Garage drywall demolition at Udall Building, DC

Interior wants a small business to demolish drywall bulkheads (about 1,500 and 6,000 linear feet) in two garage ramps at the Stewart Lee Udall Building in Washington, DC, then patch, paint and clean up.

Official title: Z--Garage Drywall Demolition at Udall Building

Due Dec 2, 12:00 PM ET · Small business

What they're buying

It is a firm fixed price job with a 90-day base period, and quotes are due Wednesday, December 2, 2026.

Top catches

Due date moved to December 2
“Quotes are due December 2nd, 2026, at 12:00 PM Eastern Standard Time (EST).” Sol_140D0427Q0949_Amd_0001.pdf

Amendment 0001 moved the deadline from November 19 at 2:00 PM. The original cover form still shows the old date, so plan for Wednesday, December 2 at 12:00 PM EST.

Walk-through is required, visit is Nov 19
“The Prime Contractor must attend an onsite walk-through of the space to ensure they understand the scope of work and existing conditions.” Sol_140D0427Q0949.pdf, page 13

The prime contractor must attend an onsite walk-through, and the only visit still open is Thursday, November 19 at 12:00 noon ET. Email both contacts first with company, attendee names and phone numbers, and bring a valid REAL ID.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 18, 2026 from the notice and 3 of 3 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Ramp A/B garage: support about 20 junction boxes and 100 linear feet of conduit, then demolish about 1,500 linear feet of drywall bulkheads.
  • Ramp C/D/G garage: support about 80 junction boxes and 400 linear feet of conduit, then demolish about 6,000 linear feet of drywall bulkheads.
  • Patch ceiling holes and paint to match. Scrape and repaint about 250 linear feet of piping (A/B) and 1,000 (C/D/G). Fire sprinkler piping is excluded. Patch damaged insulation on 50 and 200 linear feet.
  • Work only outside 6 AM to 8 PM, Monday to Friday. Haul debris off site daily; it becomes your property once removed.
  • Vacuum with HEPA-filter equipment and wet scrub the garage floor. Ramp A/B is done once at the end of work; Ramp C/D/G is done every workday.
  • Pay Davis-Bacon construction wage rates under wage determination DC20260002 Modification 3, and provide a quality control plan and a management plan.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Due date moved to December 2. Amendment 0001 moved the deadline from November 19 at 2:00 PM. The original cover form still shows the old date, so plan for Wednesday, December 2 at 12:00 PM EST.
  • Walk-through is required, visit is Nov 19. The prime contractor must attend an onsite walk-through, and the only visit still open is Thursday, November 19 at 12:00 noon ET. Email both contacts first with company, attendee names and phone numbers, and bring a valid REAL ID.
  • Acknowledge both amendments. You must acknowledge Amendments 0001 and 0002 with your offer. Missing acknowledgment can cause your offer to be rejected.“FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.” Sol_140D0427Q0949_Amd_0001.pdf, page 1
  • Lowest price wins if technically acceptable. Price decides the award once your technical quote is acceptable. Keep the technical quote within five pages, because pages past the limit are not read.“The Government intends to evaluate all timely quotes received from eligible vendors on a lowest price technically acceptable (LPTA) basis.” Notice text
  • Prices locked, increases are yours. You must lock labor and component prices when you accept the contract. Later price increases are your cost, so price in escorts, PPE and disposal now.“The contractor is expected to secure pricing for all associated labor and components at time of contract acceptance.” Sol_140D0427Q0949.pdf, page 13
  • Completion date conflicts. The Statement of Work counts 90 days from notice to proceed, but Section F counts three months from award. Ask the contracting officer which one applies before you set your crew schedule.“Delivery Date: All construction work, including cleanup, shall be completed three months after contract award.” Sol_140D0427Q0949.pdf, page 16

Key terms

Who can bidSmall businesses only (total small business set-aside)NAICS 238910, size standard $19 million. Confirm your size before you bid.Notice text
Contract period90 days from notice to proceed (base period)Section F instead says all work, including cleanup, is due three months after award. See catches.Sol_140D0427Q0949.pdf, page 6
How they chooseLowest price technically acceptable (LPTA), firm fixed pricePrice decides the award once your technical quote is acceptable. The government plans no discussions.Notice text
How to submitEmail your quote to the contracting officer and contract specialistQuote must be on SF 1442. Emails: nicholas_lewicki@ibc.doi.gov and halazzawi@ibc.doi.gov.Notice text
Questions dueTuesday, November 10, 2026, 12:00 p.m. EST (passed)Questions are closed. Late questions may not be answered.Notice text
Contract typeFirm fixed priceYou quote one total price for the work.Notice text
Site visitThursday, November 19, 2026, 12:00 noon ET, C Street entranceEmail both contacts before attending. The November 6 and November 9 visits have already passed.Notice text

How to respond

  1. Before Thursday, November 19 at 12:00 noon ET, email nicholas_lewicki@ibc.doi.gov and halazzawi@ibc.doi.gov with your company, attendee names and phone numbers. Then attend at the C Street entrance with a valid REAL ID.
  2. Email your quote on SF 1442 to Contracting Officer Nicholas Lewicki and contract specialist Haider Al Azzawi, no later than Wednesday, December 2, 2026 at 12:00 PM EST. File size limits and subject line rules: Not stated.
  3. Keep the technical quote to five pages, including the tentative schedule. Attach a draft Quality Control Plan and draft Contractor Management Plan, which are not counted in the five pages.
  4. Give one total price, not line-by-line prices. List Amendments 0001 and 0002 with their dates in item 19 of SF 1442.

Attached files

  • Sol_140D0427Q0949.pdfThe base solicitation with the work statement, clauses and instructions. You must fill in the SF 1442 offer form and sign it. Pages 23 were not provided to us, so you must read that page yourself. Read in part (pages 1–22 and 24–31 of 31).
  • Sol_140D0427Q0949_Amd_0001.pdfAmendment 0001 moves the due date to December 2, 2026 at 12:00 PM. You must read it and acknowledge it on your offer. Read.
  • Sol_140D0427Q0949_Amd_0002.pdfAmendment 0002 adds the Thursday, November 19 noon site visit and its email rule. You must read it and acknowledge it on your offer. Read.

Not stated in what we read

  • Estimated contract value: Not stated. The price lines are blank.
  • Questions and answers: the government said it would post them, but no such amendment is in the file list.
  • Primary COR: listed as TBD, so the name is not stated.
  • Bid guarantee amount: clause 52.228-1 leaves the percentage and dollar amount blank.
  • Performance and payment bonds: the required box on SF 1442 is unclear in our copy, though clause 52.228-15 is listed.
  • Davis-Bacon wage rates: the rates are not in the notice. Download wage determination DC20260002 Modification 3 from SAM.gov.

Notice text

The purpose of amendment two is to schedule an additional site visit on Thursday, November 19th at 12:00 Noon ET at the Stewart Lee Udall Building, 1849 C Street NW, Washington, DC 20240, entering through the C Street entrance and waiting at security checkpoint for office representative to pick you up. Attendees must email nicholas_lewicki@ibc.doi.gov and halazzawi@ibc.doi.gov prior to attending to confirm attendance with company name, attendee name, and phone number. All visitors must have a valid REAL ID to enter the building. __________________________________________________________________________ Amendment One is posted to extend the due date to December 2nd, 2026 at 12:00PM. The government will post an amendment with the questions and answers received shortly. ______________________________________________________________________ (i) This Request for Quote (RFQ) for construction work located at the Stewart Lee Udall Building, HQ for the Department of the Interior, 1849 C Street, NW, Washington DC 20240. (ii) This requirement is a total small business set-aside under North American Industry Classification System (NAICS) Code 238910 Site Preparation Contractors with a business size standard of $19 million. Federal Supply Code (FSC) Z2AA Repair or Alteration of Office Buildings. This solicitation is issued under Revolutionary FAR Overhaul (RFO) Part 12, Acquisition of Commercial Products and Commercial Services. (iii) This is a combined synopsis/solicitation. This announcement constitutes the only solicitation; quotes are being requested and a separate written solicitation will not be issued. The Government will award a firm fixed price contract from this solicitation to the responsible vendor whose quote, conforming to the solicitation, will be most advantageous to the Government, price and other factors considered. The Government intends to evaluate all timely quotes received from eligible vendors on a lowest price technically acceptable (LPTA) basis. The Government intends to evaluate quotations and award a contract without discussions with quoters. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. Point of Contact: The Contracting Officer shall serve as the focal point for inquiries from actual or prospective offerors. Address any questions or concerns to Contracting Officer, Nicholas Lesicki; nicholas_lewicki@ibc.doi.gov and contract specialist Haider Al Azzawi; halazzawi@ibc.doi.gov. All inquiries must be written, no phone inquiries will be answered. Questions are due by 12:00 p.m. EST on November 10, 2026. Late questions may not be answered. Quotes are due November 19, 2026, at 2:00 PM Eastern Standard Time (EST). Quotes shall be submitted to Contracting Officer, Nicholas Lewicki; nicholas_lewicki@ibc.doi.gov and contract specialist Haider Al Azzawi; halazzawi@ibc.doi.gov. A site-visit is scheduled for interested vendors on Friday November 6, 2026 at 11:00AM and Monday, November 9, 2026 at 2:00PM. Vendors attending the site-visit must send an email to nicholas_lewicki@ibc.doi.gov and halazzawi@ibc.doi.gov indicating their business, name of person(s), phone number and email address of the representative(s) attending the site-visit. All visitors must have a valid REAL ID to enter the building. The address for the site visit is 1849 C Street NW, Washington, DC, 20240, using the C Street entrance. Please wait at the security desk for a representative to get you.

As published on SAM.gov. Attachments are listed there; FedLook does not read them yet.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 18, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Departmental Offices by email

Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy