Replace two electrical substations at Philadelphia VA, PA
The VA wants two electrical substations at the Corporal Michael J. Crescenz VA Medical Center replaced with new 480/277V units, each with a 1500 kVA transformer, plus a temporary substation to keep power on during the work.
Official title: Z1DA--642-22-104 | Upgrade Substation Building 2 Phase 1 for Philadelphia VAMC
- Deadline
- Dec 7, 4:00 PM ET
- 12 days left
- Who can bid
- SDVOSB firms
- Service-disabled veteran-owned small businesses certified by SBA only · Who qualifies
- Last time
- $191K
- Likely Aeonrg LLC
- Place
- PA
- Buyer: 244-Network Contract Office 4 (36C244)
What they're buying
The contract runs 1000 calendar days from notice to proceed and is open only to service-disabled veteran-owned small businesses.
Top catches
“1.Extend the proposal due date from 11/20/2026 at 4:00PM EST to 12/7/2026 at 4:00PM EST.” 36C24426R0088 0004.pdf, page 1
The notice text still shows November 20, which has passed. Amendment 0004 sets the due date to Monday, December 7, 2026 at 4:00 pm EST, so plan around the amended date and check SAM.gov before you send.
“Failure to return a signed copy of 852.219-75 will result in proposal not being considered for award.” 36C24426R0088 0003.pdf, page 2
Without a signed copy of clause 852.219-75, the VA will not consider your proposal for award. Sign it and include it with your email, after reading its limits on subcontracting.
Read by AI (Claude Haiku) on Nov 21, 2026 from the notice and 13 of 42 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Replace Electrical Substations 1 and 2 with new 480/277V substations, each with a 1500 kVA transformer.
- Install a temporary 480/277V substation with a 1500 kVA transformer during demolition and construction, then leave it in place as a spare.
- Demolish and remove the existing substation equipment, and deliver the existing breakers from Substations 1 and 2 to the VA COR or Electrical Supervisor.
- Build a new electrical room, and complete an arc flash hazard analysis, load monitoring, and site assessment.
- Install and maintain ICRA and safety barriers, a permanent manometer with real-time display and data storage, and fire and smoke barrier penetration permits.
- Submit a baseline CPM schedule, weekly and biweekly schedule updates, certified payrolls, material lists, safety data sheets, and weekly waste reports.
Who did it before
$191K
on the contract that likely holds this work now: Aeonrg LLC. It ended Nov 24, 2026.
Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.
What to watch for
- Deadline moved to December 7. The notice text still shows November 20, which has passed. Amendment 0004 sets the due date to Monday, December 7, 2026 at 4:00 pm EST, so plan around the amended date and check SAM.gov before you send.
- Signed 852.219-75 form required. Without a signed copy of clause 852.219-75, the VA will not consider your proposal for award. Sign it and include it with your email, after reading its limits on subcontracting.
- Email-only delivery, no backup. Your proposal must reach kevin.rodgers2@va.gov by the deadline. The Government is not responsible for proposals lost to file size or system errors, so send early and keep a copy of what you sent.“The Government is not responsible for proposals that are transmitted to the Contracting Officer and not received due to size of the documents or system errors.” 36C24426R0088 0003.pdf, page 2
- Certified payroll timing conflicts. The statement of work gives two different payroll deadlines. Work cannot resume until payroll is submitted, so ask the COR which deadline applies before you schedule crews.“Submittal of all Certified payrolls must occur at the end of each work week.” Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx
- Contract length changed to 1000 days. The original solicitation showed 365 days. Amendment 0003 changed the term to 1000 calendar days, so price labor, equipment, and overhead over the longer period.“For the entire project is 1000 days from NTP issuance.” Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx
- Outages only in night and weekend hours. Power shutdowns must run 8:00 p.m. to 6:00 a.m. on Sunday through Friday nights or on weekends, and both power sources cannot be off for one building. Price after-hours crews and allow the 7-day and 15-day notice periods for utility interruptions.“For this project, off-hours are defined as 8:00 p.m. through 6:00 a.m. Sunday night through Friday night or weekends.” Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docx
Key terms
| Who can bid | Service-disabled veteran-owned small businesses onlyCheck the size standard for NAICS 236220 in FAR 52.204-8, which was not provided.SAM.gov record |
|---|---|
| Contract period | 1000 calendar days from notice to proceedAmendment 0003 changed this from 365 calendar days. The original solicitation still shows 365.36C24426R0088 0003.pdf, page 1 |
| How they choose | Best value trade-offEvaluation factors are referenced but were not in the text we received.36C24426R0088_1.docx |
| How to submit | Email to Kevin Rodgers, kevin.rodgers2@va.govEmail only. The Government is not responsible for proposals not received because of file size or system errors.36C24426R0088 0003.pdf, page 2 |
| Questions due | Closed. No more RFIs accepted after Amendment 0004.Contractor RFIs were due 7/29/2026 at 4:00pm EST.36C24426R0088 0004.pdf, page 1 |
| Estimated value | $5,000,000 to $10,000,000The notice gives a range for the project size, not a fixed contract amount.36C24426R0088_1.docx |
| Contract type | Construction project (SF 1442 solicitation)The contract type clause (52.216-1) is listed in the table of contents, but its text was not provided.SAM.gov record |
| Site visit | Held 7/22/2026. Later visits need an appointment.Visits are by appointment with the Medical Center's Engineering Officer (COR). Arrange one before you price the job.Substations Upgrade Building 2-Phase 1_Bid Documents_Specification_10-21-24.pdf, page 7 |
How to respond
- Read Amendment 0004 and sign its SF 30 form, which says the contractor is required to sign and return it.
- Complete the offer side of SF 1442, including price and amendment acknowledgments, and sign it. Page limits and required price format: Not stated.
- Attach a signed copy of clause 852.219-75 to your email.
- Email the complete proposal to Kevin Rodgers at kevin.rodgers2@va.gov before Monday, December 7, 2026 at 4:00 pm EST, and send early.
- Keep your offer valid for at least 180 calendar days after the due date. Offers with less are rejected.
Attached files
From SAM.gov. Download links open the original files.
- 2024-12-03_HAZARDOUS AND UNIVERSAL WASTE POLICY.pdf Not read: over our length limit.
- 2024-12-03_HAZARDOUS MATERIALS AND WASTE MANAGEMENT PLAN.pdf Not read: over our length limit.
- Substations Upgrade Building 2-Phase 1_Bid Documents_Specification_10-21-24.pdfThe bid specifications covering general requirements and site visit rules. Only pages 1 to 13 and 591 to 596 were provided, so read only. Read in part (pages 1–13 and 591–596 of 597).
- ALL-31-SINGLE-LINES-ONE-FILE-012325.pdf Not read: over our length limit.
- FMS 138-54 Hot Work Policy.doc Not read: over our length limit.
- 36C24426R0088 0002.docxAmendment 0002 said RFI answers and a new date would come later. It is superseded, so read only. Read.
- Confined Space Entry Program.pdf Not read: over our length limit.
- Attachment 3 General Decision Number PA20260003 10012026.docx Not read: over our length limit.
- Substations Upgrade Building 2-Phase 1 Combined Drawings.pdfDrawings for the substations, electrical room, and fire protection. Only some sheets were provided, so read only. Read in part (pages 7–14 and 22–25 of 25).
- Electrical Safety Program.pdf Not read: over our length limit.
- 7714_D_2017-04-06 ASBESTOS MANAGEMENT PROGRAM.pdf Not read: over our length limit.
- VHA Dir 7714 Asbestos Management Program.pdf Not read: over our length limit.
- Fire and Smoke Barrier Pentration Permit.pdf Scanned image, not read.
- Safety Coordination Meeting Safety Policies for SOW Project 642-22-104.pdfExcerpts from a green procurement policy and a construction safety directive. Read only. Read in part (pages 1–9 and 190–194 of 194).
- B6-SUB-PRIMARY-NORMAL-324-371-DWG-FINAL-070623.pdf Not read: over our length limit.
- Inspection Final RAC Blank Master.docx Not read: over our length limit.
- SAFE PRACTICES FOR WORKING WITH LIVE ELECTRICAL POWER.pdf Not read: over our length limit.
- 36C24426R0088 0001.docxAmendment 0001 extended the due date to 8/31/2026 and added the site visit roster. It is superseded, so read only. Read.
- 36C24426R0088 0004.pdfThe latest amendment moves the due date to December 7, 2026 and adds RFI answers and policy attachments. You must sign and return its SF 30 form. Read.
- Attachment 2 P09 Final SOW Rev1 Building 2 Substation Phase 1 642-22-104 10202026.docxThe statement of work covering schedules, outages, safety, and submittals. Only the first part was provided; read the rest on SAM.gov. You do not sign it. Read in part.
- RFI 2 Upgrade Substation 36C24426R0088.docx Not read: over our length limit.
- B02-SUB-3.pdf Not read: over our length limit.
- FMS SOP 138-44 Fire and Smoke Barrier Penetration Policy.pdf Not read: over our length limit.
- B02-SUB-2.pdf Not read: over our length limit.
- B6-SITE-POWER-WITH-MANHOLES-DWG-FINAL-070623.pdf Not read: over our length limit.
- 2024-12-03_Green Procedure Program.pdf Not read: over our length limit.
- FIRE SYSTEM permit 2021 blank.pdfA blank fire system permit form. Its text was garbled, so check the original to see what you must fill in. Read.
- MANHOLES 19529-02 VA Hospital of Philedelphia 11.17.22.pdf Not read: over our length limit.
- VHA ICRA-1.2 Oct 1 2024.pdf Not read: over our length limit.
- B02-SUB-1.pdf Not read: over our length limit.
- Blank Above Ceiling Permit.pdfA blank fire and smoke barrier penetration permit. The contractor must complete one before cutting through fire-rated barriers. Read.
- Asbestos Control Regulation.pdf Not read: over our length limit.
- 36C24426R0088 0003.pdfAmendment 0003 changed the term to 1000 days and added the revised SOW and RFI answers. You must sign and return its SF 30 form. Read.
- Building 2_LS_SB_G_B FOR REFERENCE ONLY.pdf Not read: over our length limit.
- INFECTION PREVENTION AND CONTROL POLICY BEHAVIORAL HEALTH SERVICES.pdf Not read: over our length limit.
- Fire Plan.pdf Not read: over our length limit.
- S04 Pre-Bid Sign-In Sheet 36C24426R0088 - 642-22-104 - Upgrade Substation.pdfA pre-bid sign-in sheet whose text was garbled, so check the original. Read only. Read.
- 36C24426R0088_1.docxThe solicitation cover and table of contents, with the clause list. Only the start was provided; you must complete and sign the offer side yourself. Read in part.
- Attachment 1 RFI 1 Upgrade Substation 642-22-104.docx Not read: over our length limit.
- FMS SOP 138-54 Hot Work Policy.pdf Not read: over our length limit.
- Safety and Health During Construction.pdf Not read: over our length limit.
- B02-SUB-4.pdfA single-line riser drawing for a different substation under project 642-23-113. It is reference only. Read.
Not stated in what we read
- We could not review Attachment 3, General Decision PA20260003, which sets wage rates. You must read it before you price labor.
- Evaluation factors and their weights. The solicitation refers to them, but the text was not provided.
- Bid guarantee and bond amounts. The form may require performance and payment bonds within 30 days after award, but the check mark is hard to read.
- Insurance minimums. Proof of liability insurance is due within 10 days after award, but no amounts are stated.
- Background check, badge timing, and cost. The notice says checks may be required before work starts.
- Full drawings and specifications. Many pages were not provided, so read the complete set on SAM.gov.
Notice text
642-22-104, 36C24426R0088, Upgrade Substation Building 2, Phase 1, PHL CMCVAMC Proposal Due Date: 11/20/2026 at 4:00pm EST. Email proposals to Kevin Rodgers at kevin.rodgers2@va.gov. Corporal Michael J. Crescenz Medical Center (CMC VAMC) requires replacement of Electrical Substations 1 and 2 in order to increase electrical capacity to support future facility projects. The existing substations are approximately 29 years old and require replacement to support current and future electrical demands.
This project will replace Electrical Substations 1 and 2 with new 480/277V substations each containing a 1500 kVA transformer. A temporary 480/277V substation with a 1500 kVA transformer shall be installed to maintain electrical service to the facility during demolition and construction activities. Upon completion of construction, the temporary substation shall remain installed as a spare substation for the facility. All work shall be phased to minimize service outages and maintain continuous operation of the medical center.
Defined and issued bid documents (drawings and specifications) will serve as the basis of this construction project.
As published on SAM.gov.
Contacts
- Kevin A Rodgers, Contract Specialist, kevin.rodgers2@va.gov
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at Department of Veterans Affairs for the same kind of work (NAICS 236220, service code Z1DA) in Pennsylvania that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
| Contract | Obligated | Ends | State |
|---|---|---|---|
| Repair and Replace Ug Sanitary | PHL Cmcvamc |Aeonrg LLC · 36C24426N0405 | $190,695 | Nov 24, 2026ended | PA |
| Move Audiology and Pharmacy Construction Project 503-18-104Senate Builders & Construction Managers, Inc. · 36C24422N0050 | $5,524,250 | Nov 30, 2026within a month | PA |
| Bldg One Roof.Serviam Construction LLC · 36C24426N0125 | $2,197,570 | Nov 30, 2026within a month | PA |
| Correct HVAC SPS - LebanonSenate Builders & Construction Managers, Inc. · 36C24425N0488 | $2,019,538 | Nov 18, 2026ended | PA |
| Eo 14398Serviam Construction LLC · 36C24426N0988 | $370,450 | Nov 11, 2026ended | PA |
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 21, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 7, 4:00 PM ET12 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 236220, commercial and institutional building construction, soonest deadline first.
- Department of the Air ForceBase repair and minor construction, Wright-Patterson AFB, OH
- Department of the ArmyMaintenance building at C and D Canal, Chesapeake City, MD
- Department of the NavyLab and test building at Philadelphia Navy Yard, PA
- Forest ServiceNew lookout cab and power at Barillas Peak, NM
- Department of Veterans AffairsParking garage repair and redesign in Reno, Nevada
- Department of the Air ForceEnlisted dormitory construction at Kirtland AFB, NM
- Public Buildings ServiceKitchenette refresh at Weinberger Courthouse, San Diego, CA
- Department of Veterans AffairsFY27 NRM (PROJ 573-24-110) BB - Expand Cardiology Service
Free · at most one email a morning
Get new notices from Department of Veterans Affairs by email
Each morning we'll send the new solicitations and sources-sought notices from Department of Veterans Affairs, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy