Paint and laminate floors at Quarters 4, Warm Springs, OR
Interior painting and waterproof laminate flooring at Quarters 4 in the Warm Springs National Fish Hatchery, Oregon, bought as a firm-fixed-price lump sum from small businesses only, with separately priced options.
Official title: Z--OR WARM SPRINGS QTRS 4 PAINT/FLOORING
- Deadline
- Dec 1, 5:00 PM PT
- 6 days left
- Who can bid
- Small businesses
- Size standard for NAICS 236118: $45 million in average annual receipts · Who qualifies
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- Not stated
- Buyer: FWS Contracting Activity
What they're buying
Work is expected from January 19 to February 19, 2027, and quotes are due December 1, 2026.
Top catches
“November 24, 2026, at 5:00 p.m. PST” B09_Amd1_RFQ140FF027Q0038_QA_3pp_0001.pdf, page 1
Older notices show November 24, 2026 at 5:00 p.m. PST. Amendment 0002 sets December 1, 2026, 5:00 PM PT, so plan to submit by that time.
“Wage Determination OR20260009 does not include classifications appropriate for the skilled painting and soft-floor-laying work required by this solicitation.” B09_Amd1_RFQ140FF027Q0038_QA_3pp_0001.pdf, page 2
The wage determination has no painter or flooring rate. The Government will process new rates only after award, so price all labor yourself and expect a conformance step.
Read by AI (Claude Haiku) on Nov 20, 2026 from the notice and 12 of 12 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Paint all walls, ceilings, doors, trim, closets, hallways, stairwell, bathrooms, basement and cold-air-return covers. Skip the garage, cabinets and stair handrails.
- Prep and prime, then eggshell on walls and ceilings and semi-gloss on doors and trim. Apply as many coats as needed for a uniform finish.
- Remove carpet, pad and tack strips. Install waterproof laminate, or an approved luxury vinyl plank, in the living room, dining room, hallway, hall closets, entryway, both stair runs and the downstairs landing.
- Add stair nosing, transitions and trim pieces. Stair treads and risers are not replaced.
- Price these options: replace baseboards and trim (0003), two interior doors (0004), bedroom flooring (0005), kitchen flooring (0006) and bathroom flooring (0007).
- Remove debris daily and do final cleanup. Give a one-year workmanship warranty from Government acceptance.
Who did it before
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Deadline moved to December 1. Older notices show November 24, 2026 at 5:00 p.m. PST. Amendment 0002 sets December 1, 2026, 5:00 PM PT, so plan to submit by that time.
- Painter and floor-layer wages missing. The wage determination has no painter or flooring rate. The Government will process new rates only after award, so price all labor yourself and expect a conformance step.
- Site visit has passed, measure yourself. The November 10 visit is over and no more visits are planned. There are no floor plans or quantity takeoffs, so measure the house and price quantities yourself.“No additional site visits are planned.” Amd2_A04_SOW_WarmSpringsPaint-Flooring_261119_Final_Redline_Redacted_7pp_0002.pdf, page 5
- Oregon CCB license required. You, or a subcontractor you name, must hold a current Oregon Construction Contractors Board license. Name that subcontractor in the bid schedule and attach a copy of the license.“A current and valid Oregon Construction Contractors Board (CCB) license may be provided by the prime quoter or by the proposed subcontractor(s) that will perform the regulated construction work.” B09_Amd1_RFQ140FF027Q0038_QA_3pp_0001.pdf, page 2
- Completion clock may not fit window. Work must start within 30 days and finish within 60 days after the notice to proceed, but the on-site window is about one month. If award comes late, the dates shift, so confirm your crew schedule.“within 60 calendar days after receipt of the Notice to Proceed.” B09_Amd1_RFQ140FF027Q0038_QA_3pp_0001.pdf, page 1
- Pre-1978 house, hazard stop-work. Quarters 4 has no lead inspection and abatement is not in scope. If you find suspected hazardous material, you must stop work in that area, which likely causes delay and a price change.“Quarters #4 was constructed in 1978.” Amd2_A04_SOW_WarmSpringsPaint-Flooring_261119_Final_Redline_Redacted_7pp_0002.pdf, page 6
Key terms
| Who can bid | Small businesses only (total small business set-aside)Size standard for NAICS 236118 is $45 million. An Oregon CCB license is required.SAM.gov record |
|---|---|
| Contract period | January 19, 2027 to February 19, 2027 (anticipated)Work must start within 30 days and finish within 60 days after the notice to proceed.Amd2_A04_SOW_WarmSpringsPaint-Flooring_261119_Final_Redline_Redacted_7pp_0002.pdf, page 5 |
| How they choose | Best value: price, technical, and past experienceThe Government may award to a quote that is not the lowest price.140FF027Q0038_TermsConditions_B-M_31pp.pdf, page 30 |
| How to submit | Email to nicole_johnson@ios.doi.govEmail only. Attach files in PDF or Microsoft Office format.140FF027Q0038_TermsConditions_B-M_31pp.pdf, page 25 |
| Questions due | Closed: Friday, 11/13 at 5 pm PSTQuestions are closed. Answers are in Amendments 0001 and 0002.140FF027Q0038_TermsConditions_B-M_31pp.pdf, page 25 |
| Estimated value | Less than $25,000 (magnitude only)The Government says this is not a budget or a firm maximum.140FF027Q0038_TermsConditions_B-M_31pp.pdf, page 2 |
| Contract type | Firm-fixed-price lump sum, with separately priced optionsBase items 0001 and 0002, plus option items 0003 to 0007.Amd2__Attch4_BidSchedule_Updated_Options_2pp_0002.docx |
| Site visit | Passed: November 10, 2026, 12:00 p.m. PSTNo more site visits are planned. You must measure the house yourself.Amd2_A04_SOW_WarmSpringsPaint-Flooring_261119_Final_Redline_Redacted_7pp_0002.pdf, page 5 |
How to respond
- Fill in the Amendment 0002 bid schedule (Attachment 4) with a unit price and total for items 0001 to 0007, and complete SF 1442 blocks 14 to 20C with a signature by an authorized official.
- Attach proof of a current Oregon CCB license for you or a named subcontractor, product brochures, manufacturer warranty information, a proposed schedule, and up to three similar projects from the last three years.
- Acknowledge Amendments 0001 and 0002 by signing their SF 30 forms and including them with your quote.
- Email the complete quote to nicole_johnson@ios.doi.gov by December 1, 2026, 5:00 PM PT. File size limit: Not stated.
- Enter at least 60 calendar days in SF 1442 item 17. If you cannot invoice through the Invoice Processing Platform, send a written waiver request with your quote.
Attached files
From SAM.gov. Download links open the original files.
- Sol_140FF027Q0038_Amd_0001.pdfAmendment 0001 cover form (SF 30). Sign and return it with your quote to acknowledge the amendment. Read.
- B09_Amd1_RFQ140FF027Q0038_QA_3pp_0001.pdfAmendment 0001 changes and questions on the CCB license, wage rates, bonds and site access. Read it and acknowledge it with your quote. Read.
- 140FF027Q0038_TermsConditions_B-M_31pp.pdfMain solicitation terms, sections A to M, covering clauses, submission rules and evaluation. Read it in full and complete the representations through SAM. Read.
- Sol_140FF027Q0038_Amd_0002.pdfAmendment 0002 cover form (SF 30) that extends the due date. Sign and return it with your quote to acknowledge the amendment. Read.
- Attch2_Photos_8pp.docxPhotos of current room conditions. Read it to see the rooms before you measure, and do not fill it in. Read.
- Attch1_A04_SOW_WarmSpringsPaint-Flooring_261103_5pp_Redacted.pdfOriginal statement of work, replaced by the Amendment 0002 version. Read it for background only. Read.
- Amd2__Attch4_BidSchedule_Updated_Options_2pp_0002.docxCurrent bid schedule with base and option items. You must fill in unit prices and totals for each item. Read.
- Amd2_QA-2_140FF027Q0038-261119-Final_9pp_0002.pdfAmendment 0002 questions and government answers on scope, bonds and payment. Read it in full because it sets many rules. Read.
- Attch4_BidSchedule_1p.docxEarlier two-item bid schedule, replaced by the updated schedule. Do not use it to price. Read.
- Sol_140FF027Q0038.pdfOriginal SF 1442 solicitation and offer form. You must complete blocks 14 to 20C and sign it. Read.
- Attch3_DBA_OR-20260009_5pp.pdfDavis-Bacon wage determination. Our text copy is garbled, so we could not reliably read the rates. You must read the original and check the listed classifications. Read.
- Amd2_A04_SOW_WarmSpringsPaint-Flooring_261119_Final_Redline_Redacted_7pp_0002.pdfCurrent statement of work with red-text changes. Read it in full and price to it. Read.
Not stated in what we read
- Estimated value: the only figure is a magnitude of less than $25,000, which the Government says is not a budget or a firm maximum.
- Wage rates for painters and flooring installers: the Government will process these after award, so the rates are not stated.
- Insurance types and limits: the notice does not set them, but a certificate may be requested before on-site work.
- File size limit for the emailed quote: Not stated.
- Which option items, if any, will be awarded: decided at award.
- Exact start date: depends on when the notice to proceed is issued.
Notice text
The purpose of this Amendment 0002 is to provide Government responses to questions received, revise the Statement of Work and Bid Schedule based on those responses, and extend the quotation due date to December 1, 2026, at 5:00 PM PT. See attachments. Except as changed by this amendment, all other terms and conditions remain unchanged.
As published on SAM.gov.
Contacts
- Johnson, Nicole, nicole_johnson@ios.doi.gov, 000-000-0000
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 20, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 1, 5:00 PM PT6 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 236118, residential remodelers, soonest deadline first.
Free · at most one email a morning
Get new notices from Departmental Offices by email
Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy