Water, sewer and power rehab at Grand Canyon North Rim, AZ

The National Park Service wants a contractor to rehabilitate water and power systems on the North Rim and at Roaring Springs in Grand Canyon National Park, Arizona, with sewer work and two power lines priced as options.

Official title: Y--GRCA 318719 North Rim & Springs Rehabilitation Pro

Deadline
Jan 8, 2027, 12:00 PM MT
43 days left
Who can bid
Not stated
The notice names no set-aside
Last time
None found
No contract like it at this agency in USAspending.gov
Place
Not stated
Buyer: National Park Service Contracting Activity

What they're buying

The work includes about 9,350 linear feet of drilled water pipe, a new water treatment plant and a pumphouse rebuild, to be finished within 1,095 calendar days after notice to proceed; offers are due Friday, January 8, 2027.

Top catches

Two different end dates
“March 1, 2027, through February 28, 2030.” Sol_140PP027R0005_Amd_0001.pdf, page 2

The solicitation's continuation sheet shows an end date of 03/31/2031, and Amendment 0001 changes it to 02/28/2030. The Q&A says 1,095 days after notice to proceed controls and the dates are for planning only, so build your schedule from notice to proceed and confirm with the contracting officer.

Helicopter-only access inside the canyon
“No mechanized ground transportation is permitted on innercanyon trails.” B08_Attach_01_Specs_Rehabilitate_North_Rim__Vol_A_(Div_01)_20261012.pdf, page 12

All innercanyon crews, materials and equipment move by helicopter or on foot, and you must supply the helicopter operations. The park helibase can stop your work at any time, and helicopter use must wait until a separate waterline project finishes, expected in summer 2027.

4 more catches below ↓

Read by AI (Claude Haiku) on Nov 26, 2026 from the notice and 11 of 54 attached files. Every quote on this page was found word for word in the source. Check the official notice before you bid.

The work

  • About 9,350 linear feet each of 4.5-inch raw water and finished water pipe, installed in two directionally drilled bores (Volume 02, base CLIN 0020).
  • New 6,200 square foot North Rim water treatment plant with membrane ultrafiltration, plus two new raw water tanks (Volume 06, base CLIN 0060).
  • Rebuild of the Roaring Springs Pumphouse with new pumps, strainers, a hypochlorite system and interior demolition (Volume 05, base CLIN 0050).
  • Replace about 11,622 linear feet of sanitary sewer pipe and 46 manholes on the North Rim (Volume 08, option CLIN 0080).
  • About 5,325 linear feet of new overhead power line on steel poles, and about 3,600 linear feet of buried armored power cable (Volume 10 base CLIN 0100; Volume 11 option CLIN 0110).
  • All innercanyon helicopter operations, plus North Rim power distribution work including a 750 kVA standby generator (Volume 09, base CLIN 0090).

Who did it before

No match in USAspending.gov: no contract at this agency for the same kind of work ends within a year either way.

What to watch for

  • Two different end dates. The solicitation's continuation sheet shows an end date of 03/31/2031, and Amendment 0001 changes it to 02/28/2030. The Q&A says 1,095 days after notice to proceed controls and the dates are for planning only, so build your schedule from notice to proceed and confirm with the contracting officer.
  • Helicopter-only access inside the canyon. All innercanyon crews, materials and equipment move by helicopter or on foot, and you must supply the helicopter operations. The park helibase can stop your work at any time, and helicopter use must wait until a separate waterline project finishes, expected in summer 2027.
  • Hourly event lines paid only after approval. Lines 0020.6 to 0020.11 pay by the hour for events such as intersecting a void while drilling. Paid time starts only after the contracting officer rules the event eligible, so you may carry crew and drilling costs before you are paid.“Event based CLINs (0020.6 to 0020.11) require prior Contracting Officer (CO) eligibility determination.” B08_Attach_04_CLIN_Price_Sheet_-_Services.xlsx
  • Performance and payment bonds after award. The form marks performance and payment bonds as required, with a count of 10 calendar days after award. Ask your surety now whether it can bond a job of this size, and check whether an offer guarantee applies, because the text does not show which box is marked.“THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?” Sol_140PP027R0005.pdf, page 1
  • Named brands with conflicting substitution rules. Division 01 says the named brands are sole-sourced and no substitutions are allowed. Divisions 26 to 46 say the Contracting Officer will consider equivalent products. Ask in writing which rule applies before you price the named equipment.“No product substitutions will be allowed.” B08_Attach_01_Specs_Rehabilitate_North_Rim__Vol_A_(Div_01)_20261012.pdf, page 12
  • Funding status conflicts. The original notice calls this an unfunded requirement, but Amendment 0001 says it is fully funded. Treat award as more likely now, and ask the contracting officer to confirm before you commit heavy bid costs.“This requirement is fully funded.” Sol_140PP027R0005_Amd_0001.pdf, page 2

Key terms

Who can bidFull and open competition; no set-aside statedThe size standard is in Section K, which was not in the text we received.Sol_140PP027R0005.pdf, page 1
Contract period1,095 calendar days from notice to proceedStart within 15 days of notice. End dates conflict; see catches.Sol_140PP027R0005.pdf, page 3
How to submitSealed offer, original plus 1 copy, to the Denver, CO addressElectronic submission is mentioned in the Q&A, but the method is not stated.Sol_140PP027R0005.pdf, page 1
Questions dueFriday, December 11, 2026, 1:00 PM MTAnswers come as SAM.gov amendments, and more rounds may follow.B09_Amendment_01_Answers_to_Questions_0001.pdf, page 3
Estimated valueMore than $10M (magnitude of construction)No dollar estimate or total appears in the text we received.Sol_140PP027R0005.pdf, page 1
Contract typeConstruction, with lump-sum and unit-priced linesSingle prime contract. Some lines are paid by the hour after approval.Sol_140PP027R0005.pdf, page 1
Site visitPre-proposal site visit referencedThe rules are in Section L, which was not provided. Whether it is mandatory is not stated.Sol_140PP027R0005.pdf, page 1

How to respond

  1. Send the original and one sealed copy of your offer to NPS ConOps DSC Central, 1 Denver Federal Center, Building 8, P.O. Box 25287, Denver CO 80225-0287.
  2. Mark the outside of the envelope with your name and address, solicitation number 140PP027R0005, and the date and time offers are due.
  3. Deliver by Friday, January 8, 2027, 12:00 PM (-07:00). Rules for late offers: Not stated.
  4. Prepare Volume I (factor narratives, past performance, and a Management Approach narrative of five pages or less) and Volume II (the CLIN price sheet). How to send electronic copies: Not stated.
  5. Fill in the offer form, acknowledge Amendment 0001 on it, and price every base and option line, since the price sheet says an incomplete offer may be unacceptable.

Attached files

From SAM.gov. Download links open the original files.

Not stated in what we read

  • Wage determination (B08_Attach_03_Wage_Determintation.pdf) could not be reviewed. You must read it yourself before you price labor.
  • Section L (proposal rules, evaluation factors, site visit requirements) and Section H were not in the text we received.
  • Whether a bid or offer guarantee is required. Item 13b on the form shows both choices.
  • Liquidated damages amount and payment terms. The amendment changes only a clause reference.
  • Award method (lowest price, best value, or sealed bid versus negotiated proposal). The text does not make this clear.
  • Whether the Government furnishes any materials. The Government-Furnished Materials section was not in the text we received.

Notice text

GRCA 318719 North Rim & Roaring Springs Rehabilitation Program

As published on SAM.gov.

Contacts

As listed in the notice. Ask questions in writing and before the questions deadline, if the notice sets one.

History

  • Nov 26, 2026: first seen in the SAM.gov extract

SAM.gov shows only the latest version of a notice. FedLook keeps a copy of each day's notices and records what changed.

Free · at most one email a morning

Get new notices from Departmental Offices by email

Each morning we'll send the new solicitations and sources-sought notices from Departmental Offices, with deadlines and set-asides up front. Free. Unsubscribe in one click.

The morning edition by email: free, at most one email a morning, unsubscribe in one click. We use your address for nothing else and never share it. Privacy