1. Opportunities
  2. Department of Defense
  3. Department of the Army
  4. W9127827BA002

Maintenance dredging of Pensacola Harbor channel

The Army's Mobile engineer district wants a contractor to perform maintenance dredging of sand in the Pensacola Entrance Channel, with dredged material placed on Perdido Key Beach.

Official title: Pensacola Harbor Navigation Channel Maintenance Dredging

Deadline
Dec 9, 2:00 PM CT
14 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: W074 Endist Mobile

What they're buying

Dredges must be able to reach 30 feet, and the contract length is not stated.

Top catches

Large dredge fleet required
“Dredges must be capable of dredging to a depth of 30 feet and be complete with crew, management staff and support equipment including tugs and various other floating plants” Notice text

You must be able to supply dredges that reach 30 feet, with crew, tugs and floating plants. If you do not own this fleet, you would need a partner that does or you should not bid.

Set-aside status not given
“Set-aside: Not stated” SAM.gov record

The record gives no set-aside, so the notice does not say whether small businesses get a preference or are limited to bidding. Ask the contracting office before you spend time on a bid.

3 more catches below ↓

Read by AI (Claude Haiku) on Nov 20, 2026 from the notice. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Dredge sand maintenance material from the Pensacola Entrance Channel to a depth of 30 feet capability
  • Provide a dredge of one or more types: hydraulic cutterhead pipeline, trailing suction hopper, or mechanical with scows
  • Provide a full crew, management staff and support equipment
  • Provide tugs and other floating plants normally needed for a large dredging operation
  • Place dredged material west of the Pensacola Entrance Channel along Perdido Key Beach

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Large dredge fleet required. You must be able to supply dredges that reach 30 feet, with crew, tugs and floating plants. If you do not own this fleet, you would need a partner that does or you should not bid.
  • Set-aside status not given. The record gives no set-aside, so the notice does not say whether small businesses get a preference or are limited to bidding. Ask the contracting office before you spend time on a bid.
  • No quantity or attachments. The notice gives no volume of sand, no schedule, and no attached drawings or specifications. You cannot price the job from this notice alone, so ask the contracting office for quantities before you bid.“The material type expected for this requirement will be maintenance material typical for Pensacola Entrance Channel composed of sand.” Notice text
  • Deadline zone not named. The record gives 14:00 with a -06:00 offset but no time zone name. Confirm the exact cutoff with the contracting office and submit before 14:00 on Wednesday, December 9.“2026-12-09T14:00:00-06:00” SAM.gov record
  • Place of work left blank. The record gives no place of performance, but the notice names the Pensacola Entrance Channel and Perdido Key Beach. Confirm the work site before you price travel and mobilization.“Place of performance: Not stated” SAM.gov record

How to respond

  1. Confirm the response deadline of Wednesday, December 9, 2026 at 14:00 with a -06:00 offset, since the notice does not name the time zone.
  2. Where to send your response: Not stated.
  3. Format and required contents of your response: Not stated. The notice lists no attached files.
  4. Decide whether you can supply the dredge fleet described, or whether you would need a partner that owns it.
  5. Confirm the set-aside status and the quantities with the contracting office before you price the work.

Not stated in what we read

  • Estimated value of the contract
  • Contract period and performance dates
  • Volume of sand to be dredged and the dredging schedule
  • Set-aside status and size standard
  • How, where and in what format to submit a response
  • Evaluation basis and whether the government furnishes any equipment

Notice text

This requirement is for hydraulic cutterhead pipeline dredges, trailing suction hopper dredges, and/or mechanical dredges with scows. Dredges must be capable of dredging to a depth of 30 feet and be complete with crew, management staff and support equipment including tugs and various other floating plants as would normally be expected to support a large dredging operation. The material type expected for this requirement will be maintenance material typical for Pensacola Entrance Channel composed of sand. Material dredged will be placed west of the Pensacola Entrance Channel along Perdido Key Beach.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 20, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy