Perimeter security and lot repair, Whitten Lot 9, DC

USDA wants a design-build contractor to finish Lot 9 at the Jamie L. Whitten Building in Washington, DC.

Official title: USDA Design/Build Perimeter Security Enhancement Parking Lot 9

Deadline
Jan 6, 2027, 2:00 PM ET
42 days left
Who can bid
Any business
Registered in SAM.gov · How to register
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Washington, DC
Buyer: USDA, Ocp-Pod-Acq-Mgmt-Branch-FTC

What they're buying

The work covers perimeter security, sinkhole repair, paving, electrical and landscaping, due within 11.5 months after Notice to Proceed (NTP).

Top catches

Mandatory site visit, pre-register first
“Quoters who do not attend the mandatory site visit will be non-responsive offerors.” Notice text

Attend the December 2 visit at Lot 9 or your quote is non-responsive. Email the names of everyone on your team to the Contracting Officer by December 1, 2026, 2:00PM (EST).

Contract dates conflict
“Period of Performance: 03/01/2027 to 02/15/2028” RFQ 124PCA27Q0002 SF1442.pdf, page 3

The SF 1442 lists fixed dates, 03/01/2027 to 02/15/2028, and also 345 days from award. Other documents say 11.5 months from Notice to Proceed. Ask the Contracting Officer which governs before you set your schedule and price.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 21, 2026 from the notice and 5 of 15 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Remediate sinkholes and stabilize the subsurface under Lot 9 using Langan Option 2, approved by WMATA and USDA.
  • Provide bollards at the north border with the top at least 36 inches above grade, meeting M50/P1 and certified by the manufacturer.
  • Install and wire gate arms, badge readers and hydraulic bollards at both entries, coordinated with USDA OSSP.
  • Mill and resurface the parking lot, then stripe and number the spaces and provide signage.
  • Restore the pipe rail with lead paint abatement, and build the 1:12 accessible ramp to the People's Garden with granite curbs.
  • Landscape with new plants and an irrigation system, and deliver as-built drawings, O&M manuals and a two-year bollard warranty.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Mandatory site visit, pre-register first. Attend the December 2 visit at Lot 9 or your quote is non-responsive. Email the names of everyone on your team to the Contracting Officer by December 1, 2026, 2:00PM (EST).
  • Contract dates conflict. The SF 1442 lists fixed dates, 03/01/2027 to 02/15/2028, and also 345 days from award. Other documents say 11.5 months from Notice to Proceed. Ask the Contracting Officer which governs before you set your schedule and price.
  • No price in Phase 1. Your Phase 1 quote covers the cover letter, technical approach, past work and management only. Keep every price figure out of it, or your quote can be removed. Price is scored only in Phase 2.“Offerors shall not include any pricing information in their non-price submissions.” INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 9
  • Granite curbs have long lead time. Only four 8-foot granite curb lengths were bought. The SOW says the item has a reported 16-week delivery time, so plan for it early and price the curbs you must still buy.“This is a long lead item, reportedly with a 16-week delivery time.” Attachment 1 SOW Lot 9 11.19.2026.pdf, page 3
  • Daily damages and 100% bonds. Each calendar day late costs $1,800 in liquidated damages. Performance and payment bonds for 100% of the price are due within 14 days of award, and Notice to Proceed waits for bond approval.“$1,800.00 per calendar day is included in the requirement” INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 4
  • Night and weekend work limits. The notice says there are no work-hour limits, but the SOW says noisy work must be done outside normal building hours unless the COR approves. Ask the Contracting Officer in writing and price after-hours work if you need it.“All noise producing activities affecting normal building operations shall be done outside of the above specified time, unless approved by the COR.” Attachment 1 SOW Lot 9 11.19.2026.pdf, page 5

Key terms

Who can bidUnrestricted, no set-aside, open to large and small firmsMust be actively registered in SAM under NAICS 237310. Design firms must be registered in DC, and the construction contractor needs a DC general contractor license.RFQ 124PCA27Q0002 SF1442.pdf, page 1
Contract period11.5 months from Notice to Proceed (NTP)The SF 1442 also lists fixed dates. See the contract dates catch.INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 5
How they chooseBest value, one awardPhase 1 covers Factors 1 to 4 only. Price is judged in Phase 2 after the advisory down-select.INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 20
How to submitEmail one PDF to gerardo.rivera@usda.govSubject line: RFQ #124PCA27Q0002, Lot 9 Security Enhancement, Quotation, Vendor Name. Faxed or mailed quotes are not accepted.INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 2
Questions dueWednesday, December 9, 2026, 2:00PM (EST)Email questions to the Contracting Officer. Questions after this time may get no answer.INSTRUCTIONS TO OFFERORS LOT 9 11.19.2026.pdf, page 3
Contract typeFirm-fixed-price design-buildPrice must cover all costs. Performance and payment bonds for 100% of the price are required.RFQ 124PCA27Q0002 SF1442.pdf, page 3
Site visitWednesday, December 2, 2026, 10:30 a.m. Eastern Standard Time (EST)Mandatory. Email attendee names to the Contracting Officer by Tuesday, December 1, 2026, 2:00PM (EST).Notice text

How to respond

  1. Confirm your SAM registration is active under NAICS 237310 and that your representations and certifications are current before the deadline.
  2. By Tuesday, December 1, 2026, 2:00PM (EST), email the names of everyone attending to gerardo.rivera@usda.gov. Attend the site visit on Wednesday, December 2, 2026, at 10:30 a.m. EST at Parking Lot 9.
  3. By Wednesday, December 9, 2026, 2:00PM (EST), email any questions to the Contracting Officer. Use the subject line RFQ 124PCA27Q0002, Lot 9 Security Enhancement, Questions, Vendor Name.
  4. By Wednesday, January 6, 2027, 2:00PM (EST), email one PDF to gerardo.rivera@usda.gov with the subject line RFQ #124PCA27Q0002, Lot 9 Security Enhancement, Quotation, Vendor Name. Cover letter up to 2 pages, technical up to 10, past work up to 6, management up to 4. Include no pricing.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated contract value. The notice does not state a budget or government estimate.
  • Property damage insurance amount. The instructions show a blank placeholder ($X) for it.
  • Which schedule governs: the fixed dates or 11.5 months from Notice to Proceed.
  • Quantities and condition of the bollards and curbs stored on site. You must verify them.
  • Sinkhole extent and remediation cost. These are for you to determine and are not stated.
  • Davis-Bacon wage determination and the Langan geotechnical report. We could not review them, so you must read them on SAM.gov.

Notice text

The site visit will be held on Wednesday, December 2, 2026, at 10:30 a.m. Eastern Standard Time (EST). Quoters who do not attend the mandatory site visit will be non-responsive offerors. USDA requires a Design/Build contractor to complete the rehabilitation of Parking Lot 9 at the Jamie L. Whitten Building in Washington, DC. The project includes perimeter security upgrades, parking lot resurfacing, sinkhole remediation, electrical work, and landscaping, and is a key component of a larger effort to establish Level IV security protection around the facility.

The contractor must assess and update incomplete 2021 construction documents, verify the suitability of security materials already stored on site, and coordinate closely with WMATA due to the Orange, Blue, and Silver Metro lines running beneath the parking lot. After construction began in 2024, sinkholes developed near a WMATA elevator, halting work; therefore, the contractor must determine the full extent of subsurface issues and implement a remediation plan approved by both USDA and WMATA, incorporating recommendations from Langan’s geotechnical investigation.

With historic preservation approvals already secured and no work-hour restrictions in place, the project’s objective is to restore progress on the halted construction and deliver the required Level IV perimeter security enhancements within eleven and a half months of Notice to Proceed (NTP) issuance.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 20, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from USDA, Departmental Administration by email

Each morning we'll send the new solicitations and sources-sought notices from USDA, Departmental Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy