Replace boiler exhaust stacks at Rome clinic, NY

The VA wants a contractor to replace the boiler exhaust stacks at the Rome Community Based Outpatient Clinic (CBOC) in Rome, NY.

Official title: Z1DA--NRM CONST - 528A7-18-707 - Replace Boiler Stack Rome CBOC

Deadline
Dec 2, 10:00 AM ET
7 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: 242-Network Contract Office 02 (36C242)

What they're buying

The work includes demolishing old stacks and a chimney, hazardous material abatement, new steel stacks, and re-roofing, to be finished within 270 calendar days.

Top catches

Set-aside missing from SAM record
“This is a 100% Small Business set aside procurement.” 36C24227R0008_2.docx

The SAM record leaves set-aside blank, but the notice text says this is a 100% small business set-aside. Confirm that you meet the size standard before you spend time on the bid.

Submittal deadline conflicts
“All submittals shall be submitted to the CO and COR within ten (10) calendar days after Notice to Proceed (NTP) for written approval.” 36C24227R0008_2.docx

The SOW says all submittals are due within 10 calendar days after notice to proceed, but it also allots 60 days for submittals. Plan for the 10-day date and ask the Contracting Officer which applies.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 21, 2026 from the notice and 4 of 10 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Build a new concrete foundation and steel support structure outside the building, and route three stacks through the existing concrete wall
  • Install two new 14-inch double-wall boiler vents, one per boiler, plus one 12-inch generator exhaust, ending above the roof curb
  • Demolish two boiler exhaust stacks, the generator stack, the concrete and masonry chimney, and the penthouse incinerator and its exhaust piping
  • Abate asbestos and remove other hazardous materials shown on drawing HA-101, under NYSDOL Code Rule 56
  • Cut back the gas line in the penthouse, install a new shut-off valve and cap, and re-roof and seal all openings to match the existing EPDM roof
  • Provide special inspection of the steel support tower under NYS Building Code section 1704.1.1 and section 01 45 35

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Set-aside missing from SAM record. The SAM record leaves set-aside blank, but the notice text says this is a 100% small business set-aside. Confirm that you meet the size standard before you spend time on the bid.
  • Submittal deadline conflicts. The SOW says all submittals are due within 10 calendar days after notice to proceed, but it also allots 60 days for submittals. Plan for the 10-day date and ask the Contracting Officer which applies.
  • Asbestos exclusions can void insurance. Before award you must show general liability insurance with no asbestos exclusions, and this job includes asbestos abatement. Check with your insurer now that your policy covers this work at the $500,000 per occurrence minimum.“evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage” 36C24227R0008_2.docx
  • Acknowledge both amendments. Amendments 0001 and 0002 both change the bid record, and the notice says all amendments must be acknowledged. Acknowledge both in the offer, because the amendment forms warn that failure may result in rejection of your offer.“CONTRACTORS MUST ACKNOWLEDGE ALL SOLICITATION AMENDMENTS.” 36C24227R0008_2.docx
  • Deadline is 10 AM EST, email only. The notice first says 10 AM EDT, but amendment 0001 says read EDT as EST, so the deadline is 10:00 AM EST on Wednesday, December 2, 2026. Proposals go by email only, so send early and confirm the email was received.“Any reference to Eastern Daylight Time (EDT) in the solicitation should read as Eastern Standard Time (EST).” 36C24227R0008 0001.docx
  • Signed Buy American form due with offer. The signed FAR 52.225-9 certificate must be included with your proposal. The clause also requires domestic construction material, so check the source of your steel and vent materials before you price.“The signed certificate must be received with the proposal.” 36C24227R0008_2.docx

Key terms

Who can bidSmall businesses only (100% set-aside per notice text)SAM record leaves set-aside as Not stated. You need an active SAM registration with a Unique Entity Identifier when you submit.36C24227R0008_2.docx
Contract period270 calendar days from notice to proceedPer the SOW: 60 days for submittals, 30 days for abatement, 180 days for construction.36C24227R0008_2.docx
How they chooseFour factors: Technical, Past Performance, Schedule, PriceEvaluated under RFO FAR 12.203. The notice does not state how the factors are weighted.36C24227R0008_2.docx
How to submitEmail to Ryan.Seburn@va.gov by the deadlineA signed Buy American certificate must be received with the proposal.36C24227R0008_2.docx
Questions dueMonday, November 16, 2026, 10:00 AM EDT (passed)Closed. Answers were posted in amendments 0001 and 0002.36C24227R0008_2.docx
Estimated valueMagnitude of construction: $500,000 to $1,000,000A range only. No exact estimate appears in the text we reviewed.36C24227R0008_2.docx
Contract typeConstruction contract with fixed-price payment clausesInvoices are submitted as per schedule of values.36C24227R0008_2.docx
Site visitHeld Monday, November 9, 2026, 10:00 AM EDT (passed)No other site visits will be allowed. The sign-in sheet was posted in amendment 0001.36C24227R0008_2.docx

How to respond

  1. Confirm your SAM.gov registration with a Unique Entity Identifier is active and that your annual Vets4212 report is filed before you submit.
  2. Sign the FAR 52.225-9 Buy American certificate and include it with your proposal, because it must be received with the proposal. The certificate form itself was not in the text we could review, so get it from SAM.gov.
  3. Acknowledge amendments 0001 and 0002 in Block 19 of the offer form, and complete and sign the offer section (Blocks 14 to 20).
  4. Address the Technical factor by showing experience replacing boiler exhaust stacks in a healthcare setting, and name the Competent Person / Safety Manager who will be assigned.
  5. Email the complete proposal to Ryan.Seburn@va.gov so it arrives by 10:00 AM EST on Wednesday, December 2, 2026. Page limits, file format, and file size limits: Not stated.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Whether performance and payment bonds are required, and by when, is unclear in the text we reviewed.
  • The wage rates in WD+Oneida+5-18-2026.docx were left out for length, so we could not review them. You must read this file before you price labor.
  • The final bid drawings, the scanned perforated screen drawing, and boilerspec+1.pdf could not be reviewed. You must read them.
  • Specification pages 39 to 782 were not provided. You must read them on SAM.gov.
  • Proposal page limits, format, and number of copies: Not stated.
  • Liquidated damages: Not stated in the text we reviewed.

Notice text

CONTINUATION OF SF 30 BLOCK 14 AMENDMENT DESCRIPTION 0002 AGAINST SOLICITATION NO. 36C24227R0008 1. This amendment answers the following vendor questions: Number of boiler vents: On M-101 (Boiler and Generator Exhaust Plan, Phase II), the new wall penetration/chase is labeled with two 14" I.D. pipes and one 12" I.D. pipe. Keynote 2 calls for a single "new 14" boiler double walled insulated vent stack," and the cutover notes describe that one vent connecting to Boiler #1 and continuing to within two feet of Boiler #2's vent, so one common 14" vent appears to serve both boilers.

The solicitation description, however, refers to "two new steel boiler exhaust stacks." Please confirm whether the work is: (a) one 14" double-wall vent common to Boiler #1 and Boiler #2, plus the 12" generator exhaust, or (b) two separate 14" double-wall vents (one per boiler), plus the 12" generator exhaust. If (a), please confirm what the second 14" pipe shown at the penetration represents. Answer: Confirming: it is (b) two separate 14" double-wall vents (one per boiler), plus the 12" generator exhaust. b) Draft control or stack fan: No stack fan, draft inducer, or boiler-outlet draft control appears on the drawings.

Section 23 51 00 (paragraph 2.2, Boiler Outlet Dampers and Accessories) refers to automatic draft control specified in Section 23 09 11, but Section 23 09 11 is not included in the solicitation. Please confirm whether: (a) the new boiler vent is intended to operate on natural draft (no fan or draft control required), or (b) a mechanical draft fan and/or barometric or motorized draft control is expected. If so, please issue Section 23 09 11 or identify the required equipment and control sequence.

Answer: Confirming: it is (a) the new boiler vent is intended to operate on natural draft (no fan or draft control required). c) Design heating load and operating water temperatures: Please provide the building design heating load (or recent gas and oil usage or meter data), and the normal heating-water supply and return temperatures for the two existing Fulton Vantage boilers. Return-water temperature sets the flue-gas temperature, which governs the vent sizing and draft calculation.

Please also confirm whether the two boilers operate as lead/standby (N+1) or are both required at design load. Answer: Replacing the boiler is not part of the contract. Boilers have inducer fans. There is no stack fan or boiler draft controls to be installed. d) Facility designation: Please confirm whether the Rome CBOC is designated mission-critical under VA Physical Security and Resiliency Design requirements, or otherwise required to keep heating on during a utility outage, as this affects the vent design for both fuels.

Answer: Rome CBOC is NOT designated as a Critical/Mission Critical facility. CBOCs are generally outpatient facilities rather than hospitals with inpatient, emergency, surgical, or continuity-of-government functions. Therefore, absent a specific VA risk assessment or designation, the Rome CBOC would not ordinarily be assumed to be mission critical. e) Fuel oil and emergency power: Boiler #2 fires #2 fuel oil as a backup fuel. Please confirm (a) whether the vent must be designed for oil firing on Boiler #2 (and on Boiler #1, if applicable), (b) the size and required reserve of the existing #2 oil tank, and (c) whether the boilers and their associated vent or draft equipment are served by emergency power through an automatic transfer switch.

Answer: The specified vent material (AL-29-4C) is compatible for operating the boilers on natural gas or #2 oil. This contract does not include altering the existing fuel oil tank, day tank, the boilers, or the generator. We are eliminating the existing exhaust stack and installing a new exhaust stack in a different location to serve the two existing boilers and existing emergency generator. All other terms and conditions remain unchanged.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 21, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of Veterans Affairs by email

Each morning we'll send the new solicitations and sources-sought notices from Department of Veterans Affairs, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy