Seawater pump replacement and wiring, Milford, CT
Replace the salt water pump system and its electrical controls at the NOAA Northeast Fisheries Science Center in Milford, CT, including four non-metallic pumps, four variable frequency drives and new wiring.
Official title: Seawater Pump Renovation
- Deadline
- Dec 7, 12:00 PM ET
- 12 days left
- Who can bid
- Small businesses
- Size standard for NAICS 236220: $45 million in average annual receipts · Who qualifies
- Last time
- None found
- No contract like it at this agency in USAspending.gov
- Place
- Milford, CT
- Buyer: Dept of Commerce NOAA
What they're buying
All work must be finished by February 17, 2027, with a 10-day maximum pump shutdown.
Top catches
“Submit signed and dated offers electronically via email to the Contracting Officer and Contract Specialist, Charles Kendall, at charles.kendall@noaa.gov AND Grace LaPierre, at grace.lapierre@noaa.gov, at or before the exact time specified in this solicitation.” Sol_1305M327Q0034.pdf, page 38
The SF 1442 still mentions sealed paper offers, but the RFI answer says email governs. Send your full offer by email to both contacts so it arrives before the deadline, and keep proof of sending.
“To be considered for the award, Offeror must submit a” Sol_1305M327Q0034.pdf, page 38
The provision says the Technical Plan must be submitted to be considered for award. Include all five parts: approach, schedule, warranty plan, subcontractors with percentages, and spec sheets for any substitute equipment.
Read by AI (Claude Haiku) on Nov 25, 2026 from the notice and 7 of 8 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Remove the legacy disconnects, starters, breakers, wire trough, enclosures, wiring and plumbing piping, under lock-out/tag-out.
- Four Vanton Chem-Gard non-metallic centrifugal pumps or equal, with Kynar wetted parts only, all rated 15 HP, on anti-vibration pads.
- Four WEG variable frequency drives in NEMA 4X enclosures, with Building 1 drives rated 15 HP per the RFI, plus four NEMA 4X disconnects and new THHN feeder wire.
- Replace four pressure sensors and provide two spares, plus four current transducers for local monitoring only, and LED lighting in the work zone.
- Deliver two spare impellers to facility inventory, then test with megger, insulation resistance and motor rotation checks.
- Written 5-year comprehensive labor and materials warranty on the pump assembly, with no dollar limit.
Who did it before
No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.
What to watch for
- Email is the only route. The SF 1442 still mentions sealed paper offers, but the RFI answer says email governs. Send your full offer by email to both contacts so it arrives before the deadline, and keep proof of sending.
- Technical Plan is required. The provision says the Technical Plan must be submitted to be considered for award. Include all five parts: approach, schedule, warranty plan, subcontractors with percentages, and spec sheets for any substitute equipment.
- Bid guarantee and 100% bonds. Your bid needs a bid guarantee of 20 percent of your price or $100,000, whichever is less. After award you must furnish performance and payment bonds at 100 percent of the price within 10 calendar days, so check surety capacity before you bid.“The amount of the bid guarantee shall be 20 percent of the bid price or $100,000.00, whichever is less.” Sol_1305M327Q0034.pdf, page 45
- Two wage determinations listed. Amendment 0001 switched to Connecticut wage determination CT20260023, but Amendment 0002 still lists MA20260001 as well. Ask the contracting officer which one applies before you price labor.“Renamed and upload the corrected Davis Bacon Act Wage Determination #CT20260023 (Attachment 2).” Sol_1305M327Q0034_Amd_0001.pdf, page 1
- Four-week delivery may not be realistic. The pumps and drives must be ordered at once and delivered within four weeks of notice to proceed. The RFI says NEMA 4X enclosures may take longer, so quote your real lead time and completion date.“NEMA 4X enclosures have longer lead times” Attachment 3 - RFI Tracker 1305M327Q0034 dated 11.24.2026.pdf, page 3
- All four pumps now 15 HP. The SOW lists 10 HP pumps for Building 1, but the RFI answers say all four pumps and the Building 1 drives must be 15 HP. Price every pump and drive at 15 HP.“Yes, all 4 pumps are required to have 15 HP motors.” Attachment 3 - RFI Tracker 1305M327Q0034 dated 11.24.2026.pdf, page 3
Key terms
| Questions due | Noon EST, November 19, 2026 (closed)Questions closed six days ago. Only answers in an amendment change the work.Attachment 3 - RFI Tracker 1305M327Q0034 dated 11.24.2026.pdf, page 2 |
|---|---|
| Site visit | Nov 17 and Nov 18, 2026 (both passed)Visits were highly recommended, not required. REAL ID is needed to enter campus.Sol_1305M327Q0034_Amd_0001.pdf, page 3 |
| Who can bid | Small businesses only (total set-aside)Your SAM registration must list NAICS 236220 to be eligible for award. The size standard is $45 million.SAM.gov record |
| Contract period | Award through February 17, 2027Start date is set with the COR and CO after award. Pumps must be ordered within four weeks of notice to proceed.Attachment 01 - Statement of Work.docx.pdf, page 5 |
| How they choose | Most advantageous offer, price and other factors consideredFactors, in order: technical approach, price, then past performance.Sol_1305M327Q0034.pdf, page 40 |
| How to submit | Email to charles.kendall@noaa.gov and grace.lapierre@noaa.govThe SF 1442 still mentions sealed offers, but the RFI answer says email governs.Sol_1305M327Q0034.pdf, page 38 |
| Contract type | Firm-fixed-price, one line itemYou furnish all labor, materials, equipment, transportation and supervision.Sol_1305M327Q0034.pdf, page 6 |
How to respond
- Email your offer to charles.kendall@noaa.gov and grace.lapierre@noaa.gov so it arrives by 12:00 PM EST on Monday, December 7, 2026. File format and size limits: Not stated.
- Sign and date the offer, complete SF 1442 blocks 14 to 20, and list Amendments 0001 and 0002 by number and date in block 19.
- Include a bid guarantee of up to 20 percent of your price, capped at $100,000. The notice recommends SF 24 for bid bonds.
- Write a Technical Plan with five parts, and attach manufacturer spec sheets for any equivalent pump or drive you propose.
- Attach copies of Sections I and II of each past performance questionnaire (Attachment 4) to your offer, and give each assessor the form to complete.
Attached files
From SAM.gov. Download links open the original files.
- Attachment 3 - RFI Tracker 1305M327Q0034 dated 11.24.2026.pdfThe final government answers to bidder questions, which change pump, drive and submission terms, so read it with the SOW and does not need to be filled in. Read.
- https://sam.gov/api/prod/opps/v3/opportunities/resources/files/7e196570b3374739bc2f10677a9f570f/download Could not be read.
- Sol_1305M327Q0034_Amd_0001.pdfAmendment 0001 changes the time zone, wage determination, superintendent and insurance clauses, and is read only. Read.
- Sol_1305M327Q0034.pdfThe base solicitation with the SF 1442 offer form, clauses and bid rules; you must complete, sign and return the offer blocks. Read.
- Attachment 4 - Past-Performance-Questionnaire 1305M327Q0034.docxA questionnaire template in which you complete Sections I and II and submit copies with your offer, while your past customer completes the rest. Read.
- Attachment 5 - Local Subcontracting Options.pdfA list of two local subcontractors offered as options; use is not required, so it is read only. Read.
- Attachment 01 - Statement of Work.docx.pdfThe work description, quantities, schedule and rules you must price and deliver; it is read only. Read.
- Sol_1305M327Q0034_Amd_0002.pdfAmendment 0002 replaces the RFI tracker with the final version and lists the attachments, and you must acknowledge it in block 19 of the offer. Read.
Not stated in what we read
- Estimated contract value: Not stated.
- Davis-Bacon wage rates for CT20260023 and MA20260001: the wage determinations were not in the files we could review, so read them on SAM.gov.
- One attachment hosted on SAM.gov at a download link could not be read, so you must review it yourself.
- Notice to proceed and start date: Not stated; the start is set with the COR and contracting officer after award.
- Hazardous materials on site: Not stated; the SOW says no hazardous materials survey is available.
- Funding and accounting data: Not stated.
Notice text
Amendment 0002 to Seawater pump renovation at the oyster breeding center, electrical and plumbing components present. See attached Statement of Work for details.
As published on SAM.gov.
Contacts
- LA PIERRE, GRACE, GRACE.LAPIERRE@NOAA.GOV, 2065264382
- KENDALL, CHARLES M., CHARLES.KENDALL@NOAA.GOV
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
History
- Nov 25, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 7, 12:00 PM ET12 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 236220, commercial and institutional building construction, soonest deadline first.
- Department of the NavyLab and test building at Philadelphia Navy Yard, PA
- Department of the Air ForceBase repair and minor construction, Wright-Patterson AFB, OH
- Department of the ArmyMaintenance building at C and D Canal, Chesapeake City, MD
- Forest ServiceNew lookout cab and power at Barillas Peak, NM
- Department of Veterans AffairsParking garage repair and redesign in Reno, Nevada
- Department of the Air ForceEnlisted dormitory construction at Kirtland AFB, NM
- Public Buildings ServiceKitchenette refresh at Weinberger Courthouse, San Diego, CA
- Department of Veterans AffairsFY27 NRM (PROJ 573-24-110) BB - Expand Cardiology Service
Free · at most one email a morning
Get new notices from National Oceanic and Atmospheric Administration by email
Each morning we'll send the new solicitations and sources-sought notices from National Oceanic and Atmospheric Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy