1. Opportunities
  2. Department of Defense
  3. Department of the Army
  4. W912DW27QA006

Sewage lagoon liner repair, Mud Mountain Dam, Enumclaw, WA

Clean, inspect, and repair the sewage lagoon liner, two broken PVC inlet pipes, the clogged outlet pipe, and the chlorinator at Mud Mountain Dam near Enumclaw, WA.

Official title: Mud Mountain Dam Sewage Lagoon Repair

Deadline
Dec 1, 10:00 AM PT
6 days left
Who can bid
Small businesses
Size standard for NAICS 237110: $45 million in average annual receipts · Who qualifies
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Enumclaw, WA
Buyer: W071 Endist Seattle

What they're buying

Work must finish within 45 calendar days of notice to proceed, and quotes are due Tuesday 1 December 2026 at 10:00 a.m. Pacific.

Top catches

Payment bond or letter of credit
“The amount of the payment protection shall be 100 percent of the contract price.” W912DW26QA006.pdf, page 33

You must provide a payment bond or irrevocable letter of credit for 100 percent of the contract price within 10 days of award. The Government says no other forms are accepted, so confirm you can get one and price its cost before you bid.

Davis-Bacon wage rates apply
“Davis Bacon Wage Determination WA20260125” W912DW26QA006.pdf

Workers must be paid at least the wage rates in determination WA20260125, which covers King County, plus fringe benefits. Price labor for the classes your crew needs at those rates, not your usual rates.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 24, 2026 from the notice and 7 of 9 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Mobilize and demobilize, then remove the aerator and about 15 cubic yards of gravel from the liner using a vacuum truck.
  • Inspect the liner for leaks and patch tears, holes, and blisters with HDPE patches, and replace the inlet pipe boot if it is defective, with welded seams.
  • Replace two broken PVC inlet pipes with schedule 80 PVC and banded couplings, clear the clogged outlet pipe, and replace the chlorinator with a Sanuril model 100 or equal plus one 45-pound pail of tablets.
  • Run the trial seam, vacuum box, air lance, and two 24-hour controlled water-hold tests, with the government QAR witnessing the required tests.
  • Sanitize and return the gravel, or supply new gravel of matching size, and spread it for a 4 to 6 inch cover.
  • Give a one-year warranty, and deliver the work plan, activity hazard analysis, accident prevention plan, and as-built drawings before close-out.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Payment bond or letter of credit. You must provide a payment bond or irrevocable letter of credit for 100 percent of the contract price within 10 days of award. The Government says no other forms are accepted, so confirm you can get one and price its cost before you bid.
  • Davis-Bacon wage rates apply. Workers must be paid at least the wage rates in determination WA20260125, which covers King County, plus fringe benefits. Price labor for the classes your crew needs at those rates, not your usual rates.
  • The 45 days start later. The 45 days start only when the Government issues notice to proceed, which waits on your payment protection. Approved submittals are required before you mobilize, so plan for less time on site and an unknown start date.“All work must be complete within 45 calendar days of Notice to Proceed (NTP).” W912DW26QA006.pdf, page 6
  • Failed final water test not covered. Under the SOW you have, repairs after a failed final water-hold test are not covered by the contract. The amendment says that wording was removed and points to an updated SOW that is not on the attachment list, so ask the contracting officer who pays for re-testing before you price.“Additional repairs if this test is unsuccessful are not covered under this contract.” W912DW26QA006.pdf, page 11
  • Two project types and lead seamer proof. Your technical quote is rated unacceptable unless it shows recent projects in both lagoon cleaning and liner repair, plus Lead Seamer certification or three years of HDPE liner experience. A subcontractor's projects count only if the prime uses that same subcontractor.“The Quoter shall submit evidence of the Lead Seamer's certifications or qualifications as required by Section 3.2 of the SOW.” W912DW27QA0060001.pdf, page 15
  • Payment terms conflict. The base SOW says you are paid per job after all work is done. Amendment 0001 says FAR 52.232-5 applies instead, which means monthly progress payments with up to 10 percent retainage, so plan your cash flow around monthly billing.“FAR 52.232-5 applies. See updated SOW.” W912DW27QA0060001.pdf, page 11

Key terms

Who can bidSmall businesses only (100% small business set-aside)You must be registered in SAM with an active record before you submit a quote, or your offer is ineligible.W912DW27QA0060001.pdf, page 2
Contract period45 calendar days from notice to proceedSection F lists 7 Dec 2026 to 21 Jan 2027, which will be adjusted when notice to proceed is issued.W912DW26QA006.pdf, page 6
How they chooseLowest priced quote rated Acceptable on technical and past performanceBoth factors must be Acceptable before price decides the award.W912DW27QA0060001.pdf, page 3
How to submitEmail the quote to whitny.hart@usace.army.milFaxes are not accepted. The subject line must include RFQ number W912DW27QA006.W912DW27QA0060001.pdf, page 2
Questions due24 hours before closing, by email to Whitny HartCalculated from the closing time: about 10:00 a.m. Pacific on Monday 30 November 2026. Answers are posted as amendments.W912DW27QA0060001.pdf, page 2
Contract typeFirm-fixed-price, five lump-sum line itemsFill in all five Price Schedule lines and a total price.W912DW27QA0060001.pdf, page 16
Site visitTuesday 17 November 2026, 10:00 AM, Pacific Time (passed)Registration closed Thursday 12 November 2026 at 3 p.m. PT. You can no longer attend.Site Visit - MMD Sewage Lagoon.pdf, page 1

How to respond

  1. Confirm your SAM registration is active, and gather your UEI, CAGE code, and taxpayer ID number, which Section L requires with your quote.
  2. Fill in all five lump-sum line items on the Price Schedule with one total, priced at the wage rates in WA20260125 and with no separate tax line on invoices.
  3. Assemble up to three recent projects covering lagoon cleaning and liner repair, plus Lead Seamer certification or three years of HDPE liner experience, and past performance references.
  4. Sign and date the SF 1449, and an SF 30 acknowledging Amendments 0001 and 0002.
  5. Email the complete quote to whitny.hart@usace.army.mil with RFQ number W912DW27QA006 in the subject line before 10:00 a.m. Pacific on Tuesday 1 December 2026. Faxes are not accepted, and quotes must stay valid for 30 days.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated contract value: Not stated.
  • The updated SOW that Amendment 0001 refers to for payment, the final water test, and section 6.6 is not on the attachment list, so you cannot see its wording.
  • The two as-built reference drawings (1974 and 2018) are scanned images that could not be reviewed here. You must read them yourself before pricing.
  • Exact start and end dates for performance, which depend on when notice to proceed is issued.

Notice text

This requirement is for the cleaning, inspection, and repair of the Mud Mountain Dam Sewage Lagoon. A site visit will be offered on 17 November 2026, see attachment for information and registration. Please pay attention to: Section L, Section M, and FAR 52.228-13 in the solicitation. 19 November 2026: Amendment 0001 posted, Site Visit Attendees List posted 23 November 2026: Amendment 0002 posted to extend solicitation

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 24, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy