Engine overhaul on USCGC Sturgeon, South Portland, ME
Quotes are sought to overhaul both main MTU diesel engines on the 87-foot USCGC Sturgeon and update its control system, performed dockside at its home pier in South Portland, Maine.
Official title: USCGC STURGEON (WPB-(87336) DS FY27
- Deadline
- Dec 8, 11:00 AM ET
- 13 days left
- Last time
- $473K
- Likely Rockland Marine Corp
- Place
- South Portland, ME
- Buyer: SFLC Procurement Branch 1(00080)
What they're buying
Work runs from 5 April to 5 May 2027 on a firm fixed price basis, and quotes are due Tuesday, 8 December 2026.
Top catches
“Close Date is changed from 08-DEC-26 13:00:00 to 08-DEC-26 11:00:00.” 70Z08026QPBPL00440003_US.pdf, page 2
Quotes are now due at 11:00 AM on Tuesday, December 8, 2026, not 1:00 PM as Amendment 0002 showed. Send your email well before 11:00 AM, because the RFQ requires delivery at or before the exact time.
“Quoters shall complete Attachment 1, Schedule of Services and include it in their quote.” 70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdf, page 20
Attachment 1, the Schedule of Services, must be included in your quote. This review could not read that file, so you must open it on SAM.gov and fill in every unit price in US dollars, because blank or non-dollar prices make a quote unacceptable.
Read by AI (Claude Haiku) on Nov 20, 2026 from the notice and 5 of 6 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Overhaul both main MTU 8V396 diesel engines, port and starboard, to the W-5 maintenance level, then update the control system configuration to the 87-foot WPB setup.
- Install Government-furnished parts: A and B bank turbochargers, cylinder heads, jacket water pump and starter motor.
- Furnish all gaskets, seals and o-rings you disturb, all other parts not furnished by the Government, and MTU-certified components only.
- Clean and inspect fuel injectors, charge air cooler (ultrasonic cleaning), lube oil cooler, plate cooler, charge air manifold and exhaust sleeves, and inspect cylinder liners in place.
- Supply all engine oils, coolants and inhibitors, and dispose of removed fluids under federal and local law.
- Commission the engines and run dock and sea trials under DIASYS, with a qualified MTU technical representative on site and sea trial results reported.
Who did it before
$473K
on the contract that likely holds this work now: Rockland Marine Corp. It ended Jul 10, 2026.
Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.
What to watch for
- Deadline moved two hours earlier. Quotes are now due at 11:00 AM on Tuesday, December 8, 2026, not 1:00 PM as Amendment 0002 showed. Send your email well before 11:00 AM, because the RFQ requires delivery at or before the exact time.
- Price schedule file not reviewed. Attachment 1, the Schedule of Services, must be included in your quote. This review could not read that file, so you must open it on SAM.gov and fill in every unit price in US dollars, because blank or non-dollar prices make a quote unacceptable.
- Technical plan must answer every item. Your quote needs a graphical planning document covering all three listed items, including a negative answer where a risk does not apply, plus the MTU technical representative's name and resume. A missing item can make the quote unacceptable, so check the list before you send.“Any quote that does not meet or address all Technical Capability submission requirements will be deemed unacceptable and may not be considered for award.” 70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdf, page 22
- Insurance certificate must name the cutter. Before work starts you must carry $500,000 per occurrence ship repairer's liability and comprehensive general liability, plus Longshore and Harbor Workers' and state workers' compensation coverage. The certificate must name the USCG vessel and the contract number, so confirm with your insurer before you bid.“The insurance certificate must provide the name of the US Coast Guard vessel and the contract number as specifically insured.” Attachment 3 - SOW Addendum.pdf, page 1
- Extra work unpaid until modification signed. You cannot start added repairs without the Contracting Officer's written authorization, and you cannot be paid for those hours until a written modification is signed. The RFQ also says you must absorb these repairs within the ship's availability, so plan cash flow and crew time for add-on work.“The contractor shall not be entitled to payment for any hours ordered pursuant to this clause until a written contract modification is executed.” Attachment 3 - SOW Addendum.pdf, page 3
- Only about one month to finish. The performance window is 5 April to 5 May 2027, which is about one month for a full engine overhaul and sea trials. Confirm you can staff the job and get parts in that window, because Coast Guard personnel will not supply labor to finish the contract.“AMEND-This amendment changes the POP from 10 November 2026 - 8 December 2026 to 5 April 2027 - 5 May 2027.” 70Z08026QPBPL00440002_US.pdf, page 1
Key terms
| Who can bid | Small businesses only (100% set-aside)NAICS 336611. The solicitation form lists a size standard of 1300 employees.SAM.gov record |
|---|---|
| Contract period | 5 April 2027 to 5 May 2027Amendment 0002 replaced the original 10 November to 8 December 2026 dates. The window is about one month.70Z08026QPBPL00440002_US.pdf, page 1 |
| How they choose | Best value: past performance and technical capability, then pricePrice gains weight as technical ratings get closer. Award may go to a higher-priced quote.70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdf, page 22 |
| How to submit | Email to the Contracting Officer and Contract SpecialistInclude a signed, dated cover letter, the Attachment 1 price schedule, past performance, and the technical planning document.70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdf, page 19 |
| Questions due | Tuesday, December 1, 2026 (time not stated)Send all questions in one email that cites solicitation 70Z08026QPBPL0044. Answers come by amendment.70Z08026QPBPL00440003_US.pdf, page 3 |
| Contract type | Firm fixed priceExtra repairs found during work are priced as change requests, using your proposed labor rate and material percentage.70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdf, page 33 |
| Site visit | Urged and expected, to be completed by 1 December 2026Contact MK1 Clay Woodworth at (757) 477-7998 or Clay.V.Woodworth@uscg.mil.70Z08026QPBPL00440003_US.pdf, page 2 |
How to respond
- Send all questions in one email by Tuesday, 1 December 2026, citing solicitation 70Z08026QPBPL0044. Ask whether the fire plan named in the specification must go with your bid, and book the site visit with MK1 Clay Woodworth before that date.
- Open Attachment 1, Schedule of Services, on SAM.gov. This review could not read it, so fill in every unit price in US dollars and keep the CLIN numbers unchanged.
- Write a dated, signed cover letter on company letterhead. Include solicitation 70Z08026QPBPL0044, your name, address, UEI and CAGE code, a quote expiry at least 90 days out, acknowledgment of Amendments 0002 and 0003, and the agreement statement the RFQ requires.
- Add up to three past performance references from the last three years, a graphical planning document with the schedule, critical path float and schedule risks, and the name and resume of your MTU technical representative.
- Email the complete package to the Contracting Officer and the Contract Specialist before 11:00 AM on Tuesday, December 8, 2026 (-05:00). Their email addresses are not stated in the text reviewed.
Attached files
From SAM.gov. Download links open the original files.
- Attachment 2_Specification.pdfThe technical specification for the engine overhaul and its inspection forms; you must read it and price to it. Read.
- Attachment 1_Schedule of Services Sturgeon.xls Could not be read.
- 70Z08026QPBPL00440003_US.pdfAmendment 0003, which moves the quote deadline to 11:00 AM and changes the question and site visit dates; you must read it and acknowledge it in your cover letter. Read.
- 70Z08026QPBPL0044_0_US USCGC STURGEON SOLICITATION FOR DOCKSIDE REPAIRS.pdfThe solicitation with quote instructions, clauses and evaluation rules; you must read it and include the cover letter, price schedule and technical plan it requires. Read.
- 70Z08026QPBPL00440002_US.pdfAmendment 0002, which moves the performance period to 5 April to 5 May 2027; you must read it and acknowledge it in your cover letter. Read.
- Attachment 3 - SOW Addendum.pdfSpecial instructions on insurance, change requests, the work schedule and vessel access; you must read it, price to it, and prove your insurance. Read.
Not stated in what we read
- Estimated value or total price of the job: not stated in the text reviewed, and the price schedule could not be read.
- Email addresses for the Contracting Officer and Contract Specialist, and the Contract Specialist's phone number: not stated in the text reviewed.
- Whether the Government will supply the charge air cooler, injectors, cylinder liners and pistons, which the specification marks as may provide and as Tbd quantities.
- Whether a fire plan must be sent with your bid: the specification says so, but the RFQ's list of bid items does not name it.
- Whether the engine pre-check that requires the cutter to get underway applies to this dockside job, and who provides that.
- Late-performance penalties, liquidated damages and payment terms: not stated in the text reviewed.
Notice text
This is a combined synopsis/solicitation for commercial items prepared in accordance with Federal Acquisition Regulation (FAR) Class Deviation 25-21, Rev 1 subpart 12 as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotations are being requested, and a written solicitation will not be issued. Solicitation number 70Z08026QPBPL0044 is issued as a Request for Quotations (RFQ). This solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular FAC 2026-01 effective 13 March 2026, HSAM 2026-03 effective 25 February 2026 and CGAP 2026-01 effective 25 March 202 6; Homeland Security Acquisition Manual (HSAM) 2026-02 effective 28 November 2025; Coast Guard Acquisition Procedures (CGAP) 2025-02 effective 20 June 2025.
As published on SAM.gov.
Contacts
- Michael Farris, Michael.R.Farris@uscg.mil, 7574417032
- Eddrian Logan, eddrian.b.logan@uscg.mil, 2068153591
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at U.S. Coast Guard for the same kind of work (NAICS 336611, service code J998) in Maine that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
| Contract | Obligated | Ends | State |
|---|---|---|---|
| USCGC Bridle Drydock RepairsRockland Marine Corp · 70Z08526FIBCT0048 | $473,485 | Jul 10, 2026ended | ME |
| USCGC Shackle Drydock RepairsJ. Goodison Company · 70Z08525FIBCT0115 | $606,085 | Dec 30, 2025ended | ME |
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 20, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 8, 11:00 AM ET13 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 336611, ship building and repairing, soonest deadline first.
- US Coast GuardAnchor windlass repair on USCGC Neah Bay, Cleveland, OH
- Department of the NavyPort boat davit OEM service at Sasebo, Japan
- Department of the NavyShip repair on USNS City of Bismarck, Busan, South Korea
- Department of the NavyShip repairs on USS Lewis B. Puller in Malaga, Spain
- Department of the ArmyArmy Watercraft Systems Roundtable
- Department of the NavyWatch supervisor chair parts for the Navy
- Department of the NavyPearl Harbor Naval Shipyard 2027 Technology Showcase
- Department of the NavyDive boat repair and preservation, Puget Sound, WA
Free · at most one email a morning
Get new notices from US Coast Guard by email
Each morning we'll send the new solicitations and sources-sought notices from US Coast Guard, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy