Engine control units on 3 generators, Camp Lejeune, NC

Replace the engine control units on three emergency generators at Camp Lejeune, then load-test and commission them with an independent commissioning agent.

Official title: NH100 Engine Control Unit Replacement

Deadline
Dec 4, 1:00 PM ET
8 days left
Who can bid
Small businesses
Size standard for NAICS 236220: $45 million in average annual receipts · Who qualifies
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Camp Lejeune, NC
Buyer: Navfacsyscom Mid-Atlantic

What they're buying

Amendment 0004 sets a 90-day period of performance, and only four listed contractors may submit a proposal.

Top catches

Only four firms may bid
“ONLY THE FOLLOWING LIST OF CONTRACTORS MAY SUBMIT A PROPOSAL FOR THIS PROJECT:” RFP 270700.pdf, page 1

If your firm is not one of the four listed contractors, you cannot submit a proposal, even though the SAM.gov record shows a small business set-aside. If you are listed, confirm your company details match the list before you spend time on pricing.

Bid bond is required and strict
“the bid bond should be 20% of the proposal amount.” RFP 270700.pdf, page 2

At this estimated value, a bid bond of 20 percent of the proposal amount is required. Payment and performance bonds follow at award. A proposal without a required bid bond by the deadline is removed from consideration, so line up your surety early.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 5 of 7 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Replace the engine control units on 3 generators. Amendment 0003 names new MTU ECUs, pulse-controlled fuel injectors, harnesses and Marathon DVR 2400 voltage regulators in its tests.
  • Hire an independent Commissioning Agent to direct and document functional performance tests of each generator and the emergency power system.
  • Load-test each generator to full nameplate rating of 910 kW at 0.8 power factor, using contractor-furnished load banks and temporary feeder cables. The Government provides diesel fuel from bulk storage.
  • Run an integrated system test: simulate loss of utility power, confirm critical loads transfer within 10 seconds, check paralleling and load sharing on the RussElectric switchgear, and confirm retransfer and cooldown.
  • Closeout: a signed NFPA 110 commissioning and functional test report, updated as-built wiring diagrams, O&M manuals under Section 01 78 23, and staff training.
  • Follow wage determination NC20260010 for Onslow County building work, and check whether the paid sick leave note applies to this contract.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Only four firms may bid. If your firm is not one of the four listed contractors, you cannot submit a proposal, even though the SAM.gov record shows a small business set-aside. If you are listed, confirm your company details match the list before you spend time on pricing.
  • Bid bond is required and strict. At this estimated value, a bid bond of 20 percent of the proposal amount is required. Payment and performance bonds follow at award. A proposal without a required bid bond by the deadline is removed from consideration, so line up your surety early.
  • Email is the only stated route. Proposals go by email to two Navy addresses, due Friday, December 4 at 1:00 PM EST. Send early, keep proof of sending, and do not rely on any other route, because the notice names none.“E-Mail Address for Proposals: jessica.r.huebner.civ@us.navy.mil and” RFP 270700.pdf, page 3
  • Period of performance now 90 days. Amendment 0004 overrides the RFP's 60-day period, so price for 90 days. Confirm when the clock starts, because the RFP ties it to COR-verified on-site receipt of OEM materials.“A 90-day period of performance is approved, vice the 60-day period of performance.” Amend 0004.pdf, page 2
  • Liquidated damages and work hours. Each calendar day late costs $4,686.73. Regular hours are 0730 to 1600, Monday to Friday, so weekend or after-hours work needs written COR approval at least 15 calendar days ahead; build that into your schedule and price.“Liquidated Damages: $4,686.73 per Calendar Day” RFP 270700.pdf, page 2
  • Subcontractor safety limits. Every subcontractor must have an EMR of 1.10 or less and a DART rate of 3.4 or less when you sign with them. Check each one before you sign, because relief is case by case and is not assumed.“Subcontractors on this Contract must have an effective EMR less than or equal to 1.10” Combined DIV 01 specs small projects.pdf, page 48

Key terms

Who can bidOnly the four firms on the RFP listThe SAM.gov record shows a small business set-aside. The notice places the list on the General Requirements cover page, but the list appears on RFP page 1.RFP 270700.pdf, page 1
Contract period90 days (changed from 60)The RFP says 60 days after the COR verifies on-site receipt of OEM materials. Amendment 0004 does not restate the start point.Amend 0004.pdf, page 2
How they chooseLowest priceThe notice gives no technical trade-off or other evaluation factor.RFP 270700.pdf, page 2
How to submitEmail to jessica.r.huebner.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.milThe notice names no portal or mail option. A bid bond may be sent electronically with the proposal.RFP 270700.pdf, page 3
Questions dueMonday, November 30, 2026, 2:00 PM ESTSend questions to jessica.r.huebner.civ@us.navy.mil.RFP 270700.pdf, page 3
Estimated valueBetween $500,000 and $1,000,000This is the RFP's estimated cost range, not a price you can bid.RFP 270700.pdf, page 2
Contract typeFixed-price constructionThe payment clauses cited are fixed-price construction clauses. The notice does not name the contract type directly.Combined DIV 01 specs small projects.pdf, page 8
Site visitNovember 16, 2026, 0900 (already passed)Meet at the Facilities building, NH118, Camp Lejeune. The text does not say whether attendance is required.RFP 270700.pdf, page 2

How to respond

  1. Confirm that your firm is one of the four listed contractors: T.E. Davis Construction Company, Joyce & Associates Construction, Inc., Olympic Enterprises, Inc., or Quadrant Construction.
  2. Send any questions to jessica.r.huebner.civ@us.navy.mil by Monday, November 30, 2026, 2:00 PM EST.
  3. Prepare the proposal. If it is valued at $150K or more, include a bid bond at 20 percent of the proposal amount; an electronic copy may go with the proposal. Required forms and file formats: Not stated.
  4. Email the proposal to jessica.r.huebner.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil before Friday, December 4, 2026, 1:00 PM EST.
  5. Send early and keep proof of sending. Size limits and required subject lines: Not stated.

Attached files

From SAM.gov. Download links open the original files.

  • Amend 0004.pdfAmendment 0004, which changes the period of performance to 90 days. You must read it; it names no form to complete. Read.
  • Combined DIV 01 specs small projects.pdfPart of the Division 01 general requirements (pages 1 to 54 and 214 to 235 only), covering schedule of prices, invoices, insurance, safety and base access. You must read it; pages 55 to 213 were not provided. Read in part (pages 1–54 and 214–235 of 235).
  • Amend 0003.pdfAmendment 0003, which sets commissioning rules and test steps for the generator and switchgear work. You must read it and price the testing. Read.
  • RFP 270700.pdfThe request for proposals with general requirements, schedule, liquidated damages, bonds, wage determination and submission details. You must read it in full; the offer forms it requires are not in the text we reviewed. Read.
  • NH100 REPLACE ENGINE CONTROL UNITS ON 3 GENERATORS revised.pdf Not read: over our length limit.
  • Amend 0002.pdfAmendment 0002, which gives contact details for two vendors, Curtis Power and RussElectric. You must read it; it names no form to complete. Read.
  • Amend 0001.pdf Scanned image, not read.

Not stated in what we read

  • What the revised NH100 scope file and Amendment 0001 say. We could not review them: one was left out for length and the other is a scanned image. You must read both before pricing.
  • The Scope of Work that Amendment 0003 cites (Sections 3 and 4.b). It is not in the text we reviewed.
  • When the 90-day period starts. The RFP ties it to COR-verified on-site receipt of OEM materials, and Amendment 0004 does not restate it.
  • Whether attendance at the November 16 site visit was required, and whether another visit is offered.
  • Pages 55 to 213 of the Division 01 specifications, which were not provided.
  • How the small business set-aside on the SAM.gov record applies alongside the four-firm list.

Notice text

Only M&R MACC Contractors listed on the General Requirements cover page may submit a proposal for this ROICC Camp Lejeune area of responsibility project. See attached documents for scope of work and any applicable drawings.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 26, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Navy by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Navy, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy