1. Opportunities
  2. Department of Defense
  3. Department of the Army
  4. ASG-JOCS1119

Fuel tank restoration and upkeep at JTC, Jordan

The Army wants a contractor to restore, test and maintain ASG-J-owned 6,000-gallon SCAT fuel tanks at the fuel point in Jordan, for a 12-month base period plus four 12-month options.

Official title: Initial Restoration, Testing, and Continuous Sustainment of ASG-J Owned 6K SCAT Tanks

Deadline
Dec 3, 3:00 PM UTC+03:00
8 days left
Who can respond
Any business
Market research, not a bid
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Zarqa, JOR
Buyer: W6QK ACC-Rsa

What they're buying

This is a market research notice, not a solicitation, and responses are due 3 December 2026.

Top catches

Not a solicitation yet
“This notice is NOT a solicitation and does NOT constitute a commitment by the Government to issue a solicitation or award a contract.” RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 1

You can only respond to the RFI for now. Nothing in this notice is a bid, and no solicitation has been issued.

Deadline time conflicts
“03 December 2026, 1700, local Jordan time (NLT)” RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 1

The SAM record says 15:00 at +03:00, but the RFI says 1700 local Jordan time. Submit by 15:00 +03:00 and ask the contracting specialist to confirm the time.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 20, 2026 from the notice and 2 of 2 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Initial restoration and functional testing of the covered 6,000-gallon SCAT tanks, RDS units and generators within 30 calendar days of NTP.
  • Monthly, quarterly and annual preventive maintenance on tanks, retail dispensing skids and generators.
  • Dedicated spares container with a contingency RDS and generator set, deployable within 48 hours of notification.
  • Initial Condition and Restoration Report within 5 business days after Task 1 is complete.
  • Monthly maintenance report within 5 business days after each visit; NMC and safety notices by phone, then in writing within 24 hours.
  • Out-of-scope repairs quoted at a firm fixed price and performed only after written authorization.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Not a solicitation yet. You can only respond to the RFI for now. Nothing in this notice is a bid, and no solicitation has been issued.
  • Deadline time conflicts. The SAM record says 15:00 at +03:00, but the RFI says 1700 local Jordan time. Submit by 15:00 +03:00 and ask the contracting specialist to confirm the time.
  • Tank count does not match. The RFI says there are 3 tanks, but the PWS says one tank is on site and others were under lease. Ask the COR for the exact count and serial numbers before you price the work.“total of 3 tanks, associated Retail Dispensing Skid(s) (RDS)” RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 2
  • Major repairs not in price. Major component failures are not covered by the firm fixed price. Each repair needs a separate quote and written authorization from the Contracting Officer, so do not start it without that authorization.“Major component failures (pumps, motors, meters).” PWS JTC SCAT_Tank_6K_Service Maintenance.pdf, page 3
  • Spares kept at your facility. You must keep a spare RDS and generator set at your own facility, ready to deploy within 48 hours. Price the spares container and 48-hour deployment as their own line, as the RFI pricing table asks.“held at the Contractor’s maintenance facility, not at the fuel site” PWS JTC SCAT_Tank_6K_Service Maintenance.pdf, page 2
  • JCCS registration asked for. The RFI seeks contractors registered, or eligible to register, in JCCS and asks for your status. Check your JCCS status before you respond.“registered (or eligible to register) in the Joint Contingency Contracting” RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 1

Key terms

Who can bidOpen to all; no set-aside usedSize standard is $12.0 Million. The RFI asks for JCCS registration status.SAM.gov record
Contract periodBase period of 12 months from NTP, plus four 12-month optionsOptions may be exercised at the sole discretion of the Government.PWS JTC SCAT_Tank_6K_Service Maintenance.pdf, page 1
How to submitEmail your RFI response to the contracting specialistSubject line: RFI Response – JTC 6K SCAT Tank Sustainment – [Company Name]RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 3
Questions dueThursday, 26 November 2026No time of day is stated. Send questions in writing to the same email address.RFI_JTC_6K_SCAT_Tank_Sustainment_Sources_Sought Notice.pdf, page 3
Contract typeFirm-fixed-price, non-personal servicesOut-of-scope repairs are priced separately.PWS JTC SCAT_Tank_6K_Service Maintenance.pdf, page 1

How to respond

  1. Email your RFI response to usarmy.jordan-jtc.asg-jordan.mbx.asg-j-operational-contract-supp@army.mil, addressed to Hector G Vega.
  2. Use the subject line: RFI Response – JTC 6K SCAT Tank Sustainment – [Company Name].
  3. Send it before 15:00 +03:00 on Thursday, 3 December 2026. The RFI says 1700 local Jordan time, so confirm which applies.
  4. Use Microsoft Word or searchable PDF. The RFI recommends 8 to 12 pages, excluding cover and pricing tables, covering company information, experience, technical approach and ROM pricing.
  5. Send any written questions to the same address by 26 November 2026. The time of day is not stated.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated value or budget for the contract.
  • Exact number of tanks, RDS units and generators, with serial numbers still to be confirmed.
  • Award basis and how responses will be evaluated.
  • Whether and when a solicitation will be issued.
  • Time of day for the question deadline, and the COR's name (listed as TBD).
  • Whether a site visit or pre-response meeting is planned.

Notice text

The Contractor shall provide all personnel, equipment, tools, materials, supervision, and other items and services necessary to perform initial restoration, functional testing, and continuous preventive maintenance and sustainment of the Area Support Group – Jordan (ASG-J) owned 6,000-gallon Self-Contained Aboveground Tank (SCAT) systems located at the fuel point, Joint Training Center (JTC), Jordan. This is a non-personal services contract. The Contractor shall perform to the standards in this PWS.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 20, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy