlier than the 220-day limit, depending on when you get notice to proceed, so check it against your schedule.
  • Specialized dredge equipment needed. You need dredges able to reach -47 ft MLLW and haul to two placement sites. You likely must own, lease or team with a firm that has such dredges, so price that before you bid.“The dredge(s) must have the capability to dredge maintenance material up to a depth of -47 ft MLLW” Notice text
  • Check against $37 million size standard. This solicitation is unrestricted, so no set-aside applies. Compare your company's size with the $37,000,000.00 size standard for NAICS 237990 to see whether you count as small.“the size standard is $37,000,000.00” Notice text
  • Bid opening date not set. The bid opening date will only appear in the solicitation when it is issued. Watch for it, since it may affect the timing of your offer.“The bid opening date will be specified in the solicitation when it is issued.” Notice text
  • Options priced separately. The base work is 120 days and options A to E add 100 days, which totals the 220-day limit. The notice gives no option pricing or exercise timing, so ask the contracting office how options are exercised.“Base: 120 calendar days. Option A: 15 calendar days.” Notice text

Key terms

Who can bidUnrestricted, no set-aside statedSize standard for NAICS 237990 is $37,000,000.00. You must be registered in SAM to receive an award.Notice text
Contract periodBase 120 days plus options A to E (100 days)All work, including final cleanup, must be finished within 220 days after notice to proceed. Cut-17 to Cut-41 must finish by May 20, 2027.Notice text
Contract typeFirm fixed pricePrice is fixed for the contract, which has a base period and five options.Notice text

How to respond

  1. Register in SAM.gov first. The notice says you must register to download documents and to receive an award.
  2. Search SAM.gov for solicitation W912PM27BA003 and download the package. The notice says no paper or CD copies will be sent.
  3. Where and how to send your offer: Not stated. Ask Rosalind Shoemaker, Contracting Officer, at (910) 251-4436 or rosalind.m.shoemaker@usace.army.mil.
  4. Send your offer by the response deadline, Friday, December 11, 2026, 13:00:00-05:00, and check SAM.gov for amendments until then.

Not stated in what we read

  • Solicitation documents, bid opening date and submission format, which the notice says will be issued later on SAM.gov
  • Estimated value or budget for the contract
  • How offers will be evaluated and whether price alone decides the award
  • Whether a site visit or pre-bid meeting is required
  • Last day for questions to the contracting office
  • How and when the five options are exercised, and how option prices are to be submitted

Notice text

The U.S. Army Corps of Engineers, Enterprise Dredge Delivery Center (EDDC) requires a contract to provide maintenance dredging for Jacksonville Harbor. Jacksonville Harbor: The Jacksonville Harbor, FL - FY27 O and M Contract (non-fed sponsor Jacksonville Port Authority (JAXPORT)) for maintenance dredging typically requires hopper and pipeline/mechanical dredge(s) depending on work location in the~ 20-mile federal channel. The dredge(s) must have the capability to dredge maintenance material up to a depth of -47 ft MLLW (w/additional depths for required advanced maintenance areas and allowable over depths) and to transport the dredged sediment to both a designated Dredged Material Placement Area (DMPA) known as Bartram Island and the Ocean Dredge Material Disposal Site (ODMDS) located approximately 6 nautical miles offshore.

Dredged material shall be placed upland in Bartram Island Cell F and the Jacksonville ODMDS Release Zone C1 depending on the specific reach to be dredged. The transport distance to the designated placement areas varies significantly, ranging from direct, local placement to a few miles for the upland placement area and up to 6 miles for ocean disposal from the tip of the south jetty. The work is divided into a base and five options. The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 220 days after the Contractor receives the notice to proceed.

The time stated for completion shall include final cleanup of the premises. Base: 120 calendar days. Option A: 15 calendar days. Option B: 20 calendar days. Option C: 30 calendar days. Option D: 25 calendar days. Option E: 10 calendar days. Complete all work within Cut-17 Sta. 0+00 through Cut-41 Sta. 20+00 (BASE work), which are located within an Outstanding Florida Waters (OFW), no later than May 20, 2027.This solicitation is unrestricted. The contract issued will be Firm Fixed Price.

This solicitation will be issued in electronic format only and will be available on or about 02 November 2026. The bid opening date will be specified in the solicitation when it is issued. No additional media (CD-ROM, floppy disks, facsimiles, etc.) will be provided. Paper copies of this solicitation will not be available. Other methods of requesting a package will not be honored. The North American Industry Classification System (NAICS) code is 237990, Other Heavy and Civil Engineering Construction and the size standard is $37,000,000.00.

Offerors must be registered in the System for Award Management (SAM) in order to be eligible to receive an award from any Government solicitation. Call 1-866-606-8220 for more information or visit the SAM website at www.sam.gov. After completing SAM, in order to download documents contractors and their subcontractors must register at www.sam.gov. In order to locate solicitation, Contractors can go to www. sam.gov and search for the solicitation number.

Contractors can register to be put on a plan holders list that others can access through the www.sam.gov website. It is the Offerors responsibility to check the Internet address provided as necessary for any posted changes to this solicitation and all amendments. For additional information or assistance, please contact Ruth Rodriguez, Contract Specialist, email ruth.c.rodriguez@usace.army.mil or Rosalind Shoemaker, Contracting Officer, phone (910) 251-4436, email rosalind.m.shoemaker@usace.army.mil.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 25, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy