Building 51 roof replacement, Jefferson Barracks, MO
VA is seeking an SDVOSB contractor to replace the roof on Building 51 at the St. Louis VA Medical Center, Jefferson Barracks, MO, about 56,000 square feet with a 70-mil TPO system.
Official title: Z2DA--657-27-103JB, FCA Replace Building 51 Roof
- Deadline
- Dec 7, 4:00 PM CT
- 13 days left
- Who can bid
- SDVOSB firms
- Service-disabled veteran-owned small businesses certified by SBA only · Who qualifies
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- St. Louis
- Buyer: 255-Network Contract Office 15 (36C255)
What they're buying
The period of performance is 222 calendar days after notice to proceed, but another line in the notice says 210 days.
Top catches
“the proposal due date will be on or about January 15, 2027” Notice text
The SAM record and attachment give a response due Monday, December 7, 2026 at 4:00 PM Central. The notice text says the proposal is due on or about January 15, 2027. Ask the contracting officer which date controls before you plan your bid.
“The North American Industry Classification Code (NAICS) for this procurement is 235220 Commercial and Institutional Building Construction” Notice text
The SAM record and attachment list 236220, but the notice text gives 235220 for the same procurement. The $45.0 million size standard depends on the code, so confirm the correct code with the contracting officer before you decide to bid.
Read by AI (Claude Haiku) on Nov 24, 2026 from the notice and 1 of 1 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Replace the roof on Building 51, about 56,000 square feet net (preliminary, subject to field verification), with a fully adhered 70-mil TPO membrane
- Remove existing roofing down to the retained concrete topping or metal deck, and repair deterioration within set limits
- Replace four skylights: two about 85 square feet and two about 40 square feet, with structural calculations sealed by a licensed structural engineer
- Correct about 250 square feet of depressed roof, replace two expansion-joint covers about 40 linear feet each, and repair about 150 linear feet of stanchion barrier
- Remove, reinstall and test the lightning-protection system, replace the penthouse roof-access ladder, and install walking pads along about 600 linear feet
- Submittals, a 20-year no-dollar-limit warranty, and as-built drawings in searchable PDF and editable CAD
Who did it before
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Deadline conflicts with notice text. The SAM record and attachment give a response due Monday, December 7, 2026 at 4:00 PM Central. The notice text says the proposal is due on or about January 15, 2027. Ask the contracting officer which date controls before you plan your bid.
- NAICS code does not match. The SAM record and attachment list 236220, but the notice text gives 235220 for the same procurement. The $45.0 million size standard depends on the code, so confirm the correct code with the contracting officer before you decide to bid.
- SDVOSB-only set-aside. Only Service-Disabled Veteran-Owned Small Businesses can bid. Confirm your SAM registration and Veteran Small Business Certification under the NAICS before you invest in a proposal.“prospective contractors must be registered in SAM and in the Veteran Small Business Certification (sba.gov) databases under the applicable NAICS” Notice text
- Two different contract durations. The period of performance says 222 calendar days after notice to proceed, but the duration line says 210 calendar days. Plan your schedule and crew costs against the shorter figure until the solicitation or an amendment settles it.“The duration of the project is estimated to be 210 calendar days from Notice to Proceed.” Notice text
- Hazmat testing falls on you. The notice expects no asbestos or lead. If you find a material you consider suspicious, you must hire an independent third-party VPIH (the notice does not spell this out) to do the related work, so include possible cost and delay in your price.“it will be the responsibility of the contractor to hire an independent 3rd party VPIH to complete the related work if they are to encounter a material that they deem suspicious.” Notice text
- Questions by email only. Phone calls will not be accepted. Send all questions by email to Jennifer.Hill@va.gov using the exact subject line in the notice, and send them early enough to get answers before the deadline.“telephone requests or questions will NOT be accepted” Notice text
Key terms
| Who can bid | Service-Disabled Veteran-Owned Small Businesses only (total set-aside)You must be registered in SAM and in the Veteran Small Business Certification database under the NAICS.Notice text |
|---|---|
| Contract period | 222 calendar days after Notice to ProceedThe notice text also says 210 calendar days from Notice to Proceed. See catches.Notice text |
| How they choose | Highest technically rated with a fair and reasonable priceThe government plans to award without discussions.Notice text |
| How to submit | Instructions come in the solicitation package; questions go by emailSend questions to Jennifer.Hill@va.gov with the required subject line. Phone questions are not accepted.Notice text |
| Estimated value | Between $2,000,000 and $5,000,000This is an estimated cost range, not a contract price.Notice text |
| Contract type | Firm fixed priceNotice text |
| Site visit | Date not yet set; one visit plannedThe notice says the date and time will be given when the solicitation is issued. Attendance is strongly encouraged but the text does not make it mandatory.Notice text |
How to respond
- Check SAM.gov for the solicitation package and any amendments. The notice says the package is expected on or about December 7, 2026.
- Confirm your SDVOSB status and your registrations in SAM and the Veteran Small Business Certification database under the correct NAICS code.
- Email questions to Jennifer.Hill@va.gov with the subject line 'FCA Replace Building 51 Roof, Project Number 657-27-103JB; Solicitation Number: 36C25527R0020'.
- Submit your proposal by the deadline in the solicitation package. The notice gives both December 7, 2026 at 4:00 PM Central and January 15, 2027, and the submission method is not stated.
Attached files
From SAM.gov. Download links open the original files.
- 36C25527R0020_1.docxContracting office cover sheet and project description. It is for reading only; the text provided contains no bid form for you to fill in or sign. Read.
Not stated in what we read
- Which date controls: the December 7, 2026 response date or the January 15, 2027 proposal date
- Whether the contract period is 222 or 210 calendar days from notice to proceed
- Proposal submission method, address and required forms (the solicitation package is not included)
- Date and time of the site visit
- Questions deadline
- Whether any amendments or wage requirements apply
Notice text
Project # 657-27-103JB, FCA Replace Building 51 Roof The Department of Veterans Affairs, Network Contracting Office (NCO) 15, has a requirement to Replace Building 51 Roof, project number 657-27-103JB, located at the U.S Department of Veterans Affairs, Str. Louis VAMC Jefferson Barracks 1 Jefferson Barracks Drive St. Louis, MO 63125 The following narrative is intended to provide an overview of the scope of work for the proposed project. Period of Performance 222 calendar days after Notice to Proceed (NTP) Scope of Work Furnish complete construction services to replace all designated Building 51 roofs, including projections, entrance roofs, and connecting portions.
The preliminary net roof area is approximately 56,000 square feet, subject to field verification. Provide a watertight thermoplastic polyolefin (TPO) roofing system in accordance with the VA-prepared drawings and specifications. Contractor shall submit shop drawings, product data, and installation details for all proposed materials, equipment, and systems to be installed or replaced under this contract for VA review prior to commencing the associated work.
Submittals shall include applicable manufacturer's specifications and required engineering certifications. Schedule, phasing, and occupied operations: Complete construction and closeout within 222 calendar days after the Notice to Proceed issue date. Building 51 remains occupied and operational 24 hours per day, seven days per week. Work hours are from 7:00 a.m. to 4:30 p.m., local time. Submit a contractor-developed phasing plan for the Contracting Officer's Representative (COR) to review before roofing.
Complete both highest penthouse roof platforms first on the original building and the highest roof section first on the addition; either building portion may be started first. Maintain safe access, utilities, and required infection-control and HVAC-intake protection. Provide construction fall protection and keep the building watertight; coordinate service interruptions with the VA. Investigation and Roofing Requirements: Hazardous Materials: While neither Asbestos Containing Material nor Lead is expected to be encountered within the scope of this project, it will be the responsibility of the contractor to hire an independent 3rd party VPIH to complete the related work if they are to encounter a material that they deem suspicious.
Demolition limit: At the original building (Zones 1-7, 13, and 14), remove the existing roofing assembly through the base sheet to the top of the Zonolite lightweight-concrete topping; retain the topping and underlying structural concrete deck. At the addition (Zones 8-12 and 15), remove the existing roofing assembly, including insulation and intervening layers, to the top of the metal roof deck; retain the deck and supporting structure. Clean and inspect retained surfaces, and repair deterioration within specified repair limits.
Report differing construction or deterioration beyond those limits to the COR before proceeding with affected work. New roof and mechanical securement: Install mechanically fastened rigid insulation, adhered cover board, and fully adhered 70-mil TPO roofing membrane with continuous hot-air-welded seams. Contractor shall verify that the proposed fastening system is compatible with Building 51's existing roof construction. Parapets, penetrations, and retained metal: Extend new roofing up parapets to the existing flashing.
Flash and seal, with the correct system specific boots, all roof penetrations with compatible membrane extending at least 8 inches above the finished roof, or higher where required by applicable VA criteria and manufacturer/warranty requirements. Retain metal flashings, flanges, and coping unless scheduled for replacement, and replace roofing beneath retained metal. Specific Replacement and Repairs: Associated roof work: Retain rooftop HVAC units in place and replace roofing beneath elevated units and frames and around curbs.
Replace old or deteriorated wooden rooftop support blocks with load-rated black rubber blocks compatible with the roofing; retain serviceable recently replaced blocks. Replace roof-drain covers/strainers and recondition retained drains with watertight connections. Reflash existing scuppers and provide new scuppers only where detailed; retain gutters and downspouts unless otherwise indicated. Correct approximately 250 square feet of depressed roof on the original building's middle section north of the penthouse to provide positive drainage.
Replace expansion-joint weatherproofing/cover material at two original-building sections, approximately 40 linear feet each. Temporarily remove and reinstall the existing lightning-protection system in its original locations and configuration with new clips securing it; complete specified testing and certification. Repair approximately 150 linear feet of the existing movable stanchion-and-rope warning-line barrier. Replace the penthouse roof-access ladder to meet applicable VA safety requirements and OSHA criteria.
Install 3-foot by 3-foot walking pads with 8-inch clear gaps along approximately 600 linear feet of total walkway route, including gaps. Provide positive drainage to roof drains and scuppers throughout all reroofed areas. Standing water shall not remain more than 48 hours after rainfall ends under conditions conducive to drying. Correct low spots and other drainage deficiencies that prevent compliance before final acceptance. Skylights: Replace four skylights: two approximately 85 square feet each and two approximately 40 square feet each.
Field-verify openings and provide complete watertight installations. Before fabrication, submit contractor shop drawings and supporting structural calculations signed and sealed by a licensed structural engineer responsible for their design/review. Submittals, record drawings, and closeout: Provide required construction submittals and complete specified testing, inspections, and closeout. Submit a clean, coordinated as-built record drawing set in searchable PDF and editable CAD showing actual installed conditions and accepted changes; redline markups alone are not acceptable.
Provide a 20-year no-dollar-limit (NDL) warranty and maintenance information, complete cleanup and restoration, and comply with contract records-management, privacy, and security requirements. The estimated project cost range to complete this work is Between $2,000,000 and $5,000,000. Pursuant to 38 USC 8127(d) and in accordance with Public Law 109-461, the Veterans Benefits, Health Care and Information Technology Act of 2006, this construction project will be solicited as a Total set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB).
The North American Industry Classification Code (NAICS) for this procurement is 235220 Commercial and Institutional Building Construction, with a small business size standard of $45.0 million. Contract Type: Firm Fixed. The duration of the project is estimated to be 210 calendar days from Notice to Proceed. This completion period includes final inspection and cleanup of the premises. Award will be made utilizing Highest technically rated with a fair and reasonable price approach in accordance with Federal Acquisition Regulation Part 15.
Proposal submission instructions will be included in the solicitation package. The government plans to award without discussions. The offeror is responsible to monitor and download any amendments from the Contract Opportunities (https:// sam.gov) website, which may be issued to this solicitation. In accordance with FAR 52.204-7, Required SAM, and in accordance with Veterans Affairs Acquisition Regulation (VAAR) 802.101, prospective contractors must be registered in SAM and in the Veteran Small Business Certification (sba.gov) databases under the applicable NAICS.
Firms may obtain SAM information at http://www.sam.gov and Veteran Small Business Certification (sba.gov) information at https://veterans.certify.sba.gov The solicitation package with project specifications and drawings should be available for download on or about December 7, 2026 and the proposal due date will be on or about January 15, 2027. An organized site visit will be scheduled and specific date and time will be made available at time of solicitation issuance.
Only one site visit will be scheduled and interested offerors are highly encouraged to attend. No hard copies of the solicitation or drawings will be provided; and telephone requests or questions will NOT be accepted. Please email requests or questions to Jennifer.Hill@va.gov and ensure that the subject line reads "FCA Replace Building 51 Roof, Project Number 657-27-103JB; Solicitation Number: 36C25527R0020.
As published on SAM.gov.
Contacts
- Jennifer Hill, Contracting Officer, Jennifer.Hill@va.gov, 913-946-1198
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 24, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 7, 4:00 PM CT13 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 236220, commercial and institutional building construction, soonest deadline first.
- Department of Veterans AffairsHistoric lodge renovation at Fort McPherson, Maxwell, NE
- Department of Veterans AffairsRemodel ENT procedure rooms, Jesse Brown VA, Chicago, IL
- Department of Veterans AffairsFlooring and X-ray electrical work at Bath VA, NY
- Department of the ArmyNotice to Industry - LVN B95 Fire Station Addition
- Department of the ArmyNotice to Industry - LVN B95 Fire Station Addition
- Office of the Assistant Secretary for Administration and ManagementRoof, HVAC and seismic upgrades at Clearfield Job Corps, UT
- Department of the NavySteam plant design-build at NSA Bethesda, MD
- Department of Veterans AffairsReplace flooring and paint in Building 650, Mather, CA
Free · at most one email a morning
Get new notices from Department of Veterans Affairs by email
Each morning we'll send the new solicitations and sources-sought notices from Department of Veterans Affairs, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy