1. Opportunities
  2. Department of Agriculture
  3. Forest Service
  4. 1240LT27Q0027

Barn roof, siding and lead paint work, New Meadows, ID

You would replace the roof, remove lead paint, install new siding and trim, paint the exterior, and replace about 10 feet of waterline and a hydrant at a barn in New Meadows, Idaho.

Official title: New Meadows Range Barn

Deadline
Nov 28, 5:00 PM MT
3 days left
Who can bid
Small businesses
Size standard for NAICS 237110: $45 million in average annual receipts · Who qualifies
Last time
None found
No contract like it at this agency in USAspending.gov
Place
ID
Buyer: Payette National Forest

What they're buying

Work runs 90 calendar days after a notice to proceed, a metal deck option is priced separately, and the government says it will consider a later start for better weather.

Top catches

Deadline falls on a Saturday
“Response deadline: 2026-11-28T17:00:00-07:00” SAM.gov record

Offers are due Saturday, November 28, 2026 at 17:00 at -07:00, two days after Thanksgiving. Send your quote early, because the amendment did not extend the deadline.

Offers go by email
“derrick.dodson@usda.gov” C04a SF-1442 1240LT27Q0027.pdf, page 1

The SF-1442 gives an email address as the place to send offers, and no other delivery method is listed. Send the signed form and priced schedule by email, and ask the contracting specialist to confirm receipt before the deadline.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 25, 2026 from the notice and 5 of 7 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Remove the existing roofing. Install plywood sheathing, ice and water shield over the entire roof, and new corrugated metal roofing.
  • Abate lead paint on rafter tails, soffit and fascia, then paint them.
  • Remove lead paint siding and felt paper. Install plywood sheathing, building wrap, new siding in kind and new trim in kind. Per the amendment, siding is Douglas Fir #117 double teardrop and trim is 5/4.
  • Replace about 10 feet of 1-inch SIDR 9 HDPE waterline. Move the hydrant 2 feet east, install a new Type E hydrant with a drainage basin, and replace a galvanized barb fitting with a brass one.
  • Paint all exterior surfaces. The colors are in the Section 099001 schedule.
  • Option 1: remove the wood deck and foundation piers, then build a new metal deck with steps on new piers. The amendment says bar grating is the correct material.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Deadline falls on a Saturday. Offers are due Saturday, November 28, 2026 at 17:00 at -07:00, two days after Thanksgiving. Send your quote early, because the amendment did not extend the deadline.
  • Offers go by email. The SF-1442 gives an email address as the place to send offers, and no other delivery method is listed. Send the signed form and priced schedule by email, and ask the contracting specialist to confirm receipt before the deadline.
  • Amendment must be acknowledged. You must acknowledge the amendment before the deadline, either in item 19 of the SF-1442 or by separate letter or email. The notice says an offer may be rejected if the acknowledgement is not received in time.“FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.” 1240LT27Q0027 amendment.pdf, page 1
  • Lead abatement credentials required. A Certified Renovator is not enough for this work. The government says lead workers must hold the correct certifications, and the amendment question cites a firm certification plus 32-hour and 16-hour courses. Confirm your crew's credentials before you bid.“The workers for the lead abatement must have the correct certifications for the lead abatement work.” 1240LT27Q0027 amendment.pdf, page 13
  • Wage rates not in the notice. The notice does not give wage rates. The Adams County, Idaho wage determination was attached but not included in what we could review, so you must read it on SAM.gov before you price labor.“It is not a Wage Determination” C04b 1240LT27Q0027.pdf, page 5
  • Start date may slip. The SF-1442 says you must begin within 15 calendar days after award, but the SOW shows a July 2027 start. The amendment also lists delivery as 09/30/2026, while the SF-1442 says 09/30/2027, so ask the contracting officer for the planned start and completion dates.“The Contractor shall begin performance within” C04a SF-1442 1240LT27Q0027.pdf, page 1

Key terms

Who can bidSmall businesses only (total small business set-aside)NAICS 237110. The notice lists the size standard as $45 with no unit.C04b 1240LT27Q0027.pdf, page 1
Contract period90 calendar days after notice to proceedThe SOW lists a July 2027 start. The government says a later notice to proceed may be issued for better weather.C04c SOW 1240LT27Q0027.pdf, page 3
How they chooseLowest price among technically acceptable quotesTechnical acceptability is pass or fail first. Price is compared only among acceptable quotes.C04b 1240LT27Q0027.pdf, page 17
How to submitEmail to derrick.dodson@usda.govSend the signed SF-1442 offer form and the priced Schedule of Items.C04a SF-1442 1240LT27Q0027.pdf, page 1
Contract typeCommercial construction, priced by lump sum line itemsEach Schedule of Items line is one lump sum unit.C04b 1240LT27Q0027.pdf

How to respond

  1. Complete SF-1442 items 14 to 20: your name and address, a price for every line in the Schedule of Items (Base and Option 1), the number of days your offer stays open (at least 60), and a signature.
  2. Acknowledge the amendment in item 19 of the SF-1442, or by separate letter or email, before the deadline.
  3. Email the package to derrick.dodson@usda.gov by 2026-11-28T17:00:00-07:00. File format: Not stated.
  4. Proof of certifications, insurance or bonds needed with the quote: Not stated. If you win, performance and payment bonds are due within 15 calendar days after award.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated value or budget: Not stated.
  • The Adams County, Idaho wage determination was not included in what we could review. You must read it on SAM.gov.
  • Photos with roof and barn dimensions are cited in the amendment but are not on the attachment list. We could not review them, so check SAM.gov.
  • Notice to proceed date: Not stated. The government says it will consider a later date for better weather.
  • Whether a site visit or pre-bid meeting is required: Not stated.
  • Pages 8 to 16 of the notice PDF were not provided, and the amendment text skips pages 10 and 11. You must read the full documents on SAM.gov.

Notice text

A. This project consists of modifying an existing waterline and replacing a water hydrant, removing an existing wood deck and constructing a new metal deck, replacing the existing roof, abatement of lead-based paint, removing lead-based paint siding, installing new siding, and preparing and painting exterior surfaces of the New Meadows Range Barn located at the New Meadows Barracks administrative site located at 100 S Norris Ave. New Meadows, ID 83654.

B. Base work includes the following described below: 1. Removal of existing roofing, installation of plywood sheathing over the existing skip sheathing, installation of ice/water shield over the entire roof, and installation of new corrugated metal roofing. 2. Abatement of lead-based paint of rafter tails, soffit, & fascia; and painting of aforementioned surfaces. 3. Removal of lead-based paint siding and felt paper, installation of plywood sheathing and building wrap, installation of new siding in-kind, installation of new trim in-kind around the windows, doors, and corners and painting of all aforementioned surfaces.

4. Replacement of approximately 10-feet of existing 1-inch SIDR 9 HDPE waterline including moving the existing hydrant location 2-feet to the east along the side of the building and replacement of the existing hydrant with a new hydrant and drainage basin. Additionally, replacement of an existing galvanized barb fitting with a brass barb fitting is required. C. Optional work includes the following described below: 1. Removal of existing wood decking and foundation piers and fabrication and installation of new expanded metal decking with steps over a metal frame with new foundation piers.

D. Quantities associated with these options are identified in the Schedule of Items

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 25, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Forest Service by email

Each morning we'll send the new solicitations and sources-sought notices from Forest Service, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy