Maintenance dredging of Arthur Kill, NY and NJ
The Army Corps of Engineers New York District is surveying dredging firms before a planned job to remove about 150,000 cubic yards of silt, clay and some sand from the Arthur Kill reach of New York and New Jersey Harbor, to -50 feet below mean lower low water (MLLW).
Official title: Maintenance Dredging of New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project
- Deadline
- Dec 2, 2:00 PM ET
- 7 days left
- Who can respond
- Any business
- Market research, not a bid
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- Not stated
- Buyer: W2SD Endist New York
What they're buying
Work is expected in summer or fall 2027, and this notice is a market survey asking whether you are willing and able to do it.
Top catches
“the proposed work can only be performed by utilizing a mechanical clamshell dredge with environmental bucket” Notice text
Only a mechanical clamshell dredge with an environmental bucket can do this work, according to the notice. If you do not own or cannot firmly secure one, you should likely not bid.
“The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals” Notice text
If you are the apparent low bidder, you must give the government copies of all transport, dewatering, processing and placement permits within 35 calendar days. You must line up the upland site and its permits before you bid.
Read by AI (Claude Haiku) on Nov 18, 2026 from the notice. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Mechanically dredge about 150,000 cubic yards to -50 feet MLLW plus 1 foot of allowable over-depth
- Use a mechanical clamshell dredge with environmental bucket
- Transport and place dredged material at a contractor-provided, state-permitted upland site
- Provide tugs, sealed hull barges and survey vessels for dredging, transport and placement
- Maintain an integrated production rate of at least 3,000 cubic yards per calendar day
- Start work within 5 calendar days after receiving the Notice to Proceed
Who did it before
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Dredge type limits who can bid. Only a mechanical clamshell dredge with an environmental bucket can do this work, according to the notice. If you do not own or cannot firmly secure one, you should likely not bid.
- Permits due 35 days after low bid. If you are the apparent low bidder, you must give the government copies of all transport, dewatering, processing and placement permits within 35 calendar days. You must line up the upland site and its permits before you bid.
- Production rate is a hard requirement. You must keep at least 3,000 cubic yards per calendar day, which implies at least 50 days of dredging for 150,000 cubic yards. Check that your equipment, scows and processing capacity can meet this rate before you answer question 17.“maintain an integrated production rate of at least 3,000 cubic yards per calendar day” Notice text
- Survey answers due 2 PM December 2. Survey responses are due at 2:00 PM on Wednesday, December 2, 2026, at UTC-05:00. Send your answers before that time and confirm where to send them, since the notice does not say.“Response deadline: 2026-12-02T14:00:00-05:00” SAM.gov record
Key terms
| Contract period | Work expected summer or fall 2027Contract length and option periods are not stated.Notice text |
|---|---|
| How to submit | Answer the survey questions; delivery method not statedNo email address, portal or mailing address is given in the provided text.Notice text |
| Contract type | Market survey, not a bidNo solicitation is issued here. The notice asks about interest and capability.SAM.gov record |
How to respond
- Check whether you own or can secure a mechanical clamshell dredge with an environmental bucket, plus tugs, sealed hull barges and survey vessels.
- Identify a state-permitted upland placement site and confirm you can get the transport, dewatering and placement permits within 35 calendar days of being named apparent low bidder.
- Gather your reference contact with phone number, your bonding capacity and your largest prime contract value for the survey questions.
- Send your survey answers by 14:00 (UTC-05:00) on Wednesday, December 2, 2026. Where and how to send them: Not stated.
Not stated in what we read
- Estimated value of the work
- Contract length, option periods and payment terms
- Whether the work will be set aside for small businesses, and the size standard if so
- Where and how to send survey answers
- Whether and when a solicitation with bid due dates will be issued
- Who pays for or provides the upland placement site and its fees
Notice text
Market Survey Background Information The New York District of the U.S. Army Corps of Engineers (USACE) proposes to perform maintenance dredging of the New York and New Jersey Harbor – Arthur Kill 50 foot Reach Federal Navigation Project to a depth of -50 feet Mean Lower Low Water (MLLW) plus 1 foot of allowable over-depth. The proposed maintenance dredging would remove approximately 150,000 cubic yards (CY) of material from the critical shoal area.
The dredged material would be dredged and subsequently placed at a suitable, contractor provided, state permitted upland placement site(s). The dredged material is expected to consist primarily of silt, clay, and some sand. Based on the past dredging projects within the New York Harbor, and anticipated restrictions found in the New York State Department of Environmental Conservation Water Quality Certificate, the proposed work can only be performed by utilizing a mechanical clamshell dredge with environmental bucket.
Additionally, tug-boats, sealed hull barges and survey vessels will be needed to perform the work during the dredging, transport, processing and placement activities. The dredging, transport and placement at a suitable, contractor provided, state permitted upland placement site(s) would be required to meet all federal, state, and local criteria required by the government agencies having jurisdiction where the dredging and placement sites are located.
All necessary permits required for the dredged material placement will be provided by the contractor to the government. The apparent low bidder shall, within 35 calendar days from the date the apparent low bidder is notified of being such, provide copies of all required permits and approvals for transportation, transfer, dewatering, processing, and final placement of dredged material, and shall submit evidence of such permits and approvals to the government.
Once the contract is awarded, the contractor will be required to commence work within five (5) calendar days after the date of receipt of the Notice to Proceed and maintain an integrated production rate of at least 3,000 cubic yards per calendar day for the dredging and placement of the dredged material. The presence of the dredging equipment in the channel will impact ship traffic, and it is necessary to maintain this production rate while minimizing the duration of this impact.
The proposed work is anticipated to take place in the summer / fall of 2027. SURVEY OF THE DREDGING INDUSTRY The following confidential survey questionnaire is designed to apprise USACE of prospective dredging contractors’ project execution capabilities. Please provide your response to the following questions. All questions are in regard to the Arthur Kill 50 foot Reach maintenance dredging project. General 1. Have you ever worked on dredging jobs similar in nature to this project?
If so, please describe the project and for whom the work was performed. Identify a point of contact and phone number, as a reference of relevant experience. 2. Have you performed dredging within the waters of the Port of New York and New Jersey? 3. Do you have experience with the placement of dredged material at a suitable, contractor provided, state permitted upland placement site? Please list your experience. 4. What percentage of work (volume of material dredged, transported, processed and ultimately placed) can you perform with your own equipment or equipment owned by another dredging contractor?
5. Would you be willing to bid on the project previously described? If the answer is No, please explain why not. 6. Would you be bidding on this project as a sole contractor, prime contractor with subcontractor(s) or as a joint venture? 7. Is there a dollar limit on the size of contract that you would bid? If so, what is that limit? 8. What is the largest dredging contract, in dollars, on which you were the prime contractor? 9. What is your bonding capacity per contract?
What is your total bonding capacity? 10. Do you have experience using USACE Resident Management System (RMS) 3.0 for delivering Submittals, Daily Dredging Reports and Pay Estimates? 11. In the event that the USACE transitions from Resident Management System (RMS) to an alternative construction management system during the contract, will the contractor be ready to adapt to the new management system? 12. Do you have experience applying USACE EM 385-1-1 (Mar 2024) and all requirements?
Deficiencies observed on site will require immediate attention and action to meet all applicable safety codes. Equipment 13. What type of dredge equipment do you own and/or operate that is suitable for the work described? Do you own a mechanical dredge with a closed environmental clamshell bucket? Please list each piece of equipment capable of performing the work described, i.e. dredging, transfer, transportation, processing and final placement of the material.
For each dredge that you list, please specify its bucket size(s), and any other salient characteristics. 14. Identify which dredge(s), including support equipment (tug, crew boat, scows, etc.), you would employ on this project. Also, for each dredge, identify the maximum dredging depth. 15. Do you own material scows? If so, how many do you have available for use? Please list the name of the scow, its type (ocean-going, sealed hull, etc) and the capacity.
16. Do you have the capability to process the dredged material on your own? If so please explain. If not, what commercial provider of dredge material processing will you engage for this project? What is the daily processing capacity in either case? 17. Will you be able to meet a production rate of 3,000 cubic yards per calendar day and complete all work? 18. Do you have experience with the use of an automated Dredged Material Monitoring System (Black Box / Silent Inspector) employing a Dredged Material Inspector (DMI)?
As published on SAM.gov.
Contacts
- Orlando Nieves, orlando.nieves@usace.army.mil
- Matthew Lubiak, matthew.e.lubiak@usace.army.mil
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 18, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 2, 2:00 PM ET7 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 237990, other heavy and civil engineering construction, soonest deadline first.
- Department of Veterans AffairsStormwater upgrades at Crown Hill cemetery, Indianapolis, IN
- Bureau of Indian Affairs96-inch culvert replacement on BIA Route 3, Cibecue, AZ
- Department of the ArmyNew baseball stadium at USAF Academy, Colorado Springs, CO
- Department of the ArmyLock and dam rehabilitation, Chicago, Illinois
- Department of the ArmyDredge containment repairs, Savannah and Brunswick, GA
- Departmental OfficesWater recirculation pipeline and pump, Pixley refuge, CA
- Department of the ArmyMaintenance dredging task orders, South Atlantic region
- Department of the ArmyTainter valve repair at The Dalles Lock and Dam, WA
Free · at most one email a morning
Get new notices from Department of the Army by email
Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy