Gravel road repairs and culverts, Minot Air Force Base, ND

Recondition gravel Minuteman missile access roads near Minot Air Force Base, North Dakota, and add 4 inches of aggregate surface and replacement culverts across three bid schedules.

Official title: ND OMAD 2025(1) Minuteman Missile Access Road

Deadline
Dec 2, 1:00 PM MT
7 days left
Who can bid
Small businesses
Size standard for NAICS 237310: $45 million in average annual receipts · Who qualifies
Last time
$2M
Likely Construction Solutions Group, LLC
Place
Minot, ND
Buyer: 6982AF Central Federal Lands Divisi

What they're buying

You must price all three schedules, and the finish date is not in the pages we could review.

Top catches

Electronic bids not accepted
“ELECTRONIC BIDS WILL NOT BE ACCEPTED. Submit a printed copy of your bid to the address listed on the SF-1442 (Page A-1, Item 8).” ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 4

Bids cannot be emailed or uploaded. Print, seal and deliver your bid so it is received before 1:00 p.m. on December 2, and plan for mail or courier delays.

Technical questions close today
“TECHNICAL QUESTIONS REGARDING THIS SOLICITATION WILL NOT BE ACCEPTED AFTER 4 P.M. ON NOVEMBER 19, 2026” ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 6

Written technical questions are due today at 4 p.m., and the time zone is not stated. If you need answers before bidding, send your question now by email to CFLContracts@dot.gov in one Word document.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 19, 2026 from the notice and 5 of 9 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Recondition existing gravel roads: 7.44 miles in Schedule A, 13.70 miles in Schedule B and 18.25 miles in Schedule C, per Amendment A001.
  • Place 4 inches of aggregate surface course, up to 24 feet wide, with a 4% crown or as the contracting officer approves: 19,900 tons (A), 38,700 tons (B) and 51,900 tons (C), plus haul road aggregate.
  • Replace culverts, including 18-inch and 24-inch corrugated metal and concrete pipe with end sections, and remove 3, 6 or 7 existing culverts by schedule. Schedule C also includes cleaning one culvert in place.
  • Subexcavation and embankment as approved, plus survey and staking at 3, 6 or 7 drainage structures by schedule.
  • Equipment and labor hours: dump truck, wheel loader, motor grader, hydraulic excavator, general labor and hired survey services, plus 6, 12 or 16 object markers by schedule.
  • Soil erosion and sediment control plan submitted to the contracting officer at or before the preconstruction conference, with 30 days allowed for review.

Who did it before

$2M

on the contract that likely holds this work now: Construction Solutions Group, LLC. It ended Oct 16, 2026.

Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.

What to watch for

  • Electronic bids not accepted. Bids cannot be emailed or uploaded. Print, seal and deliver your bid so it is received before 1:00 p.m. on December 2, and plan for mail or courier delays.
  • Technical questions close today. Written technical questions are due today at 4 p.m., and the time zone is not stated. If you need answers before bidding, send your question now by email to CFLContracts@dot.gov in one Word document.
  • Acknowledge Amendment A001 in Item 19. Amendment A001 changes the bid schedule, quantities and plan sheets. Enter A001 and its date in Item 19 of the SF-1442, or your bid may be rejected.“FAILURE TO ACKNOWLEDGE THIS AMENDMENT IN BLOCK 19 OF THE SF 1442 BY THE DESIGNATED DATE AND HOUR SPECIFIED IN THE SOLICITATION MAY RESULT IN REJECTION OF YOUR BID” Amendment A001 ND OMAD 2025(1).pdf, page 1
  • Schedule A length does not match. The amendment cover shows Schedule A at 7.35 miles, but its bid schedule and quantity table use 7.44 miles of reconditioning. Schedules B and C also differ. Ask the contracting officer which length applies before you price the work.“SCHEDULE A LENGTH7.35 MILES” Amendment A001 ND OMAD 2025(1).pdf, page 11
  • All three schedules must be priced. You must price every item in Schedules A, B and C to be eligible. If funds are short for Schedule C, the award is evaluated on Schedule B, and then on Schedule A. Price all three in full.“To be eligible for award of contract, the offeror shall submit prices for each item necessary to complete all contract work in Schedule A, Schedule B and Schedule C.” ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 12
  • Bid bond must be an original. The bid bond is 20 percent of the bid price, up to $3,000,000. It must be an original with original signatures and corporate seals, and it must be executed no later than bid opening. Arrange the surety before you print the bid.“Photocopied and faxed copies of bonds will be rejected and cause your bid to be non-responsive.” ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 6

Key terms

Who can bidSmall businesses only (total small business set-aside)Size limit is $45 million average annual gross receipts over 5 years under NAICS 237310. You must have an active SAM registration when you bid.SAM.gov record
Contract periodStart within 10 calendar days of notice to proceed; end date Not statedThe finish date is in SCR Section 108.01, which was not in the pages provided.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 11
How they chooseLowest responsive, responsible bidder, subject to fundsSchedule C is evaluated first, then B, then A if funds are not available.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 12
How to submitPrinted, sealed bid delivered to the Lakewood, CO office; no electronic bidsEmail is accepted only for modifications to a bid, sent to cflcontracts@dot.gov before the deadline.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 4
Questions dueThursday, November 19, 2026, 4 p.m. (time zone not stated)Send written questions by email to CFLContracts@dot.gov in one Word document. This is today.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 6
Estimated value$2,000,000 to $5,000,000This is the price range printed on the SF-1442 form, not a bid amount.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 11
Contract typeSealed bid with unit prices and lump sumsFederal Highway Administration road construction contract under the FP-24 specifications.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 12
Site visitVirtual pre-bid meeting held November 12, 2026; not mandatoryThat meeting has already passed. No site visit is stated in the pages provided.ND OMAD 2025 (1) 6982AF27B000011 IFB .pdf, page 8

How to respond

  1. Print the bid forms listed in the Notice to Bidders: SF-1442 pages A-1 and A-2, the bid schedule pages attached to Amendment A001, the certificates on pages A-13 to A-17, pages A-18 and A-19, bid bond pages B-1 to B-4, the VETS-4212 declaration on page A-iii, and bidder information pages B-5 to B-8.
  2. Enter a unit price and amount for every line in Schedules A, B and C, add the schedule totals, and sign the forms where required, including the Item 19 amendment acknowledgment for A001.
  3. Place the bid and the original bid bond in a sealed envelope marked with your name, solicitation number 6982AF27B000011, project ND OMAD 2025(1), and the date and time of receipt. Address it to Eric Grosskreuz, Federal Highway Administration, Central Federal Lands Division Office, 12300 W. Dakota Avenue, Lakewood, CO 80228; the suite number is unclear (167 or 360), so confirm it before you send.
  4. Make sure the envelope is received by 1:00 p.m. local time on Wednesday, December 2, 2026. Email is accepted only for modifications, sent to cflcontracts@dot.gov before that time.

Attached files

From SAM.gov. Download links open the original files.

1 more file from a ZIP archive
  • ND OMAD 2025(1) Culverts and Routes Schedule Seperated.kmz Could not be read.

Download the archive from SAM.gov.

Not stated in what we read

  • The finish date and other rules in the Special Contract Requirements (SCR Section 108.01 and Divisions 100 to 700), because those pages were not in the copy we reviewed.
  • Route and culvert locations: the route file is a KMZ that we could not read, and the plan set (Plans_v2.pdf) was not included. Open both on SAM.gov before you price.
  • Insurance minimums (FP-24 Subsection 107.05) and the Department of Labor wage rates (Construction Wage Rate Requirement, page D-1), which were not included.
  • Performance and payment bond amounts, which the notice refers to in sections that were not provided.
  • Whether Amendment A001 extended the bid opening. The extension check box is not clear in the text, and the SAM record still shows December 2.
  • Answers in the Q&A file dated 11.18.26 and the pre-bid conference presentation, neither of which was included.

Notice text

PROJECT DESCRIPTION: The Office of Missile Air Defense Program (OMAD) is a Defense Access Road (DAR) program used by the Department of Defense (DoD) to fund the annual maintenance and improvements on certified gravel roads. FHWA works with the Military Surface Deployment and Distribution Command (SDDC) to support the Air Force Intercontinental Ballistic Missile Program (Minuteman). These Minuteman Missile Access Roads are located in 6 counties within North Dakota.

SCOPE OF THE WORK: The work includes roadway reconditioning and adding four inches of aggregate surface course as well as the replacement of culverts. All proposed work is to stay on the existing roadway bench. The proposed typical section consists of reconditioning the existing gravel roadway per Section 303 and adding an additional 4-inches of Aggregate Surface Course with a maximum width of 24-feet. A 4% crown is proposed or as approved by the CO. The Contractor will need to taper down the proposed aggregate surface, per the typical section, at applicable locations.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

Who may hold this work now

Contracts at Federal Highway Administration for the same kind of work (NAICS 237310, service code Y1LB) in North Dakota that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.

Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.

History

  • Nov 19, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Federal Highway Administration by email

Each morning we'll send the new solicitations and sources-sought notices from Federal Highway Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy