Riprap bank repairs on Road 107, Olympic NP, WA
Bank and road repairs at two sites on Upper Hoh Road (Road 107) in Olympic National Park: riprap, engineered log jams with dolosse, planting, erosion control and traffic control.
Official title: WA ERFO NPS OLYM 2022-1(3), OLYMPIC NPS ERFO REPAIRS 2022 Road 107 MP 0.3 TO 0.5 & MP 0.8
- Deadline
- Dec 3, 2:00 PM PT
- 8 days left
- Last time
- $10.4M
- Likely Tucci & Sons LLC
- Place
- Forks, WA
- Buyer: 690567 Western Federal Lands Div
What they're buying
You price two schedules, A and B, and the work must be complete by September 13, 2027.
Top catches
“Facsimile and email bids are not authorized for this solicitation.” IFB_69056727B000002.pdf, page 18
Electronic and email bids are not accepted, so send a printed sealed bid by the deadline. Email may only modify or withdraw a bid that arrives on time, and the government is not responsible for email failures.
“Bids received without a valid bid bond will be rejected.” IFB_69056727B000002.pdf, page 3
A bid without a valid original bid bond on Standard Form 24, with the Power of Attorney attached, will be rejected. The bond amount is not stated in the text provided; it refers to FAR 52.228-1.
Read by AI (Claude Haiku) on Nov 25, 2026 from the notice and 7 of 14 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.
The work
- Riprap: 790 cubic yards Class 4 and 260 cubic yards Class 5, plus 80 boulders.
- Engineered log jams with dolosse at MP 0.8: 4 units per schedule, with 6 environmental design root wads.
- Clearing and grubbing of 1,400 square yards, and a temporary stream diversion at MP 0.3 to 0.5.
- Erosion control: 330 linear feet of fiber roll, 1,300 square yards of rolled erosion control product, 1,600 square yards of hydraulic mulch, and 840 square yards of hydraulic turf establishment with Government-furnished seed.
- Install Government-furnished plants and poles, and keep one lane open to traffic at all times.
- Traffic control: 1,000 flagger hours, 50 supervisor days, 40 tubular markers, 15 drums, 6 warning lights, 190 square feet of signs, and 80 linear feet of pavement markings and removal.
Who did it before
$10.4M
on the contract that likely holds this work now: Tucci & Sons LLC. It ended Oct 30, 2026.
Matched in USAspending.gov by agency, NAICS and service code; notices rarely name the contractor.
What to watch for
- Paper bids only, no email. Electronic and email bids are not accepted, so send a printed sealed bid by the deadline. Email may only modify or withdraw a bid that arrives on time, and the government is not responsible for email failures.
- Bid bond or bid is rejected. A bid without a valid original bid bond on Standard Form 24, with the Power of Attorney attached, will be rejected. The bond amount is not stated in the text provided; it refers to FAR 52.228-1.
- Schedule B needs textured dolosse. Schedule B calls for tree-bark-style texture on the dolosse. A bidder asked to drop the texture, and the government answered to bid per the solicitation, so price the textured units for Schedule B.“For Schedule B, provide tree-bark-like texture precast dolosse” wa-ep-olym2022-1-3_plans_IFB.pdf, page 15
- Root wad counts do not match. The bid schedule lists 6 root wads, but the log-jam notes call for 11 root wads in Layer A alone, plus 7 in Layer B and 4 in Layer C. Ask the contracting office in writing which count governs before you price the root wads.“3. Layer A: 11 log-dolos bundles and 11 root wads.” wa-ep-olym2022-1-3_plans_IFB.pdf, page 15
- Question cutoff may have passed. By our count the cutoff was likely close of business November 24, and a bidder asked FHWA to confirm November 25; no answer appears in the text provided. Check SAM.gov for answers, and send any plan or spec question in writing to wfl.plans-spec@dot.gov if the cutoff is still open.“confirm if the last day to submit questions is” QandA_11-24-2026.pdf, page 2
- EPA plan due 30 days before work. If this EPA permit condition applies, a plan must reach EPA Region 10 at least 30 days before construction starts, and the work needs daily inspections. Ask the contracting office whether it applies and who carries that duty before you price the job.“Submit the plan to EPA Region 10 at R10-401-Certs@epa.gov at least 30 days prior to commencing construction activities.” IFB_69056727B000002.pdf, page 342
Key terms
| Who can bid | Open to all bidders (full and open); no set-asideA large-business low bidder must submit a subcontracting plan, and a 10% price factor can apply to a large-business low bid.Notice text |
|---|---|
| Contract period | Start within 10 days of notice to proceed; finish by 09/13/2027The completion date assumes notice to proceed by 01/25/2027 and moves later if notice comes later.IFB_69056727B000002.pdf, page 22 |
| How to submit | Printed sealed bid to the FHWA office in Vancouver, WA; no email or electronic bidsEmail may be used only to modify or withdraw a bid.IFB_69056727B000002.pdf, page 1 |
| Questions due | Unclear: close of business Nov 24 or Nov 25, 2026Five business days before the Dec 3 due date; FHWA has not confirmed the date in the text provided.QandA_11-24-2026.pdf, page 2 |
| Estimated value | $2,000,000 to $5,000,000 (price range)A government price range, not a bid total.IFB_69056727B000002.pdf, page 23 |
| Contract type | Unit-price construction contract, sealed bidBid unit prices times estimated quantities; some items are lump sum (LPSM).IFB_69056727B000002.pdf, page 30 |
| Site visit | No show-me tours; view the site on your ownSigns do not mark the project limits, and no government staff will meet you.IFB_69056727B000002.pdf, page 16 |
How to respond
- Price both Schedule A and Schedule B on the bid schedule pages A-7 to A-12, using unit price times quantity for each item, and enter each schedule total on the summary page A-12.
- Sign the SF 1442 (pages A-3 and A-4) and the bid bond, attach the Power of Attorney and an Authority to Sign form for each signer, and list your UEI, CAGE code and any amendment numbers.
- Print the bid and seal it in an envelope marked 'Bid Enclosed' in the lower left corner, with solicitation number 69056727B000002 and the project name.
- Deliver the sealed bid to FHWA Western Federal Lands Division, 610 East Fifth Street, Vancouver, WA 98661, by 2:00 PM local time on Thursday, December 3, 2026. Email is not an accepted way to submit the bid.
- Use email to wfl.contracts@dot.gov only to modify or withdraw a bid received before the deadline, and call 360.619.7520 to confirm receipt.
Attached files
From SAM.gov. Download links open the original files.
- QandA_11-23-2026.pdfA question and answer log dated 11/23/2026 with one bidder question on the Schedule B dolosse finish, answered to bid per the solicitation documents; read only. Read.
- QandA_11-24-2026.pdfA second question and answer log that repeats the dolosse question and asks about the question deadline, with no answer on that deadline; read only. Read.
- IFB_69056727B000002.pdfThe invitation for bids with the SF 1442, bid schedules, bid bond form and certifications; you must complete and sign the SF 1442, bid bond, bid schedules and certifications. Only pages 1 to 44 and 339 to 380 were provided. Read in part (pages 1–44 and 339–380 of 380).
- wa-ep-olym2022-1-3_plans_IFB.pdfConstruction plan sheets, quantity tables and standard details, with notes on dolosse and root wads; read it to price and build, and nothing needs signing. Read.
10 more files from a ZIP archive, 3 read
- FLH Bridge Oversized-Overweight Permit Load Request Form.pdfA blank form for oversize or overweight loads on bridges; complete it only if you will haul such loads for this project. Read.
- wa-ep-olym-1-3_clearing-limit.pdf Older version, not read.
- wa-ep-olym-1-3_clearing-limit.xlsxA spreadsheet of construction limit points that replaces an older PDF version; read it for limits, and nothing needs signing. Read.
- wa-ep-olym2022-1-3_control-points.xlsx Not read: over our length limit.
- wa-ep-olym2022-1-3_ESCP.pdf Not read: over our length limit.
- wa-ep-olym2022-1-3_existing-ground-surface.xml Could not be read.
- wa-ep-olym2022-1-3_HYD_memo.pdf Not read: over our length limit.
- wa-ep-olym2022-1-3_proposed-alignment_Main01.pdf Not read: over our length limit.
- wa-ep-olym2022-1-3_proposed-alignment_Main01.xml Could not be read.
- wa-ep-olym2022-1-3_WFLHD-28.pdfOnly an Adobe Reader error page was provided, so I could not review this file; you must read it on SAM.gov. Read.
Download the archive from SAM.gov.
Not stated in what we read
- Wage rates: the General Wage Decision (Section D) and Davis-Bacon details are not in the text provided.
- Award basis under Subsection 102.05A, and the bid bond amount under FAR 52.228-1.
- Special Contract Requirements and insurance rules (Subsections 102.02, 107.05, 108 and 552.12), which fall in pages 45 to 338 that were not provided.
- Dolosse size, count and finish: a bidder question cites 8-ton units and 140 pieces, but the answer does not confirm either figure.
- Files not provided: the ESCP, hydraulic memo, alignment, control point and existing ground files; you must read them on SAM.gov.
- Material sources and the Hoh Pit staging site: no source is identified, and you must secure permits for any site you use.
Notice text
Update 11/24/2026: QandA_11-24-2026.pdf posted to arrachments. Update 11/23/2026: QandA_11-23-2026.pdf posted to arrachments. Invitation for Bids (IFB) for Construction Project, WA ERFO NPS OLYM 2022-1(3), OLYMPIC NPS ERFO REPAIRS 2022 Road 107 MP 0.3 TO 0.5 & MP 0.8 The IFB, plans, and physical data are posted under Attachments/Links. Note: This project is being advertised as Full and Open INTERESTED VENDORS LIST: The Interested Vendor List on SAM.gov is viewable only by users who are linked to an entity with an active Unique Entity Identifier (UEI) and hold an assigned role (such as Contract Opportunities Administrator, Data Viewer, or Data Entry). The Federal Government does not maintain or provide a separate plan holders list. If you need assistance, go to https://www.fsd.gov/gsafsd_sp.
As published on SAM.gov.
Contacts
- Contracts G. Office, wfl.contracts@dot.gov, 3606197520
As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.
Who may hold this work now
Contracts at Federal Highway Administration for the same kind of work (NAICS 237310, service code Y1LB) in Washington that end within a year either way of today. Notices rarely name the current contractor: these are likely candidates, not a fact.
Source: USAspending.gov, prime contracts of $100,000 or more. Department of Defense contracts appear there about 90 days after award.
History
- Nov 25, 2026: first seen in the SAM.gov extract
SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.
Should you bid?
Dec 3, 2:00 PM PT8 days left
A free report for your company: whether you can bid, what to confirm first and who may hold the work now.
Get the free reportSimilar open notices
Open now under NAICS 237310, highway, street, and bridge construction, soonest deadline first.
- Departmental OfficesWaterman canal gate for Wheeler refuge, Decatur, AL
- Department of the ArmyRoads, parking and grounds renovation, Detroit, MI
- Departmental OfficesRoad and bridge repair at national parks nationwide
- Department of the NavyService road realignment and roundabout, Camp Lejeune, NC
- Federal Highway AdministrationThree bridges and road rebuild in Arches National Park, UT
- Federal Highway AdministrationThree bridges and a culvert on SR 35, Mimbres, NM
- Forest ServiceRoad and trailhead upkeep, Little Missouri Grassland, ND
- Department of the Air ForceTaxiway repairs at North Auxiliary Airfield, SC
Free · at most one email a morning
Get new notices from Federal Highway Administration by email
Each morning we'll send the new solicitations and sources-sought notices from Federal Highway Administration, with deadlines and set-asides up front. Free. Unsubscribe in one click.
The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy