Road realignment and roundabout, Camp Lejeune, NC
Realign the Wallace Creek service road with A Street at McHugh Boulevard, build a roundabout, demolish Building 41 and replace parking at Camp Lejeune, NC.
Official title: P1555U Wallace Creek Service Road
- Deadline
- Dec 1, 2:00 PM ET
- 5 days left
- Last time
- $1.43M
- Likely Riza Construction Inc
- Place
- Camp Lejeune, NC
- Buyer: Navfacsyscom Mid-Atlantic
What they're buying
The work runs 730 days after award and the notice estimates its cost at $5,000,000 to $10,000,000.
Top catches
“Only Civil/Paving MACC Contractors listed on the General Requirements cover page may submit a proposal for this ROICC Camp Lejeune area of responsibility project.” Notice text
The SAM.gov record says HUBZone set-aside, but the notice limits proposals to three named MACC contractors. If your firm is not on the list, do not submit; ask the contracting officer how the set-aside applies before you price.
“This amendment should be acknowledged when your proposal is submitted.” Amend 0006.pdf, page 1
Six amendments change or answer questions, and the newest is dated 11/25/26. Acknowledge each one on your offer, or the proposal may be rejected. Read each answer before you price.
Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 15 of 19 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Realign the Wallace Creek service road with A Street and build a roundabout at the new four-way intersection.
- Undercut and dispose of 750 cubic yards of unsuitable subgrade soil and replace it with imported structural fill. An option adds 250 cubic yards.
- Handle, stockpile, sample, analyze and dispose of 750 cubic yards of surplus excavation spoils that may be contaminated.
- Remove 150 tons of buried debris and remove or relocate existing utilities, priced at 50 linear feet in each of four utility categories.
- Demolish Building 41 and replace the Building 17 parking lot on the Building 41 site.
- Optional items: landscaping (ELIN 0002), narrowing an 8-foot sidewalk to 6 feet (ELIN 0003), and concrete splitter islands (ELIN 0004).
Who did it before
$1.43M
on the contract that likely holds this work now: Riza Construction Inc. It ended Jun 19, 2026.
Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.
What to watch for
- HUBZone set-aside conflicts with list. The SAM.gov record says HUBZone set-aside, but the notice limits proposals to three named MACC contractors. If your firm is not on the list, do not submit; ask the contracting officer how the set-aside applies before you price.
- Acknowledge all six amendments. Six amendments change or answer questions, and the newest is dated 11/25/26. Acknowledge each one on your offer, or the proposal may be rejected. Read each answer before you price.
- Bid bond due with proposal. Proposals of $150,000 or more need a bid bond for 20% of the proposal amount, and proposals of $35,000 or more need a payment bond. A missing bond by the deadline removes your proposal, so arrange the bond before you send it.“Failure to submit a required bid bond by the deadline will result in your proposal being removed from consideration.” RFP P1555U.pdf, page 2
- Contaminated spoils and PFAS disposal. You must price testing, stockpiling and disposal of 750 cubic yards of surplus spoils that may contain PFAS, petroleum, metals and SVOCs. Ask for lab and disposal limits before you price this line.“(including, but not limited to, PFAS, petroleum, metals, and SVOCs)” RFP P1555U.pdf, page 13
- Daily damages of $1,263.51. If the work runs late, the government can charge $1,263.51 for each calendar day. Build that exposure and your schedule risk into your price.“Liquidated Damages: $1,263.51 per Calendar Day” RFP P1555U.pdf, page 2
- Environmental approval dates from 2021. The only environmental decision provided is dated 20 Jan 2021 and lists an end-by date of 2-May-23. It also says it may not authorize work. Ask the contracting officer whether it still covers this project.“End By Date: 2-May-23” NEPA_P1555U_POM27_20230714.pdf, page 3
Key terms
| Who can bid | Only the listed MACC contractors may submitThree firms are named on the RFP cover page. The SAM.gov record also shows a HUBZone set-aside, which conflicts with this list.RFP P1555U.pdf, page 1 |
|---|---|
| Contract period | 730 days after awardThis is the contract completion period. Liquidated damages apply after that.RFP P1555U.pdf, page 2 |
| How they choose | Lowest priceWhether the optional items are scored in the comparison is not stated.RFP P1555U.pdf, page 2 |
| How to submit | Email to two Navy contactsSend to anna.m.lundquist.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil. File format and size limits are not stated.RFP P1555U.pdf, page 2 |
| Questions due | 11/16/2026 3:00 PM EST (passed)The RFI cutoff has passed. Later answers appear in Amendments 0004 to 0006.RFP P1555U.pdf, page 3 |
| Estimated value | $5,000,000 to $10,000,000Estimated cost range from the RFP. Bond requirements depend on your proposal amount.RFP P1555U.pdf, page 2 |
| Site visit | 11/09/2026 0900 EST (date has passed)Held at the St Francis Xavier Chapel parking lot. Whether attendance was mandatory is not stated.Amend 0002.pdf, page 1 |
How to respond
- Confirm that your firm is one of the three listed contractors on the RFP cover page. If it is not, do not submit a proposal.
- Email your proposal to anna.m.lundquist.civ@us.navy.mil and lauren.f.loconto.civ@us.navy.mil by 2:00 PM EST on Tuesday, December 1, 2026.
- Acknowledge receipt of Amendments 0001 through 0006 on each copy of your offer.
- If your proposal is $150,000 or more, include a bid bond for 20% of the proposal amount in a FAR 53.300 format. An electronic copy may be sent with the proposal.
- Price each ELIN on the pricing sheet, including the options. File format, file size and subject line rules are not stated.
Attached files
From SAM.gov. Download links open the original files.
- 1810206dwg07of08_LANDSCAPE.pdfPlanting plan and plant schedule. Read it to price the landscape options. Read in part.
- RFP P1555U.pdfThe solicitation cover list, general requirements, bond rules and pricing sheet. You must complete and return the pricing sheet. Read in part.
- P-1555U WCSR PROD.pdfPermit record that assigns some permits, including well abandonment, to the construction contractor. You must read it; you do not sign it. Read in part.
- Amend 0001.pdfChanges specification section 01 78 00 on the interim DD Form 1354 submittal. You must read it and acknowledge it. Read in part.
- 1810206dwg05of08_CIVIL SITE.pdf Not read: over our length limit.
- 1810206spc1of1.pdf Not read: over our length limit.
- 1810206dwg08of08_ELECTRICAL.pdf Not read: over our length limit.
- Amend 0004.pdfAnswers on the force main and water line relocation. It tells you to assume SDR26 pipe for pricing. You must acknowledge it. Read in part.
- Amend 0005.pdfAnswers on optional landscape items, the dumpster pad, overhead service and duct bank. You must acknowledge it. Read in part.
- 1810206dwg03of08_SURVEY.pdfSurvey sheets with the subsurface utility table. Several utilities need relocation, so read the table before you price. Read in part.
- 1810206dwg04of08_GEOTECHNICAL.pdfGeotechnical sheets with boring records and lab results. Only headers were readable, so read the boring logs yourself. Read in part.
- Amend 0006.pdfAnswers an RFI on edging size, issued 11/25/26. You must acknowledge it. Read in part.
- 1810206dwg06of08_CIVIL GRADING UTILITIES.pdf Could not be read.
- 1810206dwg01of08_GENERAL.pdfCover and traffic control drawings. Only some pages were provided, so read the full sheet set yourself. Read in part.
- Amend 0003.pdfA site visit amendment. The text provided stops early, so read the full amendment on SAM.gov and acknowledge it. Read in part.
- 1810206dwg02of08_ENVIRONMENTAL.pdfExisting environmental site conditions plan. The text is garbled in the copy provided, so review the drawing yourself. Read in part.
- Amend 0002.pdfSchedules the site visit for 11/09/2026. The date has passed, so read it for reference only. Read in part.
- NEPA_P1555U_POM27_20230714.pdfA 2021 categorical exclusion memo with conditions on groundwater, UXO, stormwater and permits. You must read it; you do not sign it. Read in part.
- P-1555U WCSR DD1354 27FEB2026.pdfDraft property transfer form. Amendment 0001 requires an interim version from the contractor after the pre-construction conference. Read it for pricing. Read in part.
Not stated in what we read
- Whether the 11/09/2026 site visit was mandatory, and what was said there. The text of Amendment 0003 was cut off.
- Whether the optional items (ELIN 0002 to 0008) count in the lowest-price comparison.
- How the HUBZone set-aside applies to the three named contractors.
- Several attachments were not provided: the specification book 1810206spc1of1.pdf, civil site drawings (sheet 5), electrical drawings (sheet 8), and civil grading and utilities drawings (sheet 6), which could not be read. You must review them yourself.
- File format, file size and subject line rules for the emailed proposal.
- Payment terms and whether price escalation applies.
Notice text
Only Civil/Paving MACC Contractors listed on the General Requirements cover page may submit a proposal for this ROICC Camp Lejeune area of responsibility project. See attached documents for scope of work and any applicable drawings.
As published on SAM.gov.
Contacts
- Jessica Huebner, jessica.r.huebner.civ@us.navy.mil, 9104515892
- Lauren Loconto, lauren.f.loconto.civ@us.navy.mil, 9104515916
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at Department of the Navy for the same kind of work (NAICS 237310, service code Z1LB) in North Carolina that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
| Contract | Obligated | Ends | State |
|---|---|---|---|
| FY24 Repair Fencing Multiple LocationsRiza Construction Inc · N4008524F6636 | $1,426,011 | Jun 19, 2026ended | NC |
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 26, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 1, 2:00 PM ET5 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 237310, highway, street, and bridge construction, soonest deadline first.
- Departmental OfficesWaterman canal gate for Wheeler refuge, Decatur, AL
- Department of the ArmyRoads, parking and grounds renovation, Detroit, MI
- Departmental OfficesRoad and bridge repair at national parks nationwide
- Federal Highway AdministrationThree bridges and a culvert on SR 35, Mimbres, NM
- Forest ServiceRoad and trailhead upkeep, Little Missouri Grassland, ND
- Department of the Air ForceTaxiway resurfacing at North Auxiliary Airfield, SC
- Department of the Air ForceAirfield rubber removal and striping, Dover AFB, DE
- Department of the NavyPedestrian footbridge replacement at Camp Lejeune, NC
Free · at most one email a morning
Get new notices from Department of the Navy by email
Each morning we'll send the new solicitations and sources-sought notices from Department of the Navy, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy