Sewage lagoon liner repair, Mud Mountain Dam, Enumclaw, WA

Clean, inspect and repair the liner of the sewage lagoon at Mud Mountain Dam in Enumclaw, WA, and replace two broken PVC inlet pipes and the chlorinator.

Official title: Mud Mountain Dam Sewage Lagoon Repair

Deadline
Dec 1, 10:00 AM PT
5 days left
Who can bid
Small businesses
Size standard for NAICS 237110: $45 million in average annual receipts · Who qualifies
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Enumclaw, WA
Buyer: W071 Endist Seattle

What they're buying

All work must be complete within 45 calendar days of notice to proceed.

Top catches

Final water test leak repair conflict
“Additional repairs if this test is unsuccessful are not covered under this contract.” W912DW27QA0060001.pdf, page 22

Amendment 0001 says it removed the sentence excluding repairs after a failed final test, and Amendment 0003 says such a leak repair is a formal change, not part of your price. Yet the SOW text in Amendment 0001 still contains that exclusion, so ask the contracting officer which rule applies before you price the job.

Level 3 safety officer is conditional
“HOWEVER the quoter must fully consider all potential risks and plan to” W912DW27QA0060003.pdf, page 4

You may use a competent person instead of a full-time Level 1 safety officer only if every job step rates Medium risk or lower. Approval of your hazard analysis is what allows that, so plan and price for a full-time safety officer if you cannot meet that level.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 8 of 10 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • Clean the lower liner by vacuum truck, removing about 15 cubic yards of gravel and inspecting for leaks.
  • Repair tears, holes and blisters with patches, and replace the inlet pipe boot if it is defective, using a seamer with the required certification.
  • Replace two broken PVC inlet pipes with new schedule 80 PVC, clear the clogged outlet pipe, and paint exposed PVC.
  • Replace the chlorinator with a Sanuril model 100 or equal, plus one 45-pound pail of tablets.
  • Run the required tests, including trial seam tests, vacuum box tests, air lance tests at 50 PSI, and two 24-hour controlled water-hold tests.
  • Submit a work plan, hazard analysis, accident prevention plan and product data before mobilization, plus as-built drawings and a one-year warranty.

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Final water test leak repair conflict. Amendment 0001 says it removed the sentence excluding repairs after a failed final test, and Amendment 0003 says such a leak repair is a formal change, not part of your price. Yet the SOW text in Amendment 0001 still contains that exclusion, so ask the contracting officer which rule applies before you price the job.
  • Level 3 safety officer is conditional. You may use a competent person instead of a full-time Level 1 safety officer only if every job step rates Medium risk or lower. Approval of your hazard analysis is what allows that, so plan and price for a full-time safety officer if you cannot meet that level.
  • Only sewage lagoon cleaning experience counts. Your project examples must show cleaning and sanitizing a sewage lagoon. A stormwater pond job does not count, and a weak example can make your whole quote unacceptable. Check your past projects and any subcontractor's before you bid.“only "cleaning and sanitizing of sewage lagoons" will earn an acceptable rating.” W912DW27QA0060003.pdf, page 2
  • Bond or letter of credit within 10 days. After award you must provide a payment bond or irrevocable letter of credit for 100 percent of the contract price within 10 days. It must cover the performance period plus one year, so confirm your bonding capacity and price its cost before you bid.“The submission of the payment protection is required within 10 days of contract award.” W912DW26QA006.pdf, page 33
  • Davis-Bacon wage classes are your job. The government will not say which wage classes apply to the geomembrane seamer, vacuum truck operator or excavator. Check wage determination WA20260125 yourself and price those rates, because Amendment 0003 leaves that choice to you.“The contractor is responsible for determining which classifications apply and following procedures to ensure compliance with laws concerning Davis Bacon wage rates.” W912DW27QA0060003.pdf, page 4
  • No site visit and unknown sludge depth. You cannot attend the site visit now, and the sludge depth is not given. The government says you must estimate sludge volume from the visit and photos, so allow extra time and cost for cleaning.“Quoters will need to estimate sludge volume themselves using visual inspection from site visit and photos provided with SOW.” W912DW27QA0060003.pdf, page 4

Key terms

Who can bidSmall businesses only (100% set aside)NAICS 237110, size standard USD 45,000,000.00. You must be registered in SAM.W912DW26QA006.pdf, page 57
Contract periodWithin 45 calendar days of notice to proceed (NTP)Section F shows 07 Dec 2026 to 21 Jan 2027, but the government says those dates will be adjusted when NTP is issued.W912DW26QA006.pdf, page 9
How they chooseLowest price among quotes rated Acceptable on both Technical and Past PerformanceTechnical is rated Acceptable or Unacceptable. A quoter with no past performance record is rated Neutral, which counts as Acceptable.W912DW27QA0060003.pdf, page 7
How to submitEmail to whitny.hart@usace.army.mil with RFQ number W912DW27QA006 in the subject lineFaxed quotes are not accepted. Quotes must be valid for 30 days.W912DW26QA006.pdf, page 57
Questions dueNo later than 24 hours before closing, by email to Whitny HartIf closing stays at 10:00 a.m. on 1 December, this is about 30 November at 10:00 a.m. (inferred).W912DW26QA006.pdf, page 57
Contract typeFirm-fixed-price, job-based, five lump-sum items (CLIN 0001 to 0005)Progress payments monthly with retainage under FAR 52.232-5, per Amendment 0001.W912DW27QA0060003.pdf, page 7
Site visitVisit was 17 November 2026. Registration closed 12 November 2026.The attendee list was posted, but no official notes were issued. You cannot attend now.Notice text

How to respond

  1. Email your signed quote to whitny.hart@usace.army.mil before 10:00 a.m. on 1 December 2026. Faxed quotes are not accepted.
  2. Put the RFQ number W912DW27QA006 in the email subject line, or the quote may not be accepted.
  3. Include a signed and dated SF 1449, a signed SF 30 for each amendment (0001, 0002 and 0003), and the contractor information block with tax ID, UEI, CAGE code and remit-to address.
  4. Price all five CLINs (0001 to 0005) as a firm fixed price, state the total, and include three project examples and the lead seamer's certification or three years of documented experience.
  5. Keep your price valid for 30 days after the quote is submitted.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Estimated value of the contract: not stated.
  • Content of pages 40 to 48 of the base solicitation, which were not provided; you must read them on SAM.gov.
  • Content of the two reference as-built drawings (1974 and 2018): they are scanned and we could not review them, so you must read them on SAM.gov.
  • Whether the government now moves and disconnects the aerator, as Amendment 0003 says; the updated SOW it refers to was not provided.
  • The final period of performance dates, which the government says will be set when notice to proceed is issued.
  • Name and contact details of the government representative and quality assurance inspector, which the SOW says will come with the award.

Notice text

This requirement is for the cleaning, inspection, and repair of the Mud Mountain Dam Sewage Lagoon. A site visit will be offered on 17 November 2026, see attachment for information and registration. Please pay attention to: Section L, Section M, and FAR 52.228-13 in the solicitation. 19 November 2026: Amendment 0001 posted, Site Visit Attendees List posted 23 November 2026: Amendment 0002 posted to extend solicitation 25 November 2026: Amendment 0003 posted to respond to questions.

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 26, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Department of the Army by email

Each morning we'll send the new solicitations and sources-sought notices from Department of the Army, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy